North Bridge Leisure Centre Delays
Dear Calderdale Metropolitan Borough Council,
Please provide the following information.
1) Why did McLaughlin and Harvey ("the contractors") pull of out the North Bridge Leisure Centre project?
2) When did CMBC first become aware that the contractors wanted to pull out of the project?
3) What contract(s) did CMBC have in place with the contractors?
4) Did the contract(s) in part 3 contain any clauses for pulling out of the project and any penalties or notice periods for doing so? Please provide details.
5) What was the original cost of the project when the original contractors were involved?
6) What will be the updated cost of the project with the new contractors in place?
7) What date will the project now be completed?
Yours faithfully,
Calderdale Against Corruption
Thank you for your email. If you are making a request, a formal
acknowledgement will be sent to you in due course.
Information Governance Team
Calderdale MBC
Dear Calderdale Against Corruption,
Please find attached our acknowledgement in relation to your recent
request.
Kind regards,
Helen Ambler
Information Governance Officer
The Borough Council of Calderdale
Legal & Democratic Services
Town Hall
Crossley Street
HALIFAX
HX1 1UJ
Email: [1][email address]
Dear Calderdale Against Corruption,
Please find attached our response in relation to your recent Freedom of
Information request.
Kind regards,
Helen Ambler
Information Governance Officer
The Borough Council of Calderdale
Legal & Democratic Services
Town Hall
Crossley Street
HALIFAX
HX1 1UJ
Email: [1][email address]
We work to defend the right to FOI for everyone
Help us protect your right to hold public authorities to account. Donate and support our work.
Donate Now