Procurement and Framework Information

Response to this request is long overdue. By law, under all circumstances, Liverpool John Moores University should have responded by now (details). You can complain by requesting an internal review.

Dear Liverpool John Moores University,

I would be grateful if you could please provide me with the following information on the University’s procurement process.

1. How the University procures Construction Consultancy Services?

2. If by your own framework, please advise:
a. The titles and content of the relevant frameworks
b. The start and end dates of the frameworks
c. Any possible extension periods to the frameworks
d. The companies appointed under the current frameworks (in relation to Construction Consultancy Services)

3. If there is not framework in place how do the University typically procure construction consultancy under and over OJEU value thresholds and if not a Trust procured framework which frameworks do you typically use?

Yours faithfully,

Ms C Harrison

foi, Liverpool John Moores University

Dear Ms Harrison

Thank you for your email requesting information under the Freedom of Information Act 2000 (FOIA). The University will respond within the regulatory framework of 20 working days by 6th October 2017.

Please email [Liverpool John Moores University request email] should you have any queries in the meantime.

Kind regards

Secretariat
Liverpool John Moores University
[Liverpool John Moores University request email]

foi, Liverpool John Moores University

2 Attachments

Dear Ms Harrison

Please find attached the University's response to your request below.

Kind regards

Secretariat
Liverpool John Moores University
[Liverpool John Moores University request email]