Dear The Christie NHS Foundation Trust,

I would be grateful if you could please provide me with the following information on the Trust’s procurement process.

1. How the Trust procures Construction Consultancy Services?

2. If by your own framework, please advise:
a. The titles and content of the relevant frameworks
b. The start and end dates of the frameworks
c. Any possible extension periods to the frameworks
d. The companies appointed under the current frameworks (in relation to Construction Consultancy Services)

3. If there is not framework in place how do the Trust typically procure construction consultancy under and over OJEU value thresholds and if not a Trust procured framework which frameworks do you typically use?

Yours faithfully,

Ms C Barber

Dear Applicant

FOI Request – (Reference J932)

Thank you for your recent Freedom of Information request.

Under the terms of the Freedom of Information Act we expect to respond to your request within 20 working days. We are now investigating the nature of the search and the quantity of information requested, if there is a cost involved in collecting the information then we will suspend the period for response until such time as we receive your payment. We will advise you of any such costs.

In accordance with section 12 of the Freedom of Information Act 2000 where multiple requests for information are received from one person or by different persons who appear to be acting together in a single campaign the estimated cost of complying with any of the requests is to be taken to be the estimated total cost of complying with all of them. To this effect your requests for information will be dealt with under the single reference number above.

There are also a number of exemptions which the Act permits with respect to releasing information. The information will be assessed for these exemptions prior to us releasing the information to you. We will advise you if we are unable to provide the information requested.

Should you have any reservations about how your request was handled or if you feel the information supplied is inadequate, you will have access to our internal review procedure which will be notified to you within the response to your request.

Kind Regards
 
FOI Team
The Christie NHS Foundation Trust
[The Christie Hospital request email]

1 Attachment

Dear Applicant

 

Thank you for your recent FOI request (reference J932).  Please find set
out below the responses to the information you have requested.

 

1.            How the Trust procures Construction Consultancy Services?
Own framework

 

2.            If by your own framework, please advise:

a.            The titles and content of the relevant frameworks

Professional Construction Consultancy Services

                Capital

Lot 1: Project Management

Lot 2: Civil & Structural Engineering

Lot 3: Architectural

Lot 4 Cost Advisor

Lot 5: Mechanical & Electrical Engineering

Lot 6: CDM Co-ordinator

Lot 7: BREEAM

 

Estates & Facilities

Lot 8: Project Management

Lot 9: Civil & Structural Engineering

Lot 10: Architectural

Lot 11 Cost Advisor

Lot 12: Mechanical & Electrical Engineering

Lot 13: CDM Co-ordinator

Lot 14: BREEAM

 

b.            The start and end dates of the frameworks 1^st June 2014 to
31^st May 2017

c.             Any possible extension periods to the frameworks 12 months
to 31^st May 2018

d.            The companies appointed under the current frameworks (in
relation to Construction Consultancy Services) See attached

 

3.            If there is not framework in place how do the Trust
typically procure construction consultancy under and over OJEU value
thresholds and if not a Trust procured framework which frameworks do you
typically use? Not applicable.

 

I do hope you find this information to be helpful.

 

However if you are unhappy with this response please let us know giving
your reasons for believing we have not satisfied the requirements of the
Freedom of Information Act 2000.  An internal review of the response will
then be undertaken and a further response issued to you.  This
correspondence will include details of the Information Commissioner who
you can contact if you remain dissatisfied with our response.

 

It would be greatly appreciated if you could spare a couple of minutes to
complete the following survey, which is monitored to help us improve the
service provided: [1]http://www.surveymonkey.co.uk/r/FOI_Appl...

 

If you have any queries, please get in touch. Please remember to quote the
reference number provided in any future communications.

 