Permitted development
Dear East Devon District Council, application 24/2320/AGR. the council have stated under heading background
the application falls to be considered against the relevant criteria of class E part 6 {forestry developments}this class permits works, including for e
the erection of a building subject to specified restrictions and where they are reasonably necessary for the purposes of forestry{including afforestation} on land used for that purpose. so by law can the council please inform me where the specified restrictions for forestry/afforestion are set out in the gpdo/nppf/ppg
Yours faithfully,
JUSTIN LACEY
[1][IMG]
Dear Mr Lacey
Thank for submitting your Freedom of Information request.
We will respond to your request as quickly as possible, within the 20
working day statutory deadline under the Freedom of Information Act 2000.
For updates on this case, please quote your reference number
FS-Case-667601493.
Yours sincerely,
Information and Complaints Officer
East Devon District Council
[2][East Devon District Council request email]
[3]www.eastdevon.gov.uk
East Devon - an outstanding place
© 2023 East Devon District Council
Follow us on [4]Facebook and [5]Twitter
[6]Subscribe to your East Devon Update for regular news and information
about what’s happening at East Devon District Council. Choose which topics
you’re interested in to get a personalised update.
[7]Email disclaimer
[8][IMG]
References
Visible links
1. https://eastdevon.gov.uk/
2. mailto:[east%20devon%20district%20council%20request%20email]
3. http://www.eastdevon.gov.uk/
4. http://www.facebook.com/eastdevon
5. http://twitter.com/eastdevon
6. https://public.govdelivery.com/accounts/...
7. http://eastdevon.gov.uk/help/email-discl...
8. https://www.eastdevon.gov.uk/parking
Dear East Devon District Council,
I have asked East Devon Council what pacific restrictions are set out for Forestry Permitted Development only and could they be clear where these specific restrictions are in the gPDo/nppf/Ppg
Yours faithfully,
JUSTIN LACEY
[1][IMG]
Dear Mr Lacey,
Thank you for your request for information. Please find the response to
your query below.
Application 24/2320/AGR. the council have stated under heading background
the application falls to be considered against the relevant criteria of
class E part 6 {forestry developments} this class permits works, including
for the erection of a building subject to specified restrictions and where
they are reasonably necessary for the purposes of forestry{including
afforestation} on land used for that purpose.
So by law can the council please inform me where the specified
restrictions for forestry/afforestion are set out in the gpdo/nppf/ppg -
Your request does not fall within the parameters of Freedom of Information
legislation. You are asking an open ended question which we do not have to
answer under FOI.
I hope this information is helpful but, if you feel dissatisfied with the
way we have responded to your request, please contact our Monitoring
Officer, to request an internal review [2][email address].
You can also request a review using [3]our online request form.
You may also approach the Information Commissioner for advice at
[4]www.ico.org.uk.
Yours sincerely,
Information and Complaints Officer
East Devon District Council
[5]www.eastdevon.gov.uk
East Devon - an outstanding place
© 2023 East Devon District Council
Follow us on [6]Facebook and [7]Twitter
[8]Subscribe to your East Devon Update for regular news and information
about what’s happening at East Devon District Council. Choose which topics
you’re interested in to get a personalised update.
[9]Email disclaimer
[10][IMG]
References
Visible links
1. https://eastdevon.gov.uk/
2. mailto:[email%20address]
3. https://eddc-self.achieveservice.com/ser...
4. http://www.ico.org.uk/
5. http://www.eastdevon.gov.uk/
6. http://www.facebook.com/eastdevon
7. http://twitter.com/eastdevon
8. https://public.govdelivery.com/accounts/...
9. http://eastdevon.gov.uk/help/email-discl...
10. https://www.eastdevon.gov.uk/parking
Dear Mr Lacey,
You have requested an internal review of this FOI enquiry however the due
date for response is 3^rd January 2025. We do not include any bank
holidays within the 20 working day timescale permitted for response under
FOI legislation. We have responded to your FOI enquiry today within
deadline and therefore your request for an Internal Review is refused.
Kind regards
Information & Complaints Team
EDDC
From: JUSTIN LACEY <[FOI #1209367 email]>
Sent: Thursday, January 2, 2025 10:07 AM
To: FOI EDDC <[East Devon District Council request email]>
Subject: Internal review of Freedom of Information request - Permitted
development
Dear East Devon District Council,
I have asked East Devon Council what pacific restrictions are set out for
Forestry Permitted Development only and could they be clear where these
specific restrictions are in the gPDo/nppf/Ppg