Parking permits and electric vehicle charging infrastructure statistics in the council

The request was partially successful.

Dear Hackney Borough Council,

Under the Freedom of Information Act, can you please provide the following information on parking permits and electric vehicle charging infrastructure statistics in the council.

Parking Permits - The information is required for last 3 calendar years (2016, 2017, 2018 and 2019 Jan & Feb)
1. Annual number of residents parking permits issued (all types of vehicles)
2. Annual number of residents parking permits for Battery electric vehicles (zero emission vehicles only)
3. Annual number of Business parking permits issued (all types of vehicles)
4. Annual number of Business parking permits for Battery electric vehicles (zero emission vehicles only)

Charging Infrastructure - The information is required for last 3 calendar years (2016, 2017, 2018 and planned for 2019)
1. Total number of public charging locations (excluding taxi only and private charge points like car parks)
2. Total number of public charging points (Multiple points at a single location)
3. 7 kW and below charging points
4. 11 kW charging points
5. 22kW charging points
6. 43 kW and above charging points

Charging Infrastructure - by supplier - The information is required for last 3 calendar years (2016, 2017, 2018, and planned for 2019)
1. Total number of charging points - Supplier 1
2. Total number of charging points - Supplier 2
3. Total number of charging points - Supplier …

Yours faithfully,

Rafique Nadaf

hackney@infreemation.co.uk, Hackney Borough Council

Thank you for your information request.

This is an automated response and acknowledgement. If you have submitted a
request under the Freedom of Information Act (FOIA) or the Environmental
Information Regulations (EIR), we will aim to respond within the statutory
timescale of 20 working days.

hackney@infreemation.co.uk, Hackney Borough Council

Dear Rafique Nadaf 

 

Re: Freedom of Information Request.

Thank you for your request for information under the Freedom of
Information Act 2000. We would like to offer our sincere apologies for the
delay in responding to your enquiry. Your request has been considered and
our response is in bold below.

 

You requested the following: 

Please provide the following information on parking permits and electric
vehicle charging infrastructure statistics in the council.

Parking Permits - The information is required for last 3 calendar years
(2016, 2017, 2018 and 2019 Jan & Feb)
1. Annual number of residents parking permits issued (all types of
vehicles)
2. Annual number of residents parking permits for Battery electric
vehicles (zero emission vehicles only)
3. Annual number of Business parking permits issued (all types of
vehicles)
4. Annual number of Business parking permits for Battery electric vehicles
(zero emission vehicles only)
 

Q1. Year Number of permits  
  2016 21654  
  2017 31293  
  2018 34104  
  2019 8038  
 (Permits dates from 1st Jan 2019 to 25/03/2019)  
       
Q2. Year Number of permits  
  2016 92  
  2017 171  
  2018 197  
  2019 43  
(Permits dates from 1st Jan 2019 to 25/03/2019)
 
 
Q3. Year Number of permits  
  2016 534  
  2017 666  
  2018 636  
  2019 129  
(Permits dates from 1st Jan 2019 to 25/03/2019)  
       
Q4. Year Number of permits  
  2016 17  
  2017 28  
  2018 35  
  2019 8  
           

(Permits dates from 1st Jan 2019 to 25/03/2019)

 

Charging Infrastructure - The information is required for last 3 calendar
years (2016, 2017, 2018 and planned for 2019)
1. Total number of public charging locations (excluding taxi only and
private charge points like car parks)
2. Total number of public charging points (Multiple points at a single
location)
3. 7 kW and below charging points
4. 11 kW charging points
5. 22kW charging points
6. 43 kW and above charging points
 

As of December 31, 2016

6 Rapid charge points in 3 locations. Under ownership of the London
Borough of Hackney. Points are 43kW AC power and 50kW DC power.

Residential / freestanding / rapid chargers overseen by TfL: We do not
hold accurate information for this period in relation to this charging
technology.

 

As of December 31, 2017

6 Rapid charge points in 3 locations. Under ownership of the London
Borough of Hackney. Points are 43kW AC power and 50kW DC power.

Residential / freestanding / rapid chargers installed by TfL: We do not
hold accurate information for this period in relation to this charging
technology.

 

As of December 31, 2018

44 free standing points in 22 locations. Points are 7kw.

6 Rapid charge points in 3 locations. Under ownership of the London
Borough of Hackney. Points are 43kW AC power and 50kW DC power.

6 Rapid charge points in 3 locations on the TfL Road Network (TLRN).

13 Residential Lamp Columns.

 

Planned: As of December 31, 2019

Planned installations: By the following date we intend to have installed
the following additional charge points: -

Up to 59 residential charge points utilising lamp column technology.

Up to 24 free standing charge points. Points are 7kw.

Up to 12 rapid charge points in 6 different locations installed as part of
TfL’s remit.

Charging Infrastructure - by supplier - The information is required for
last 3 calendar years (2016, 2017, 2018, and planned for 2019)
1. Total number of charging points - Supplier 1 
2. Total number of charging points - Supplier 2
3. Total number of charging points - Supplier �

 

As of December 31, 2016

6 Rapid charge points in 3 locations. Under ownership of the London
Borough of Hackney. Service provided by Charge Point Services.

We do not hold accurate information for this period in relation to other
charge points.

 

As of December 31, 2017

6 Rapid charge points in 3 locations. Under ownership of the London
Borough of Hackney. Service provided by Charge Point Services.

We do not hold accurate information for this period in relation to other
charge points.

 

As of December 31, 2018

44 charge points provided by Source London.

6 Rapid charge points in 3 locations. Under ownership of the London
Borough of Hackney. Service provided by Charge Point Services.

13 charge points installed as part of a trial through Ubitricity.

 

Planned: As of December 31, 2019

Up to 59 residential charge points utilising lamp column technology. We in
the final stages of a procurement process to appoint a supplier. Further
details are currently commercially sensitive. 

Up to 24 free standing charge points. Points are 7kw. We are in the final
stages of a procurement process to appoint a supplier. Further details are
currently commercially sensitive. 

Up to 12 rapid charge points in 6 diffe

 

Appeals & Complaints Procedure

If you are dissatisfied with this response and wish to appeal, please
write to the Information Management Team and this will be dealt with
through our Internal Review procedure.

Information Management Team - Governance

London Borough of Hackney

Hackney Service Centre

1 Hillman Street

London E8 1DY

[1][Hackney Borough Council request email]

 

Your request for an internal review should be submitted to us within 40
working days of receipt by you of this response. Any such request received
after this time will only be considered at the discretion of the Council.

 

If you are still not satisfied following the Internal Review, you have a
right to appeal to the Information Commissioner at the contact details
provided below.

 

Information Commissioner's Office
Wycliffe House
Water Lane
Wilmslow
Cheshire
SK9 5AF 

Telephone: 01625 545 700

[2]www.ico.org.uk

 

Yours sincerely

 

Information Management Team

ICT Services
London Borough of Hackney  

 

References

Visible links
1. mailto:[Hackney Borough Council request email]
2. http://www.ico.cgov.uk/

Looking for an EU Authority?

You can request documents directly from EU Institutions at our sister site AskTheEU.org . Find out more .