M25 Junction 10 – 16 (Smart Motorway) - latest Appraisal Summary Table (AST)

The request was partially successful.

Dear Highways England Company Limited,

I request:
1. the latest Appraisal Summary Table (AST) for the M25 Junction 10-16 Smart Motorway scheme
2. the environmental scoping report for this scheme
3. the Environmental Assessment Report for this scheme
4. any other assessment made of the carbon impacts of this scheme
5. Notice of Determination for this scheme

Please also place the documents listed above on the scheme page on your website, as currently there is very little information there.

Thank you.

Yours faithfully,

Rebecca Lush

foi@highwaysengland.co.uk,

 

Dear Rebecca Lush

Thank you for your request relating to M25 Junction 10 a€“ 16 (Smart
Motorway) - latest Appraisal Summary Table (AST) dated 11 December 2021. 

The due date for issuing a response is 12 January 2022.

Please feel free to contact our team if you have any queries quoting
FOI/2936 in any future communications

Kind regards

 

Amanda Speight

FOI Advice

 

You can make new FOI requests and review published responses by
visiting [1]https://foiform.highwaysengland.co.uk/

References

Visible links
1. https://foiform.highwaysengland.co.uk/

Dear [email address],

Please could I have a reply as soon as possible, as your response is overdue.

Yours sincerely,

Rebecca Lush

Dear Ms Lush,

Thank you for your e-mail.

I can confirm that a holding response was sent to you on this case on the 12 January 2022 however it appears not to have been received by your What Do They Know account. I have provided the response issued on the 12 January below for your records.

Kind Regards

Jonathan Drysdale

FOI Officer

Dear Rebecca Lush

FOI 2936

Thank you for your information request dated 11/12/2021 regarding M25 Junction 10-16 Smart Motorway scheme.

Unfortunately, we are still working on this request and we will not be able to provide you with a response within the 20 working day limit.

Please accept my sincere apologies for this delay.

We plan to let you have a response by Tuesday, 09 February 2022, this being a delay of 20 working days.

Further information about your rights to information is available from the Information Commissioner's Office at www.ico.org.uk

The Information Commissioner can be contacted at: [email address]

Information Commissioner’s Office

Wycliffe House

Water Lane

Wilmslow

Cheshire

SK9 5AF

Please remember to quote reference number FOI/2936 in any future communications about this response.

Kind regards

Jaspriya Singh Rana

Senior Administrator- M25 J 10-16

Smart Motorways Alliance
National Highways | 2 Colmore Square | Floor 5 | Birmingham | B4 6BN
Tel: 0300 123 5000

Email: [email address]

Web: www.highwaysengland.co.uk

show quoted sections

foi@highwaysengland.co.uk,

Dear Ms Lush

My apologies for the delay. 

We recognise that your response is over due and are now final stage of
approving it for release to you.

Thank you for your patience.

Yours sincerely

Louisa Gosling

.

 

Dear [email address],

Please could I have a reply as soon as possible, as your response is
overdue.

Yours sincerely,

Rebecca Lush

show quoted sections

foi@highwaysengland.co.uk,

2 Attachments

 

Dear Ms Lush,

Please see below

 

Response FOI/2936

 

Your request received on 11/12/2021:

I request:
1. the latest Appraisal Summary Table (AST) for the M25 Junctions 10 to 16
Smart Motorway scheme
2. the environmental scoping report for this scheme
3. the Environmental Assessment Report for this scheme
4. any other assessment made of the carbon impacts of this scheme
5. Notice of Determination for this scheme

Please also place the documents listed above on the scheme page on your
website, as currently there is very little information there.

 

Our Response

We have dealt with your request under the provisions of the Environmental
Information Regulations (EIR) 2004.  This is because the information
requested concerns measures and activities affecting or likely to affect
elements of the environment or affect factors such as noise, pollution
discharges and other releases into the environment.

 

Information Held 

1. The latest Appraisal Summary Table (AST) for the M25 Junctions 10 to 16
Smart Motorway scheme

 

This is provided in Annex 1.

 

2. The environmental scoping report (ESR) for this scheme

 

This is provided in Annex 2.

 

The M25 Junctions 10 to 16 Scoping Report was prepared in
2018.  Subsequently, in October 2019, LA 114 was issued.  National
Highways is committed to incorporating the LA 114 requirements in the M25
Junctions 10 to16 scheme.  Therefore, please note that the Scoping Report
provided here is to be updated.

