North Bridge Leisure Centre Delays

The request was successful.

Calderdale Against Corruption

Dear Calderdale Metropolitan Borough Council,

Please provide the following information.

1) Why did McLaughlin and Harvey ("the contractors") pull of out the North Bridge Leisure Centre project?

2) When did CMBC first become aware that the contractors wanted to pull out of the project?

3) What contract(s) did CMBC have in place with the contractors?

4) Did the contract(s) in part 3 contain any clauses for pulling out of the project and any penalties or notice periods for doing so? Please provide details.

5) What was the original cost of the project when the original contractors were involved?

6) What will be the updated cost of the project with the new contractors in place?

7) What date will the project now be completed?

Yours faithfully,

Calderdale Against Corruption

Information Management, Calderdale Metropolitan Borough Council

 
Thank you for your email.  If you are making a request, a formal
acknowledgement will be sent to you in due course.

Information Governance Team
Calderdale MBC
 

show quoted sections

Helen Ambler, Calderdale Metropolitan Borough Council

1 Attachment

Dear Calderdale Against Corruption,

 

Please find attached our acknowledgement in relation to your recent
request.

 

Kind regards,

 

Helen Ambler

Information Governance Officer

The Borough Council of Calderdale

Legal & Democratic Services

Town Hall

Crossley Street

HALIFAX

HX1 1UJ 

 

Email: [1][email address]

 

 

show quoted sections

Helen Ambler, Calderdale Metropolitan Borough Council

1 Attachment

Dear Calderdale Against Corruption,

 

Please find attached our response in relation to your recent Freedom of
Information request.

 

Kind regards,

 

Helen Ambler

Information Governance Officer

The Borough Council of Calderdale

Legal & Democratic Services

Town Hall

Crossley Street

HALIFAX

HX1 1UJ 

 

Email: [1][email address]

 

 

show quoted sections