IT Projects
Dear University of Sussex,
Could you please provide the following information?
How many IT projects are currently in development?
Of those projects how many are on time?
Of those projects how many are delayed?
Of those projects how many are on budget?
Of those projects how many are over budget?
Of these projects how many are both delayed and over budget?
If you have any projects which are delayed, or over budget could you please provide the total time delay and total budget overspend on projects in these catagories
Can you also please provide the name and purpose of your single biggest over budget project if you have one?
Please use the definition of "IT Project" as you would in your own governance structure
Yours faithfully,
Yours faithfully,
Matt Jones
Dear Mr Jones,
Thank you for your correspondence received on 16 January 2019.
Your request will be dealt with under the Freedom of Information Act 2000
and will be answered as soon as possible and within twenty working days
following the date of receipt, i.e. by 13 February 2019.
If you need to contact us about your request please quote your reference
number FOI-19-0020.
Kind regards,
Information Management Team
University of Sussex, Sussex House, Brighton BN1 9RH
[1]cid:image001.png@01D335FF.FB69BDA0
References
Visible links
Dear Mr Jones,
Please find attached our formal response to your recent Freedom of
Information request.
Kind regards
Lucy Pattenden
Information Officer
University of Sussex, Sussex House, Brighton BN1 9RH
Tel: 01273 873954
[1]cid:image001.png@01D384A9.A49DC9A0
References
Visible links
We work to defend the right to FOI for everyone
Help us protect your right to hold public authorities to account. Donate and support our work.
Donate Now