Reasons for termination of Breyer Group Plc contract
Dear Tower Hamlets Homes Limited,
Breyer Group Plc carried out works for THHL under a contract known as Tower Hamlets Homes EWI & External Works between 2014 and 2016. Please confirm whether this contract was completed, or whether it was terminated by THHL prior to completion, and if so, please advise the reasons for termination.
Yours faithfully,
Chris Peskett
Information request
Our reference: 10629665
--------------------------------------------------------------------------
Dear Mr Peskett
Freedom of Information Act 2000
Thank you for your request for information that was received on 22
December 2017 requesting:
[FOI #453676 email]]
Sent: 22 December 2017 10:12
Reasons for termination of Breyer Group Plc contract
Dear Tower Hamlets Homes Limited,
Breyer Group Plc carried out works for THHL under a contract known as
Tower Hamlets Homes EWI & External Works between 2014 and 2016. Please
confirm whether this contract was completed, or whether it was terminated
by THHL prior to completion, and if so, please advise the reasons for
termination.
Please note that in some cases publication of requests and responses will
be delayed.
We are dealing with your request under the Freedom of Information Act
2000 and we aim to send a response by 24 January 2018.
In some case, a fee may be payable. If we decide a fee is payable, we will
send you a fee notice and we will require you to pay the fee before
proceeding with your request.
The Freedom of Information Act 2000 may restrict the release of some or
all of the information you have requested. We will carry out an assessment
and if any exemptions apply to some or all of the information then we
might not provide that information to you. We will inform you if this is
the case and advise you of your rights to request an internal review and
to complain to the Information Commissioner's Office.
We will also advise you if we cannot provide you with the information
requested for any other reason together with the reason(s) why and details
of how you may appeal (if appropriate).
Yours sincerely
Jane Jones
Admin Officer
Legal Services
020 7364 4736
[email address]
NOTE: Please do not edit the subject line when replying to this email.
Information request
Our reference: 10629665
--------------------------------------------------------------------------
Dear Mr Peskett
Your request for information has been considered under the requirements of
the Freedom of Information Act 2000.
I can confirm that the information requested is held by Tower Hamlets
Council and is attached to this email.
The information has also been put on the [1]Council's Disclosure Log,
where you can also search for information supplied on other topics.
The Council’s website www.towerhamlets.gov.uk contains a section on the
Freedom of Information Act that lists other publications readily available
from the Council under its Publication Scheme.
Conditions for the re-use of information where the copyright is owned by
the London Borough of Tower Hamlets can be found on our website.
If you are dissatisfied with the handling of your request, you have the
right to ask for an internal review. Internal review requests should be
submitted within two months of the date of receipt of the response to your
original letter and should be addressed to:
Complaints and Information
Town Hall
Mulberry Place
5 Clove Crescent
E14 2BG
icw[Tower Hamlets Homes Limited request email]
If you are still dissatisfied with the Council’s response after the
internal review you have a right of appeal to the Information Commissioner
at:
The Information Commissioner's Office
Wycliffe House
Water Lane
Wilmslow
Cheshire SK9 5AF.
Telephone: 01625 545 700
Website: www.ico.gov.uk
Yours sincerely
Jane Jones
Admin Officer
Legal Services
020 7364 4736
[email address]
References
Visible links
1. https://towerhamletsportal.icasework.com...
We work to defend the right to FOI for everyone
Help us protect your right to hold public authorities to account. Donate and support our work.
Donate Now