 

3. The Environmental Assessment Report (EAR) for this scheme

 

The only information we hold in this regard is a draft EAR dated January
2020. 

The data and analysis presented in this draft has not been updated or
validated. This information falls under the exception in regulation
12(4)(d) of the Environmental Information Regulations because it is
unfinished material or material in the course of completion. 

ICO guidance on EIR 12(4)(d) is available here:

[1]https://ico.org.uk/media/for-organisatio...

 

This exception is subject to a Public Interest Test (PIT).  The PIT we
conducted concluded that the balance of the public interest lies in
withholding the information. This conclusion was based on the following
considerations:

 

It may be in the public interest to disclose this information to permit
the public to comment on information where a public authority is proposing
to spend public money on a road scheme.  However, in this case the data is
out of date or has not yet been fully assessed or written up in a report
form and therefore cannot be provided in an accessible format. 
Accordingly, we believe that this outweighs any public interest in
disclosing this information at this stage.  However, the EAR will be made
available once it has been completed

 

 

 

4. any other assessment made of the carbon impacts of this scheme

 

Further to the information already provided with this response (as
described above), this information is not held..

5. Notice of Determination (NOD) for this scheme

 

This information is not held. To date, the NOD has not been issued

 

 

Advice and Assistance

 

You have requested that we “place the documents listed above on the scheme
page on your website, as currently there is very little information there”

 

We recognise that the information currently provided on the scheme page on
our website is limited .  We plan to update the information on this page
 in due course.

 

 

 

If you are unhappy with the way we have handled your request you may ask
for an internal review by reply, or email
[2][email address].

 

The internal review involves an independent investigation of the
information provided and/or withheld in the response, including the
process and considerations which were involved in preparing the response. 
The aim of the internal review is to assess compliance with our statutory
obligations under the appropriate framework (either the Freedom of
Information Act, or the Environmental Information Regulations), and to
provide you with a report on this assessment.  Where an internal review
finds that withheld information should have been provided to you, this
information will be also be provided.

 

If you are not content with the outcome of the internal review, you have
the right to apply directly to the Information Commissioner for a
decision. The Information Commissioner can be contacted at:

 

Information Commissioner’s Office

          Wycliffe House

          Water Lane

          Wilmslow

          Cheshire

          SK9 5AF

 

If you have any queries about this letter, please contact me.

 

Please remember to quote our reference number FOI / 2936 in any future
communications about this request.

 

 

Yours sincerely

 

Jaspriya Singh Rana

 M25 J 10-16

Smart Motorways Alliance

References

Visible links
1. https://ico.org.uk/media/for-organisatio...
2. mailto:[email address]

A12 Chelmsford A120 wide, National Highways Limited

1 Attachment

Good afternoon

Please find attached information regarding A12 Chelmsford to A120 widening
scheme and notice of accepted application for a Development Consent Order.

Please do not hesitate to get in touch if you have any further questions.
 
Kind regards
 
The A12 project team
 
If you’d like more information about how we manage data, or a copy of our
privacy notice, please contact:
[1][email address]

We’d love to get your feedback about our reply to you today, simply click
[2]here to complete our short survey
 
You can also tell us about something wrong on any of our roads by using
the Report a Problem page on our National Highways website:
[3]https://nationalhighways.co.uk/about-us/...

This email may contain information which is confidential and is intended
only for use of the recipient/s named above. If you are not an intended
recipient, you are hereby notified that any copying, distribution,
disclosure, reliance upon or other use of the contents of this email is
strictly prohibited. If you have received this email in error, please
notify the sender and destroy it.

National Highways Limited | General enquiries: 0300 123 5000 |National
Traffic Operations Centre, 3 Ridgeway, Quinton Business Park, Birmingham
B32 1AF | [4]https://nationalhighways.co.uk |
[5][email address]

Registered in England and Wales no 9346363 | Registered Office: Bridge
House, 1 Walnut Tree Close, Guildford, Surrey GU1 4LZ

Consider the environment. Please don't print this e-mail unless you really
need to.

References

Visible links
1. mailto:[email address]
2. https://forms.office.com/Pages/ResponseP...
3. https://nationalhighways.co.uk/about-us/...
4. https://nationalhighways.co.uk/
5. file:///tmp/[email address]