Our reference: 22403 EIR
01 November 2023
Dear Ms Wright,
Thank you for your request of 18 October 2023 in which you asked for the
following information, please find our response below in bold:
When is construction work currently expected to finish on:
a) the Eynsham Park and Ride, and
The planned completion date for the Eynsham Park & Ride is February
2024, with landscaping completing by May 2024.
b) each section of the A40 bus lane?
The current planned completion for construction is June 2027.
If they are not opening immediately after completion, an opening date would
also be much appreciated.
Not Applicable, please see above.
Internal review
If you are dissatisfied with the service or response to your request, you can
ask for an internal review as follows:
• Contact the Freedom of Information team in Customers and
Organisational Development
xxx@xxxxxxxxxxx.xxx.xx
• Write to the Freedom of Information team at the FREEPOST address:
Freedom of Information Team
Oxfordshire County Council
FREEPOST RTLL-ECKS-GLUA
Oxford OX1 1YA
If you remain dissatisfied with the handling of your request or complaint, you
have a right to appeal to the Information Commissioner at:
The Information Commissioner's Office,
Wycliffe House,
Water Lane,
Wilmslow,
Cheshire,
SK9 5AF
Telephone: 0303 123 1113
Website
: www.ico.gov.uk
Please let me know if you have further enquiries. I would be grateful if you
could use the reference number given at the top of this email.
Yours sincerely,
Olu Solola
Programme Lead
Transport and Infrastructure
Oxfordshire County Council
Email
: xxx.xxxxxx@xxxxxxxxxxx.xxx.xx
www.oxfordshir.gov.uk