Dear North Northamptonshire Council,

Please treat this as a Freedom of Information/Environmental Information Regulations request.

I would like information about your council’s planning in relation to climate action for the Council Climate Action Scorecards. This information is most likely to be held by a planning officer or similar.

In particular, please supply me with information relating to the following questions:
a. Has the Council approved any new *1 or expanded *2 roads or road junctions in its area from 1st January 2019 until 1st January 2023? Please list which ones were accepted.

*1 The intention of this question is to understand overall increases in road capacity, rather than recent housing developments. Please exclude minor roads built exclusively to connect new housing to the pre-existing road network.

*2 An expanded road or road junction is one that has increased capacity for motor vehicle traffic, not counting bus lanes, cycle infrastructure, or pedestrian infrastructure. Please include roads and junctions where new lanes have been added.

b. Has the council approved any new or expanded airport runways, terminals, measures to increase passenger numbers or other planning proposals that expand airport capacity in its area since 1st January 2019 until 1st January 2023? Please list which ones were accepted.

c. Has the Council approved any planning applications for fossil fuel extraction projects proposed in its area since 1st January 2019 until 1st January 2023? Please list which ones were accepted, including where relevant fossil fuel projects that were later ‘called in’ by central government.
By fossil fuel extraction projects we mean: any oil wells and fields (on or offshore), coal mines, fracking and shale gas, gas, natural (including liquified) gas (on or off shore) plants, and unabated fossil fuel generation and power plants well as related infrastructure such as pipelines and terminals for the fossil fuels.

I look forward to hearing from you in due course.

Yours faithfully,

Hannah Jewell, Climate Emergency UK

Data Requests, North Northamptonshire Council

Thank you for your email. This is an automated response and
acknowledgement of your correspondence.

If you have submitted a request under the Freedom of Information Act
(FOIA) or the Environmental Information Regulations (EIR), your request
will be considered and you will receive our response within the statutory
timescale of 20 working days.

If you have made a request for your own personal data (Subject Access
Request), or to exercise any of your Information Rights, you will receive
a response within one calendar month.  If your request is complex, we may
extend our response timeframe by up to a further two months.  We will
advise you as soon as possible if this is the case.

If we need to clarify any part of your enquiry, or your query is regarding
a different matter one of our Information Governance Team will be in
contact within 5 working days. 

Where clarification is sought in relation to a request for information, or
any fees are due following a fees notice, the statutory response timeframe
will be paused until such time as they are received.

If you have submitted a Complaint you will receive a response within 20
working days under the terms of our Corporate Complaints Procedure.

Kind regards

Information Governance Team

 

 

══════════════════════════════════════════════════════════════════════════

Any views expressed in this email are those of the individual sender and
are not necessarily those of North Northamptonshire Council unless
explicitly stated.

This email (including any attachments) may contain confidential or
privileged information and is intended solely for the use of the
individual or entity to whom it is addressed. Any confidential, sensitive
or protectively marked material must be handled accordingly.

If you are not the intended recipient you must not disclose, distribute,
copy, print or rely on any of the information contained in the email or
attachments, and all copies must be deleted immediately. If you do receive
this email in error, please notify the sender immediately and note that
confidentiality or privilege is not waived or lost.

North Northamptonshire Council may monitor the contents of emails sent and
received via its network for the purposes of ensuring compliance with
relevant legislation and the Council’s policies and procedures. All such
monitoring will take place in accordance with relevant legislation
including privacy and data protection legislation. For details of how
North Northamptonshire Council uses personal information please see the
Council’s website.

North Northamptonshire Council has scanned this email and attachments for
viruses but does not accept any responsibilities for viruses once this
email has been transmitted. You should therefore carry out your own
anti-virus checks before opening any documents.

══════════════════════════════════════════════════════════════════════════

Disclaimer

The information contained in this communication from the sender is
confidential. It is intended solely for use by the recipient and others
authorized to receive it. If you are not the recipient, you are hereby
notified that any disclosure, copying, distribution or taking action in
relation of the contents of this information is strictly prohibited and
may be unlawful.

This email has been scanned for viruses and malware, and may have been
automatically archived by Mimecast, a leader in email security and cyber
resilience. Mimecast integrates email defenses with brand protection,
security awareness training, web security, compliance and other essential
capabilities. Mimecast helps protect large and small organizations from
malicious activity, human error and technology failure; and to lead the
movement toward building a more resilient world. To find out more, visit
our website.

Data Requests, North Northamptonshire Council

1 Attachment

Dear Ms Jewell

 

Thank you for your below request for information, reference F0744,
received by the authority on 17 January 2023. I can confirm that North
Northamptonshire Council holds the information requested.

 

Please see below the service response:

North Northamptonshire Council as the minerals and waste planning
authority has not approved any oil wells and fields (on or offshore), coal
mines, fracking and shale gas, gas, natural (including liquified) gas (on
or off shore) plants during this period.

