Technical review content of the Hydraulic Fracture Plan PNRz1.

richard parker made this Freedom of Information request to Oil and Gas Authority

This request has been closed to new correspondence from the public body. Contact us if you think it ought be re-opened.

The request was successful.

Dear Oil and Gas Authority,

Please advise as to why no signatory appear on either the hydraulic plan 'pnrz1 hydraulic fracture plan' or the technically sparse approving review 'PO3 Approval compliance acceptance report 020718'.

Please confirm or otherwise, that two separate, identified and qualified 'senior geophysicists' cited as originators of the plan by Cuadrilla have been recorded.

Could you please publish or indicate the whereabouts of the full recorded technical review details of the hydraulic plan for the public to peruse. There is no evidence of any review of the detailed technical aspects of the geology interpretation by Cuadrilla, traffic light seismic monitoring scheme and the envisaged frack stage progression in the compliance acceptance report

Similarly could you please confirm that the individuals that have reviewed and authorised the hydraulic plan have been recorded.

Yours faithfully,

richard parker

Dear Oil and Gas Authority,

Please advise as to the progress of the request.

Yours faithfully,

richard parker

OGA FOI requests, Oil and Gas Authority

2 Attachments

Dear Mr Parker,

Please find attached a response from the OGA to your FOI request.

Yours sincerely

FOI Requests

Oil and Gas Authority is a limited company registered in England and Wales with registered number 09666504 and VAT registered number 249433979. Our registered office is at 21 Bloomsbury Street, London, United Kingdom, WC1B 3HF. For information about how we process data and monitor communications please see our Privacy Statement and for terms of use please see our Terms and Conditions, both available on our website.