Railway Bridge Marple Station

The request was successful.

Dear Stockport Metropolitan Borough Council

Please can you provide the documentation and consultation papers used to inform the community that the foot bridge at Marple station was to be relocated Would you please also provide the steps taken to inform the public prior to a decision to remove was agreed to

Yours faithfully,

Paula Smith

FOI Officer, Stockport Metropolitan Borough Council

Dear Ms White,

Thank you for your request for information, which has been given reference FOI 5561. Please quote this on any correspondence regarding your request.

Stockport Council will respond to your request within 20 working days. If there will be a charge for disbursements e.g. photocopying in order to provide the information, we will inform you as soon as possible to see if you wish to proceed; however such charges are usually waived if they amount to less than £10.

Yours sincerely,

Corporate Information Services

Confidentiality: This email, its contents and any attachments are intended only for the above named. As the email may contain confidential or legally privileged information, if you are not, or suspect that you are not, the above named or the person responsible for delivery of the message to the above named, please delete or destroy the email and any attachments immediately and inform the sender of the error.

show quoted sections

FOI Officer, Stockport Metropolitan Borough Council

1 Attachment

Dear Ms Smith,

I am writing in response to your request for information (ref FOI 5561) regarding Marple Station footbridge.

The information has been prepared by the relevant Council service and is as follows.

The application to which this request relates is unfortunately not one which would be subject to neighbour notification and wider publicity by the Local Planning Authority. The footbridge at Marple Station is a Network Rail structure and not one the Council has responsibility for. Hence Engineering Services have never carried out any consultation.

Within the planning system Network Rail benefit from extensive rights that allow them to undertake works without the need for full planning permission. In this respect Network Rail already benefitted from the principle for the removal and replacement of the footbridge by virtue of existing planning legislation. As such the application dealt with by the Local Planning Authority was purely restricted to consideration of the siting and appearance of the replacement footbridge. A copy is attached for your information.

Unfortunately I am not aware if Network Rail discussed their intentions with the local community in advance of carrying out any works.

If you are unhappy with the way we have handled your request for information, you are entitled to ask for an internal review; however you must do so within 40 working days of the date of this response. Any internal review will be carried out by a senior member of staff who was not involved with your original request. To ask for an internal review, contact [email address] in the first instance.

If you are unhappy with the outcome of any internal review, you are entitled to complain to the Information Commissioner. To do so, contact:

Information Commissioner’s Office
Wycliffe House
Water Lane
Wilmslow
Cheshire
SK9 5AF

www.ico.gov.uk

01625 545 745

Yours sincerely

Corporate Information Service
Stockport Council

Confidentiality: This email, its contents and any attachments are intended only for the above named. As the email may contain confidential or legally privileged information, if you are not, or suspect that you are not, the above named or the person responsible for delivery of the message to the above named, please delete or destroy the email and any attachments immediately and inform the sender of the error.