Dear Birmingham City Council,

Could you please advise what date Amey submitted their Pre-Qualification Questionnaire (PQQ) when bidding for the local highways contract, what date they submitted their final tender, and what date the contract was signed?

Also, is the named principal contractor in tendering documents stated as being Amey LG (also known as Amey Local Government)?

Finally, as part of their bid, did Amey at any point declare any significant health and safety incidents (for example, workplace fatalities, major injuries, etc.) or whether there were any legal proceedings that were either threatened, pending or had concluded against them?

Yours faithfully,
Richard Davis

Jenny Bent, Birmingham City Council

1 Attachment

Dear Richard Davis

 

Please find attached the response to your recent request for information.
Should you need to contact us again could you please quote the reference
FOI17195  to enable us to locate your enquiry on our database.

 

 

Yours sincerely

Economy Highways Team

show quoted sections

Dear Jenny Bent,

Many thanks for your reply. Apologies for the delay in getting back to you.

In addtion to the date of final tender and contract signing, I also requested the date that Amey submitted their PQQ which wasn't detailed in your response. Would you be able to advise please?

If at all possible, your speediest response would be greatly appreciated, as time is of the essence.

Many thanks in advance

Yours sincerely,
Richard Davis