In light of the proposed supermarket development on the Hibbert Lane site of the existing Cheadle+Marple Sixth Form College, could you please provide answers to the questions below.

1. Retail Impact Assessment

a. On what date was it commissioned?
b. If not commissioned yet, please advise date it is due to be commissioned, if known.
c. If commissioned already, please provide copies of report.

2. Noise Impact Assessment

a. On what date was it commissioned?
b. If not commissioned yet, please advise date it is due to be commissioned, if known.
c. If commissioned already, please provide copies of report.

3. Traffic Impact Assessment
a. On what date was it commissioned?
b. If not commissioned yet, please advise date it is due to be commissioned, if known.
c. If commissioned already, please provide copies of report.

Yours faithfully,

Neil Corrie

FOI Officer, Stockport Metropolitan Borough Council

Dear Mr Corrie,

Thank you for your request for information below which has been given
reference FOI 4569. Please quote this on any correspondence regarding your
request.

Stockport Council will respond to your request within 20 working days. If
there will be a charge for disbursements e.g. photocopying in order to
provide the information, we will inform you as soon as possible to see if
you wish to proceed; however such charges are usually waived if they
amount to less than £10.

Yours sincerely,

Corporate Information Services

Stockport Metropolitan Borough Council

show quoted sections

FOI Officer, Stockport Metropolitan Borough Council

Dear Mr Corrie,

I am writing in response to your request for information below (Ref 4569).

The response to your request has been prepared by the relevant Council
service and is as follows:

1a/1b/1c. No retail impact assessment has been commissioned by the
Council. Such a statement would be required to be submitted with a
planning application by whoever the applicant was.

2a/2b/2c. No noise impact assessment has been commissioned by the
Council. Such a statement would be required to be submitted with a
planning application by whoever the applicant was.

3a/3b/3c. No traffic (or transport) impact assessment has been
commissioned by the Council. Such a statement would be required to be
submitted with a planning application by whoever the applicant was.

In the event that an application is submitted accompanied by the above
documentation the Council may undertake (or commission) its own assessment
so as to check the validity of what is being claimed.

If you are unhappy with the way we have handled your request you are
entitled to ask for an internal review. Any internal review will be
carried out by a senior member of staff who was not involved with your
original request. To ask for an internal review, contact
[1][email address] in the first instance.

If you are unhappy with the outcome of any internal review, you are
entitled to complain to the Information Commissioner. To do so, contact:

Information Commissioner’s Office

Wycliffe House

Water Lane

Wilmslow

Cheshire

SK9 5AF

[2]www.ico.gov.uk

01625 545 745

Yours sincerely,

Corporate Information Services

Stockport Metropolitan Borough Council

show quoted sections