Full un-redacted copy of the Eco Park contract between SCC and Suez/M and W
Dear Surrey County Council,
This is a Freedom of Information request.
Following the information commissioner ruling against Derby Council withholding an un redacted copy of the contract with their waste contractor, using the same excuses as Surrey County Council, I now request the following-
An unredacted copy of the contract that Surrey County Council have with Suez and/or M+W for the building of the Eco Park gasification and anaerobic digestion plant. This is to be in electronic form and include all figures, key dates and clauses.
Any contracts relating to the PFI contract with Suez regarding the building of the Eco Park in Charlton Lane, again unredacted in electronic format.
Many thanks for your help.
Yours faithfully,
Adrian Corti
Dear Mr Corti
YOUR REQUEST REF NO. FOI001930 UNDER THE FREEDOM OF INFORMATION ACT 2000
Thank you for your request for information received on the 4 August 2019. Your request reference is as above.
We will respond to your request promptly and in any event within 20 working days from the date of receipt of your request. If you wish to contact me to discuss the progress of your request, please use the contact details given below and quote the reference number given above.
Regards
Helen Gilbert
Legal & Democratic Services
Corporate Information Governance Team (Room 138) | Democratic Services | Surrey County Council | County Hall | Penrhyn Road | Kingston upon Thames | Surrey | KT1 2DN
Tel: 020 8541 8935 | Email: [Surrey County Council request email] |
Dear Mr Corti,
RE: YOUR REQUEST FOI001930 UNDER THE ENVIRONMENTAL INFORMATION REGULATIONS 2004
(REGULATION 7 – EXTENSION OF TIME)
We have considered your request which was for:
'Following the information commissioner ruling against Derby Council
withholding an un redacted copy of the contract with their waste
contractor, using the same excuses as Surrey County Council, I now request
the following-
An unredacted copy of the contract that Surrey County Council have with
Suez and/or M+W for the building of the Eco Park gasification and
anaerobic digestion plant. This is to be in electronic form and include
all figures, key dates and clauses.
Any contracts relating to the PFI contract with Suez regarding the
building of the Eco Park in Charlton Lane, again unredacted in electronic
format.'
Your request falls under the Environmental Information Regulations 2004 as
it is about environmental information and therefore we will be handling
your request in accordance with those Regulations.
We consider your request to be both complex and voluminous and that it
would be impracticable to either comply with the request within 20 working
days or to make a decision to refuse to do so within that period.
Therefore, we are extending the period for responding to 40 working days
in accordance with Regulation 7 (1) of the Environmental Information
Regulations 2004.
Yours sincerely,
Gregory Finneron (on behalf of Richard Parkinson)
*********************************************
Greg Finneron
Team Manager - Leadership Office
Community Protection, Transport & Environment Directorate
Surrey County Council
County Hall
Penrhyn Road
KT1 2DN
Dear Mr Corti
I attach a letter in response to your request of 4 August 2019. The
contract between SCC and SUEZ is too large to e-mail therefore I can
either post a paper copy to you or send an electronic copy via our Egress
file sharing system.
If you would like a copy posted then please can you let me have your
postal address. If you would like me to send an electronic copy via Egress
then please can you provide an e-mail address.
Regards
Richard Parkinson
Environment Delivery Group Manager
Community Protection, Transport & Environment Directorate
Surrey County Council
Tel 020 8541 9391
Dear Richard Parkinson,
Please send me a link and instructions on how to electronically receive this information via your share file.
My email address is [email address]
Yours sincerely,
Adrian Corti
We work to defend the right to FOI for everyone
Help us protect your right to hold public authorities to account. Donate and support our work.
Donate Now