Dear City of York Council,

In April 2022 Mr Ferris made an urgent delegated ( according to him) decision to spend £400k on ‘the carriageway’ (private land) at Springfield Close. This was a dead end, there was no road but in view of his asserted powers he used urgency principles to agree this.

https://democracy.york.gov.uk/ieDecision...

As this land other than a narrow footway was all owned and under the control of a private land owner with frontagers and the Foss drainage board all involved please provide the following:

1. An excel sheet of all costs to date over the last 3 financial years to include but not limited to all remedial works, construction, surveys, design and legal costs. Staffing costs, by department, including legal and which of those if any were capitalised.
2. Any contractural commitments including costs committed to as at the start of FY 23/4 but not paid out
3. Provide all recorded information on measures taken to extract funding from Frontagers, Foss Drainage Board and the Land owner
4. All legal agreements to enter in on private lane.
5. The legal status of the highway and culvert you have now built at taxpayers expense, and all limitations regarding usage, weight limits and legal liabilities including for health and safety of the road users.

Yours faithfully,

Gwen Swinburn

Information Governance - CYC, City of York Council

1 Attachment

Thank you for your email.  Please note this is an automatically generated
receipt to let you know we have received your email.

 

For information:

 

·        The timescale for responding to Freedom of Information Act (FOIA)
and Environmental Information Regulation (EIR) requests is up to 20
working days. We will contact you promptly if we need you to clarify your
request or an extension to complete a public interest test.

 

·        The timescale for responding to requests for a review, for FOIA
or EIR responses, is up to 20 working days. You are also able to contact
the Information Commissioner Office (ICO) contact details below:

 

·        The timescale for responding to your rights in relation to
personal data eg: subject access to records (SAR) request, is up to 1
month. We will contact you promptly if we require further information from
you, or an extension.

 

·        The timescale for responding to requests for a review, of
responses to your rights regarding personal data, is up to 1 month. You
are also able to contact the ICO, contact details below:

 

·        If after we complete our investigation and reply to you with our
findings, you still remain dissatisfied you can contact the ICO:

 

Phone:  0303 123 1113 or via their [1]live chat. Their normal opening
hours are Monday to Friday between 9am and 5pm (excluding bank holidays). 
You can also report, enquire, register and raise complaints with the ICO
using their web form on [2]Contact us | ICO

·        You can find more information about how we deal with Freedom of
Information Requests at:

 

[3]Make a freedom of information request – City of York Council

 

·        You can find the Corporate Governance Team Privacy Notice at:

 

[4]https://www.york.gov.uk/privacy/Corporat...

 

Regards

 

Corporate Governance Team

 

 

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
* * * * * * * * *
Help protect the environment! please don't print this email unless you
really need to.

show quoted sections

Information Governance - CYC, City of York Council

2 Attachments

Dear Ms Swinburn

 

Please see below the response to your enquiry under the Freedom of
Information Act (FOIA). Please accept the councils sincere apologies for
the delay in responding.

 

1.    An excel sheet of all costs to date over the last 3 financial years
to include but not limited to all remedial works, construction, surveys,
design and legal costs. Staffing costs, by department, including legal and
which of those if any were capitalised.

 

Please see below the costs that have been charged to Springfield Close
since 1^st April 2020 and provide up to 30th September:

 

 

 

2.    Any contractual commitments including costs committed to as at the
start of FY 23/4 but not paid out

 

     Retention payment due to the contractor £5534.06  plus VAT due March
2024

WSP Invoice no 64639165 for Aug 2023 valued at £1075.51+VAT has not yet
been paid

 

3.    Provide all recorded information on measures taken to extract
funding from Frontagers, Foss Drainage Board and the Land owner

 

This has previously been answered in response CGT10953 therefore it is
exempt from disclosure under section 21 of the FOIA as it is already
accessible by other means

 

4.    All legal agreements to enter in on private lane.

 

This information is exempt from disclosure under section 21 of the FOIA as
it has already been provided to you in a previous response. See CGT10953

 

5.    The legal status of the highway and culvert  you have now built at
taxpayers expense, and all limitations regarding usage, weight limits and
legal liabilities including for health and safety of the road users.

 

The adopted highway boundary has not changed following the works. The
footway remains adopted highway. The rest is a privately maintained
street. There are no weight limits in place.

 

 

If you are dissatisfied with our response you have the right to ask for an
independent review of how your enquiry was handled and responded to. This
can be done by contacting us at [1][City of York Council request email]
within 40 working days of receiving your response, stating your reason(s)
why you are dissatisfied.

 

If you remain dissatisfied following the internal review response you can
contact the Information Commissioner, contact details below:

 

Phone:  0303 123 1113 or via their [2]live chat. Their normal opening
hours are Monday to Friday between 9am and 5pm (excluding bank holidays). 
You can also report, enquire, register and raise complaints with the ICO
using their web form on [3]Contact us | ICO

 

Kind regards,

 

Information Governance Advisor.
t: 01904 554145 | e: [4][City of York Council request email]

 

City of York Council  |  Corporate Governance Team

West Offices  | Station Rise | York YO1 6GA

[5]www.york.gov.uk | [6]facebook.com/cityofyork | [7]@CityofYork

 

 

You can find information about how the Corporate Governance Team uses your
personal information at

 

[8]https://www.york.gov.uk/privacy/Corporat...

 

 

 

 

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
* * * * * * * * *
Help protect the environment! please don't print this email unless you
really need to.

show quoted sections

We don't know whether the most recent response to this request contains information or not – if you are Gwen Swinburn please sign in and let everyone know.