HS2 Compulsory Purchase

Department for Transport did not have the information requested.

Dear Department for Transport,

Given that Compulsory Purchase powers for Phase One of the scheme are due to run out on 23rd February 2023, please can you tell me how many:

1) Parcels of land (not including subsoil in tunnelling locations) have been identified as being permanently required by phase one of the scheme in total.

2) Parcels of land (not including subsoil in tunnelling locations) have been identified as being temporarily required by phase one of the scheme in total.

3) Parcels of land (not including subsoil in tunnelling locations) have been identified as being permanently required by phase one of the scheme in total.

3) Parcels of land (not including subsoil in tunnelling locations) required for the construction of phase one where purchase has been completed.

4) Parcels of land (not including subsoil in tunnelling locations) on the route of phase one which HS2 Ltd has taken temporary possession of.

5) Parcels of land (not including subsoil in tunnelling locations) on phase one which HS2 Ltd has taken temporary possession of, but will be required on a permanent basis.

6) Plots subsoil in tunnelling locations which have been identified as being permanently required by phase one of the scheme.

7) Plots subsoil in tunnelling locations to be used for phase one purposes where purchase has been completed.

Yours faithfully,

Joe Rukin

Department for Transport

Dear Sir/Madam,

I am writing to acknowledge receipt of your request for information which
has been allocated reference number P0019695.

A response will be issued to you in due course.

Regards,

Department for Transport
FOI Advice Team
Governance Division
Zone D/04
Ashdown House
Sedlescombe Road North
St Leonards on Sea
East Sussex
TN37 7GA

show quoted sections

highspeedrail, Department for Transport

1 Attachment

Dear Mr Rukin

 

Please find attached our response to your request under the Freedom of
Information Act.

 

Please send or copy any follow-up correspondence relating to this request
to the FOI Advice Team using the reference F0019695 to help ensure that it
receives prompt attention. 

 

Yours sincerely

 

Correspondence Team

High Speed Rail Group

 

Correspondence and Briefing| High Speed and Major Rail Projects Group |
Department for Transport
Second Floor | Great Minster House | 33 Horseferry Road | London SW1P 4DR

 

show quoted sections