Pothole costs
To whom it may concern,
Please could you provide -
For - September, October, November, December 2023 and January and February 2024
Number of potholes reported by month
Number of potholes filled by month
Cost of filling potholes by month
How many compensation claims made for potholes by month
Total cost of these claims, by month
How cost of pay outs, by month
What road / pothole had the most individual claims? How many?
What road / pothole incurred the highest value of claims in terms of total cost? How much?
What was the largest individual claim financially - where, when and how much and what for?
How much was spent defending claims?
Please provide data set in an excel or CSV format.
Yours faithfully,
L Elvin
Dear Sir / Madam
I am pleased to acknowledge your request for information, which has been
allocated the reference number NELC/30602/2324.
Your request has been passed to the relevant department and you can expect
your response within the 20 working day limit. If it will take us longer
than 20 working days to respond to you, we will inform you of this and
provide you with the expected date for receiving a response.
Further information about how we will deal with your Freedom of
Information requests is available on our website at:
[1]https://www.nelincs.gov.uk/your-council/...
Please feel free to contact me if you require any further information or
assistance quoting the reference number above.
Yours sincerely
North East Lincolnshire Council
Dear Sir / Madam
Thank you for your information request, reference number NELC/30602/2324.
I can confirm that North East Lincolnshire Council holds the following
information:
A pothole is recognised as a road surface defect 40mm or greater in depth
and greater than 300mm in diameter. The table below includes road surface
defects recorded by our highway inspectors during the course of routine
highway safety inspections, as well as those reported by the public and
other agencies.
The Council’s Highway Management database holds records of defects
reported at identified locations. A defect record will include one or more
potholes. The data provided in the table is for the number of defect
records reported / repaired.
Note: Reported defects included within the final 2-3 months of the latest
year above may not be due for repair for up to 3 months, in accordance
with the risk assessment and priority contained in the Council's policy
for Highway Inspection and Maintenance.
These figures will therefore be subject to change in subsequent data
updates.
For - September, October, November, December 2023 and January and February
2024
Number of potholes reported by month.
Number of potholes filled by month.
┌──────────────┬─────────────────────┬────────────────────┐
│ Month │ Reported Total │ Repaired Total │
├──────────────┼─────────────────────┼────────────────────┤
│ Sep-23 │ 56 │ 54 │
├──────────────┼─────────────────────┼────────────────────┤
│ Oct-23 │ 70 │ 64 │
├──────────────┼─────────────────────┼────────────────────┤
│ Nov-23 │ 106 │ 102 │
├──────────────┼─────────────────────┼────────────────────┤
│ Dec-23 │ 105 │ 92 │
├──────────────┼─────────────────────┼────────────────────┤
│ Jan-24 │ 117 │ 64 │
├──────────────┼─────────────────────┼────────────────────┤
│ Feb-24 │ 146 │ 48 │
├──────────────┼─────────────────────┼────────────────────┤
│ Totals: │ 600 │ 424 │
└──────────────┴─────────────────────┴────────────────────┘
Cost of filling potholes by month
This is information not held by North East Lincolnshire Council as this
service is delivered by NELC’s Regeneration Partner Equans as part of the
total contract fee.
How many compensation claims made for potholes by month.
Total cost of these claims, by month
┌─────────────────┬──────────────────┬─────────────────┬─────────────────┐
│ Month │ Number of claims │ Amount sought │ Payouts │
├─────────────────┼──────────────────┼─────────────────┼─────────────────┤
│ Sep-23 │ 0 │ N/A │ N/A │
├─────────────────┼──────────────────┼─────────────────┼─────────────────┤
│ Oct-23 │ 0 │ N/A │ N/A │
├─────────────────┼──────────────────┼─────────────────┼─────────────────┤
│ Nov-23 │ 1 │ £96 │ £0 │
├─────────────────┼──────────────────┼─────────────────┼─────────────────┤
│ Dec-23 │ 7 │ £1395 │ £0 │
├─────────────────┼──────────────────┼─────────────────┼─────────────────┤
│ Jan-24 │ 6 │ £801 │ £0 │
├─────────────────┼──────────────────┼─────────────────┼─────────────────┤
│ Feb-24 │ 4 │ £894 │ £0 │
├─────────────────┼──────────────────┼─────────────────┼─────────────────┤
│ Totals: │ 18 │ £3186 │ £0 │
└─────────────────┴──────────────────┴─────────────────┴─────────────────┘
What road / pothole had the most individual claims? How many?
Moody Lane, Grimsby
4 claims for pothole damage
What road / pothole incurred the highest value of claims in terms of total
cost? How much?
Moody Lane, Grimsby
Total sought for 4 claims of vehicular damage £884.00.
What was the largest individual claim financially - where, when and how
much and what for?
Moody Lane, Grimsby
08/12/2023
£400
Alleged damage to Alloy Wheel and Tyre.
How much was spent defending claims?
In-house and via Insurers so no costs incurred in defending.
If you believe that your request for information has not been handled in
accordance with the Freedom of Information Act, you have the right to
request an internal review by the Council. If you wish to request an
internal review, please write to us detailing the reasons why. Please be
clear about which elements of the Council’s response or handling of the
request you are unhappy with, and would like the Council to address during
the internal review process. If following this you are still dissatisfied
you may contact the Office of the Information Commissioner.