Muswell Hill Library / 54-56 Muswell Hill Report

The request was successful.

Dear Haringey Council,

Please release the full report, compiled by consultants GL Hearn, into the future of both Muswell Hill Library and the council-owned site at 54-56 Muswell Hill.

Please also publicise how much Haringey Council paid GL Hearn for this work.

Yours faithfully,

George Danker

Haringey Borough Council

Dear Mr Danker

 

Freedom of Information / Environmental Information Regulations Request:
LBH/6716517

 

I acknowledge your request for information received on 19 October 2017.

 

This information request will be dealt with in accordance with the Freedom
of Information Act 2000 / Environmental Information Regulations and we
will send the response by 16 November 2017

 

Yours sincerely,

 

 

 

Feedback and Information Governance

 

Shared Service Centre | Central Team

Haringey Council 

10th Floor, Alexandra House, 10 Station Road, Wood Green, London N22 7TR

 

www.haringey.gov.uk

twitter@haringeycouncil

facebook.com/haringeycouncil

 

 

This email and any files transmitted with it are confidential, may be
subject to legal privilege and are intended only for the person(s) or
organisation(s) to whom this email is addressed. Any unauthorised use,
retention, distribution, copying or disclosure is strictly prohibited. If
you have received this email in error, please notify the system
administrator at Haringey Council immediately and delete this e-mail from
your system. Although this e-mail and any attachments are believed to be
free of any virus or other defect which might affect any computer or
system into which they are received and opened, it is the responsibility
of the recipient to ensure they are virus free and no responsibility is
accepted for any loss or damage from receipt or use thereof. All
communications sent to or from external third party organisations may be
subject to recording and/or monitoring in accordance with relevant
legislation.

Dear Haringey Borough Council,

Please ensure that a response is sent today, as today is legally the last day on which a response can be submitted without breaching the regulations.

Yours faithfully,

George Danker

Dear Haringey Borough Council,

By law you should have responded to this FOI request by yesterday at the very latest. I had also sent a reminder message yesterday to prompt your reply.

I would appreciate a response to this request today otherwise I will have to submit a formal complaint and request an internal review of conduct.

Yours faithfully,

George Danker

Bowmer Saheeda, Haringey Borough Council

1 Attachment

Dear Mr Danker,

Re: Freedom of Information Act Request ref: LBH/6716517

 

Thank you for your request for information received on 19 October 2017, in
which you asked for the following information:

 

Please release the full report, compiled by consultants GL Hearn, into the
future of both Muswell Hill Library and the council-owned site at 54-56
Muswell Hill.

 

Please also publicise how much Haringey Council paid GL Hearn for this
work.

 

 

My response is as follows:

 

I can confirm we hold the information you have requested and have prepared
the attached redacted version of the full report prepared by GL Hearn. 
This report is redacted due to containing commercially sensitive
information. 

 

Section 43 (2) of the Freedom of Information Act allows us to withhold
information if to provide it would be likely to prejudice the commercial
interests of any person and it is in the public interest to withhold the
information. We think that to disclose the commercial information relating
to potential rent (and associated deal) the Council can get from the two
properties would prejudice the commercial interests of the Council. We do
not believe it would be in the public interest for this information to be
placed in the public domain, because the Council ran a public consultation
in 2016 regarding the relocation of Muswell Hill Library and the response
was largely against relocating the library and subsequently the Council
has decided not to relocate the library, therefore there is no public
benefit to the commercial information being released.   This response is
therefore a refusal notice, in part.

 

To answer your second question, we can confirm GL Hearn were paid a total
of £10,000 to prepare this report.

 

If you are unhappy with how we have responded to your request you can ask
us to conduct an Internal Review. If so, please contact the Feedback and
Information Team as below. (Please note you should do this within two
months of receiving this response.)   

 

Feedback and Information Team

10th Floor, Alexandra House

10 Station Road

London

N22 7TR

E [1][email address]

 

You may also complain to the Information Commissioner’s office, who may be
able to help you. However they would normally expect the local authority
to have undertaken a complaint investigation or Internal Review of the
request before they will accept the referral.

 

 

You can contact the Commissioner at:

 

Information Commissioner

Wycliffe House

Water Lane

Wilmslow

Cheshire

SK9 5AF

E [2][email address]

W [3]www.ico.org.uk

 

 

Yours sincerely,

 

Saheeda Bowmer

Senior Project Manager

Strategic Property

 

--------------------------------------------------------------------------

 

 

show quoted sections