UKSC Chicksands River Flit
Dear Ministry of Defence,
It stands to reason that the MoD is responsible for the maintenance of the portion of the River Flit within the bounds of the UKSC Chicksands site. Please may I request:
The date on which this portion was last cleared or dredged of silt
The current assessment of the condition and/or safety of any bridges/dams/weirs etc along this portion
Yours faithfully,
Simon Richards
Good Afternoon
Your request has been logged under our reference 2024/11696 and the target
date for response is 26/07/2024.
Yours sincerely
DIO Secretariat
Good afternoon,
Please find attached the response to your correspondence of 27 June 2024.
Kind regards,
Defence Infrastructure Organisation
Secretariat Parliamentary Team
Dear DIO Sec-Parli (MULTIUSER),
Many thanks for your response. In order to best fully answer my original question regarding the present condition of these structures (noting the dates on these reports puts them at a few years old), could you please clarify:
Which recommended works outlined in the reports, if any, have been conducted?
Where recommended works have not been conducted, please provide an explanation.
Yours sincerely,
Simon Richards
Good Afternoon
Your request has been logged under our reference 2024/13934 and the target
date for response is 27/08/2024.
Yours sincerely
DIO Secretariat
Good afternoon,
Please find the response to your correspondence of 27 July 2024.
Kind regards,
Defence Infrastructure Organisation
Secretariat Parliamentary Team
We work to defend the right to FOI for everyone
Help us protect your right to hold public authorities to account. Donate and support our work.
Donate Now