Questions on Truslove House Construction Tendering Process

Sabine Mairey made this Freedom of Information request to Homes for Lambeth This request has been closed to new correspondence. Contact us if you think it should be reopened.

The request was successful.

Dear Homes for Lambeth,

In respect of 2 Roman Rise, Truslove House new build, please advise,

When the construction tendering process for the main contract works (substructure and superstructure) commenced
How may contractors were invited to tender
How many contractors submitted bona fide tenders
When were final construction tenders submitted
When is a main contractor is likely to be appointed
When main construction works are due to commence on site

Yours faithfully,

Sabine Mairey

FOI request,

Thank you for your email. This is an automated email to let you know that
we have received your message, and to inform you what will happen next.

Freedom of Information requests are generally resolved within 20 working
days. If it is not possible to comply fully within the 20 day period, we
will contact you to let you know the reasons for this. Your rights under
the Act remain unaffected at all times.

Because we may have received your email out of regular working hours, or
during a weekend or public holiday, there may be some variation in exactly
when the 20 day period commences. Of course, we remain committed to
responding to all requests in a timely manner and remain available to you
should you require.

You may contact us via this email address which is monitored during
regular working hours.

Warm regards

Homes for Lambeth Information Governance Team

Disclaimer

The information contained in this communication from the sender is
confidential. It is intended solely for use by the recipient and others
authorized to receive it. If you are not the recipient, you are hereby
notified that any disclosure, copying, distribution or taking action in
relation of the contents of this information is strictly prohibited and
may be unlawful.

This email has been scanned for viruses and malware, and may have been
automatically archived by Mimecast, a leader in email security and cyber
resilience. Mimecast integrates email defenses with brand protection,
security awareness training, web security, compliance and other essential
capabilities. Mimecast helps protect large and small organizations from
malicious activity, human error and technology failure; and to lead the
movement toward building a more resilient world. To find out more, visit
our website.

FOI request,

6 Attachments

Dear Sabine,

 

We are currently working on a response to your information request of 22
March 2022, ref: IRN9882451.

 

We have not been able to respond to your enquiry due to the half-term
holidays, which increased the number of staff being off, which reduced
capacity.

 

We apologise for this delay, and we are making all efforts to respond as
quickly as possible. We will provide an answer to your information request
within 10 working days from today. If we cannot respond in this period, we
will contact you again.

 

Yours sincerely,

FOI team

 

 

   ​
  FOI request  
Building ​Thriving ​Communities  
​and ​Better Futures   [1][Homes for Lambeth request email]          
 
  [2]www.homesforlambeth.co.uk
    
Homes for Lambeth, Lambeth Town Hall, 6 Brixton Hill SW2 1RW
Follow us on:  [3]LinkedIn [4]YouTube [5]Facebook [6]Twitter [7][IMG]
         
Disclaimers apply for full details
see [8]https://www.homesforlambeth.co.uk/email-...

From: Sabine Mairey <[FOI #846432 email]>
Sent: 22 March 2022 01:03
To: FOI request <[Homes for Lambeth request email]>
Subject: Freedom of Information request - Questions on Truslove House
Construction Tendering Process

 

Dear Homes for Lambeth,

In respect of 2 Roman Rise, Truslove House new build, please advise,

When the construction tendering process for the main contract works
(substructure and superstructure) commenced
How may contractors were invited to tender
How many contractors submitted bona fide tenders
When were final construction tenders submitted
When is a main contractor is likely to be appointed
When main construction works are due to commence on site

Yours faithfully,

Sabine Mairey

-------------------------------------------------------------------

Please use this email address for all replies to this request:
[9][FOI #846432 email]

Is [10][Homes for Lambeth request email] the wrong address for Freedom of
Information requests to Homes for Lambeth? If so, please contact us using
this form:
[11]https://www.whatdotheyknow.com/change_re...

Disclaimer: This message and any reply that you make will be published on
the internet. Our privacy and copyright policies:
[12]https://www.whatdotheyknow.com/help/offi...

For more detailed guidance on safely disclosing information, read the
latest advice from the ICO:
[13]https://www.whatdotheyknow.com/help/ico-...

Please note that in some cases publication of requests and responses will
be delayed.

If you find this service useful as an FOI officer, please ask your web
manager to link to us from your organisation's FOI page.

show quoted sections

Sabine Mairey left an annotation ()

This has been answered elsewhere by Lambeth Council