Property take Summary
Dear High Speed Two (HS2) Limited,
Please can you give me an updated figures on below :-
1) How much has been spent to date on property?
2) What are the committed property liabilities to date?
3) What are the estimated further property costs?
4) How many parcels of land (not including subsoil in tunnelling locations) required
for the construction of phase one where purchase has been completed?
5) How many parcels of land (not including subsoil in tunnelling locations) on the
route of phase one which HS2 Ltd has taken temporary possession of?”
Yours faithfully,
Mike Haville
Dear Mike Haville
Thank you for your email to HS2 Ltd. We are considering your request under
the Freedom of information Act 2000 and aim to reply as soon as possible
and no later than 05 May 2022.
Your reference number for this request is FOI 22-4609.
Regards
Briefings, Correspondence and Freedom of Information (BCFOI) advisor | HS2
Ltd
Tel: 08081 434 434 (Freephone number)|[1][HS2 request email]|
[2]Facebook | [3]Twitter | [4]LinkedIn
High Speed Two (HS2) Limited , Two Snow Hill, Snow Hill Queensway,
Birmingham, B4 6GA | [5]www.gov.uk/hs2
References
Visible links
1. mailto:[HS2 request email]
2. http://www.facebook.com/HS2ltd
3. http://www.twitter.com/hs2ltd
4. http://www.linkedin.com/company/high-spe...
5. http://www.gov.uk/hs2
Dear Mike Haville
Please see the attached correspondence.
Kind Regards
Briefings, Correspondence and Freedom of Information (BCFOI) advisor | HS2
Ltd
Tel: 08081 434 434 (Freephone number)|[1][HS2 request email]|
[2]Facebook | [3]Twitter | [4]LinkedIn
High Speed Two (HS2) Limited , Two Snow Hill, Snow Hill Queensway,
Birmingham, B4 6GA | [5]www.gov.uk/hs2
References
Visible links
1. mailto:[HS2 request email]
2. http://www.facebook.com/HS2ltd
3. http://www.twitter.com/hs2ltd
4. http://www.linkedin.com/company/high-spe...
5. http://www.gov.uk/hs2
Dear FOI Request,
This FOI is a totally separate request from FOI-22-4582 & only asks for an update of information
that has already been provided in FOI-21-4244.
As you decided to combine, please note that is why I have reapplied with a new FOI for an update on a previously answered FOI that is in no way related to FOI-22-4582 or its internal review.
You cannot deny an FOI on the basis of your previous actions.
Yours sincerely,
Mike Haville
Dear Mike Haville
Please find attached a response to this request for review (FOI-22-4609-R).
Thank you
Briefings, Correspondence and Freedom of Information (BCFOI) Advisor | HS2 Ltd
Carl Bird | Senior Manager Briefings, Correspondence and Freedom of Information (BCFOI) | HS2 Ltd
Tel: 08081 434 434 (Freephone number)| [HS2 request email]| Facebook | Twitter | LinkedIn
High Speed Two (HS2) Limited , Two Snow Hill, Snow Hill Queensway, Birmingham, B4 6GA | www.gov.uk/hs2
We work to defend the right to FOI for everyone
Help us protect your right to hold public authorities to account. Donate and support our work.
Donate Now