 

There has been no ‘unabated’ fossil fuel generation and power plants as
well as related infrastructure such as pipelines and terminals for the
fossil fuels planning applications approved over the same period by NNC as
the local planning authority (the local planning authorities of Corby
Borough Council, Kettering Borough Council, East Northamptonshire Council
and Borough Council of Wellingborough prior to 1 April 2021).

New roads or junctions we have approved in Highways which would meet these
requirements are:

 

• The revised preferred route for the A509 Isham Bypass which was agreed
by Executive on 16 June 2022 (a public paper)
• Capacity improvements to the A43/Steel Road roundabout at Corby

 

There have been no approvals relating to airports.

 

I trust the above is helpful, however if you are dissatisfied with the way
we have handled your enquiry or you are unhappy with the response
provided, you have the right to request an internal review.  You can do
this by emailing [1][North Northants Council request email]. Please quote your
reference number.

 

Please note a request for an internal review should be submitted no later
than 40 working days from the date of receipt of this response.  The
Council is not obliged to accept a request for an internal review beyond
this timeframe.  A full response to your request for a review will be
provided within 20 working days. 

 

If you remain dissatisfied with the Council’s internal review, you have
the right to appeal to the Information Commissioner (ICO).  It is
recommended that you contact them no later 3 months from the date of our
final response, using the contact details below: 

 

Information Commissioner’s Office 

Wycliffe House 

Water Lane 

Wilmslow 

Cheshire 

SK9 5AF 

 

Telephone:  0303 123 1113 

 

[2]https://ico.org.uk/make-a-complaint/ 

  

Yours sincerely 

 

Lucy DaSantos | Information Officer

North Northamptonshire Council

Swanspool House, Doddington Road, Wellingborough, NN8 1BP

T: 0300 126 3000 | DD: 01933 231822

 

Twitter: @NNorthantsC

Facebook: @NorthNorthants

Web: [3]www.northnorthants.gov.uk

[4]A picture containing background pattern Description automatically
generated

 

From: Climate Emergency UK <[FOI #937149 email]>
Sent: 16 January 2023 19:46
To: Data Requests <[North Northants Council request email]>
Subject: Freedom of Information request - High carbon infrastructure and
fossil fuel extraction planning

 

[CAUTION: EXTERNAL EMAIL] This email originated from outside of the
organisation. Do not click links or open attachments unless you recognise
the sender and know the content is safe.

Dear North Northamptonshire Council,

Please treat this as a Freedom of Information/Environmental Information
Regulations request.

I would like information about your council’s planning in relation to
climate action for the Council Climate Action Scorecards. This information
is most likely to be held by a planning officer or similar.

In particular, please supply me with information relating to the following
questions:

a. Has the Council approved any new *1 or expanded *2 roads or road
junctions in its area from 1st January 2019 until 1st January 2023? Please
list which ones were accepted.

*1 The intention of this question is to understand overall increases in
road capacity, rather than recent housing developments. Please exclude
minor roads built exclusively to connect new housing to the pre-existing
road network.

*2 An expanded road or road junction is one that has increased capacity
for motor vehicle traffic, not counting bus lanes, cycle infrastructure,
or pedestrian infrastructure. Please include roads and junctions where new
lanes have been added.

b. Has the council approved any new or expanded airport runways,
terminals, measures to increase passenger numbers or other planning
proposals that expand airport capacity in its area since 1st January 2019
until 1st January 2023? Please list which ones were accepted.

c. Has the Council approved any planning applications for fossil fuel
extraction projects proposed in its area since 1st January 2019 until 1st
January 2023? Please list which ones were accepted, including where
relevant fossil fuel projects that were later ‘called in’ by central
government.

By fossil fuel extraction projects we mean: any oil wells and fields (on
or offshore), coal mines, fracking and shale gas, gas, natural (including
liquified) gas (on or off shore) plants, and unabated fossil fuel
generation and power plants well as related infrastructure such as
pipelines and terminals for the fossil fuels.

I look forward to hearing from you in due course.

Yours faithfully,

Hannah Jewell, Climate Emergency UK

-------------------------------------------------------------------

Please use this email address for all replies to this request:

[5][FOI #937149 email]

Is [6][North Northants Council request email] the wrong address for Freedom of
Information requests to North Northamptonshire Council? If so, please
contact us using this form:

[7]https://www.whatdotheyknow.com/change_re...

Disclaimer: This message and any reply that you make will be published on
the internet. Our privacy and copyright policies:

[8]https://www.whatdotheyknow.com/help/offi...

For more detailed guidance on safely disclosing information, read the
latest advice from the ICO:

[9]https://www.whatdotheyknow.com/help/ico-...

[10]https://www.whatdotheyknow.com/help/ico-...

Please note that in some cases publication of requests and responses will
be delayed.

If you find this service useful as an FOI officer, please ask your web
manager to link to us from your organisation's FOI page.

show quoted sections