Dear Greenwich Borough Council,

Under the Freedom of Information Act, can you please provide the following information on parking permits and electric vehicle charging infrastructure statistics in the council.

Parking Permits - The information is required for last 3 calendar years (2016, 2017, 2018 and 2019 Jan & Feb)
1. Annual number of residents parking permits issued (all types of vehicles)
2. Annual number of residents parking permits for Battery electric vehicles (zero emission vehicles only)
3. Annual number of Business parking permits issued (all types of vehicles)
4. Annual number of Business parking permits for Battery electric vehicles (zero emission vehicles only)

Charging Infrastructure - The information is required for last 3 calendar years (2016, 2017, 2018 and planned for 2019)
1. Total number of public charging locations (excluding taxi only and private charge points like car parks)
2. Total number of public charging points (Multiple points at a single location)
3. 7 kW and below charging points
4. 11 kW charging points
5. 22kW charging points
6. 43 kW and above charging points

Charging Infrastructure - by supplier - The information is required for last 3 calendar years (2016, 2017, 2018, and planned for 2019)
1. Total number of charging points - Supplier 1
2. Total number of charging points - Supplier 2
3. Total number of charging points - Supplier …

Yours faithfully,

Rafique Nadaf

foi, Greenwich Borough Council

Dear Sir/Madam

Environmental Information Regulations request: EIR-26012

Thank you for your request dated 20 March 2019

Your request will be answered by 17 April 2019

If you have any queries about this request, please contact me, quoting the reference number above.

Yours sincerely,

Jackie Jago
Head of Corporate Services
Corporate Services
Directorate of Communities & Environment
Royal Borough of Greenwich

 020 8921 5044
 Room 20 Basement The Town Hall, Wellington Street, London SE18 6PW
 www.royalgreenwich.gov.uk

 Please consider the environment before printing this email

show quoted sections

foi, Greenwich Borough Council

1 Attachment

Dear Mr Nadaf

 

Environmental Information request:  EIR 26012

Thank you for your request dated 20^th March 2019.

Our response is as follows:

Under the Freedom of Information Act, can you please provide the following
information on parking permits and electric vehicle charging
infrastructure statistics in the council.

 

o Parking Permits - The information is required for last 3 calendar
years (2016, 2017, 2018 and 2019 Jan & Feb)

1. Annual number of residents parking permits issued (all types of
vehicles)

 

  2016 2017 2018 2019 (Jan-Feb)
Resident permits 9152 9211 10475 1564

 

2. Annual number of residents parking permits for Battery electric
vehicles (zero emission vehicles only)

 

The Royal Borough currently do not issue resident permits based on vehicle
type or emissions. Therefore, we do not hold the data requested.

 

3. Annual number of Business parking permits issued (all types of
vehicles)

 

  2016 2017 2018 2019 (Jan-Feb)
Business permits 1128 1127 1240 132

 

4. Annual number of Business parking permits for Battery electric vehicles
(zero emission vehicles only)

 

The Royal Borough currently do not issue business permits based on vehicle
type or emissions. Therefore, we do not hold the data requested.

 

·         Charging Infrastructure - The information is required for last 3
calendar years (2016, 2017, 2018 and planned for 2019) 1. Total number of
public charging locations (excluding taxi only and private charge points
like car parks) 2. Total number of public charging points (Multiple points
at a single location) 3. 7 kW and below charging points 4. 11 kW charging
points 5. 22kW charging points 6. 43 kW and above charging points

 

 

 

·         Charging Infrastructure - by supplier - The information is
required for last 3 calendar years (2016, 2017, 2018, and planned for
2019) 1. Total number of charging points - Supplier 1 2. Total number of
charging points - Supplier 2 3. Total number of charging points - Supplier

Please see Attachment 1 for information on charging infrastructure.

 

If you have any queries about this correspondence, please contact me,
quoting the reference number above.

If you are not satisfied with our response to your request, you can ask
for an Internal Review.  Internal review requests should be submitted
within two months of the date of receipt of the response to your original
request.  If you wish to do this, please contact us, setting out why you
are dissatisfied.

 

If you are not satisfied with the outcome of the Internal Review, you may
apply directly to the Information Commissioner (ICO) for a decision. 
Generally, the ICO cannot make a decision unless you have exhausted the
Internal Review procedure provided by the Council. You can contact the ICO
by emailing [1][email address], or by post at Customer Contact,
Information Commissioner's Office, Wycliffe House, Water Lane, Wilmslow,
SK9 5AF.

 

Yours sincerely,

 

Jackie Jago

Head of Corporate Services

Corporate Services

Directorate of Central Services

Royal Borough of Greenwich

 

' 020 8921 5044

*   Room 20 Basement The Town Hall, Wellington Street, London SE18 6PW

8 www.royalgreenwich.gov.uk

 

 

show quoted sections