Silvertown Tunnel reports

The request was successful.

Dear Transport for London,

Please could you send me the following reports:

Atkins (April, 2013) Silvertown Tunnel: Highway Infrastructure Conceptual Design Recommendations

Atkins (May, 2012) TfL Silvertown Crossing: Highway Options and Feasibility Design

Atkins (October, 2012) TfL Crossing: Highway Options and Feasibility Design

Hyder Consulting (November 2013) River Crossings, Silvertown Tunnel Options Study Report

Mott Macdonald (December, 2009) New Thames River Crossing: Greenwich to Silvertown – Highways (Alignment and Interfaces)

Mott Macdonald (February, 2012) Silvertown Crossing Study: Tunnel Engineering Mott Macdonald (July 2013) Silvertown Tunnel Further Development of Tunnel Engineering 298348/MNC/TUN/002

Mott Macdonald (May, 2010) New Thames River Crossing: Network Development and Forecasting Report

Mott Macdonald (May, 2013) TfL River Crossings – Ground Investigation Desk Study Preliminary Sources Study Report

TfL (July, 2012) TfL River Crossings Package Report to the Mayor on 2012 Informal Consultation

Yours faithfully,

Darryl Chamberlain

FOI, Transport for London

Dear Mr Chamberlain

TfL Ref: 1034-1415

Thank you for your email received by Transport for London (TfL) on 26 September 2014.

Your request will be processed in accordance with the requirements of the Environmental Information Regulations and TfL’s information access policy.

A response will be provided to you by 24 October 2014.

In the meantime, if you would like to discuss this matter further, please do not hesitate to contact me.

Yours sincerely

Jasmine Howard
FOI Case Officer
FOI Case Management Team
General Counsel
Transport for London

show quoted sections

FOI, Transport for London

1 Attachment

Dear Mr Chamberlain

 

Our Ref: 1034-1415

 

Thank you again for your email received by TfL on 26 September 2014. You
have asked for various Silvertown tunnel reports. Your request is being
considered under the terms of the Environmental Information Regulations
(EIRs).

 

Unfortunately because of its complexity, we have been unable to resolve
your request within the initial statutory 20 working day deadline. This is
because of the volume of information you have requested.

 

To enable us to fully consider your request, in accordance with the EIRs
we have had to extend the deadline for providing a response to 40 working
days from the date we received your request. The amended date for a final
response is now 21 November 2014. We are working hard to ensure that you
receive a response before this date. 

 

I apologise for the delay and any inconvenience this may cause you. If you
have any queries or would like to discuss your request, please do not
hesitate to contact me.   

 

If you are not satisfied with this response, please read the attached
help-sheet entitled ‘Your Right to Appeal’

 

Yours sincerely

 

 

Jasmine Howard

FOI Case Officer

FOI Case Management Team

General Counsel

Transport for London

 

 

 

 

show quoted sections

FOI, Transport for London

1 Attachment

Dear Mr Chamberlain

 

TfL Ref: 1034-1415

 

Thank you for your email received by us on 26 September 2014 asking for
information about the Silvertown Tunnel reports.

Your request has been considered in accordance with the requirements of
the Environmental Information Regulations (EIR) and our information access
policy. 

 

Because we are in the process of finalising our response, we have not been
able to resolve your request within the statutory 40 working days.

 

We intend to provide you with a full response as soon as possible. Please
accept my apologies for this delay.

 

In the meantime, if you have any queries relating to your request, please
do not hesitate to contact me.

 

Please see the attached information sheet for details of your right to
appeal.

 

Yours sincerely

 

 

Jasmine Howard

FOI Case Officer

FOI Case Management Team

General Counsel

Transport for London

 

 

 

 

 

show quoted sections

FOI, Transport for London

1 Attachment

Dear Mr Chamberlain

TfL Ref: 1034-1415

Further to my previous emails in relation to your Environmental
Information Regulations request, this is the third and final email
providing the remainder of the Silvertown Tunnel project reports.

If this is not the information you are looking for, or if you are unable
to access it for any reason, please do not hesitate to contact me.

Yours sincerely

 

Jasmine Howard

FOI Case Officer

FOI Case Management Team

General Counsel

Transport for London

 

 

 

show quoted sections

FOI, Transport for London

2 Attachments

Dear Mr Chamberlain

TfL Ref: 1034-1415

Further to my previous email in response to your Environmental Information
Regulations request; please find attached two further files regarding the
Silvertown Tunnel reports.

Yours sincerely

 

Jasmine Howard

FOI Case Officer

FOI Case Management Team

General Counsel

Transport for London

 

 

 

show quoted sections

FOI, Transport for London

2 Attachments

Dear Mr Chamberlain

TfL Ref: 1034-1415

Thank you for your email received by us on 26 September 2014 asking for
information about the Silvertown Tunnel reports. Please accept my
apologies for the delay in responding.

 

Your request has been considered in accordance with the requirements of
the Environmental Information Regulations and our information access
policy.  I can confirm that we hold the information you require.

 

The reports you requested are available on our website at
[1]https://www.tfl.gov.u
k/corporate/publications-and-reports/silvertown-tunnel with the exception
of the following:

Atkins (May, 2012) TfL Silvertown Crossing: Highway Options and
Feasibility Design 

 

Atkins (October, 2012) TfL Crossing: Highway Options and Feasibility
Design

Mott Macdonald (December, 2009) New Thames River Crossing: Greenwich to
Silvertown – Highways (Alignment and Interfaces)

These three reports have been superseded and summarised by the Highway
Infrastructure Conceptual Design Recommendations Report, April 2013 which
is available via the aforementioned link.

Mott Macdonald (May, 2010) New Thames River Crossing: Network Development
and Forecasting Report has been superseded by the Silvertown Tunnel
traffic Forecasting Report, October 2014 and Base Year Development and
Validation Report February 2014, which is again available via the
aforementioned link.

The original reports are attached; please note that due to the size of
these attachments, we will need to send them in more than one email.

 

If this is not the information you are looking for, or if you are unable
to access it for any reason, please do not hesitate to contact me.

Please see the attached information sheet for details of your right to
appeal as well as information on copyright and what to do if you would
like to re-use any of the information we have disclosed.

 

Yours sincerely

 

 

Jasmine Howard

FOI Case Officer

FOI Case Management Team

General Counsel

Transport for London

 

 

 

 

 

 

show quoted sections