Dear Southport and Ormskirk Hospital NHS Trust,

1. Does the trust currently have an Electronic Document Management System (EDMS) in place?
2. If so, what EDMS is deployed?
3. When was the system deployed?
4. When does the contract with the EDMS supplier end or when is the review date?
5. What is the rough spend on the EDMS either annually or total contract value (TCV)?
6. How was the EDMS procured, i.e. via framework and if so, which one?
7. .Does the trust have an Electronic Patient Record (EPR) system in place?
8. If so, what EPR is deployed?
9. When was the EPR deployed?
10. What is the value of the EPR contract, either annually or total contract value (TCV)?
11. When is the current EPR contract due for renewal?
12. Does the trust store active physical patient files in-house or off-site
13. If off-site, who is the current storage provider?
13 a - When is the contract due for renewal?
14. How many files/boxes are stored off-site
15. If physical files are stored on-site, roughly how many files/boxes are in the trusts library?
16. How many WTE/FTE work within the library
17. How many clinical appointments does the trust average each day/week/month?
18. Please supply the details of your CCIO, COO and CIO (where relevant) including names and email addresses

Yours faithfully,

Daniel Stonard

FOI (Southport and Ormskirk Hospital NHS Trust), Southport and Ormskirk Hospital NHS Trust

Thank you for your email received by the Freedom of Information team at
Southport and Ormskirk Hospital NHS Trust.

 

We are now processing your request for information and will respond to you
in full as soon as possible.

 

Under the Freedom of Information Act the Trust has 20 working days in
which to respond to your request. If for any reason it becomes apparent
that there could be a delay in responding to you, we will advise you
accordingly.

 

If you have any queries then please contact me by return e-mail to
[Southport and Ormskirk Hospital NHS Trust request email]

 

 

 

show quoted sections

FOI (SOUTHPORT AND ORMSKIRK HOSPITAL NHS TRUST), Southport and Ormskirk Hospital NHS Trust

Thank you for your Freedom of Information request, received below. Unfortunately there has been a delay in processing the request.

May I apologise on behalf of the Trust for an inconvenience caused by the delay in responding to your request. We are aware that the 20 working day deadline has not been met and endeavour to now resolve your request as soon as possible.

If the information is no longer required, or the request has changed since it was submitted, it would greatly appreciated if you could inform me by return email of any changes or withdrawal. Particularly at this time as we deal with urgent operational response to the current Public Health priorities.

If we do not hear from you within the next 30 days we will close this FOI

Once again, please accept my apology.

FOI Team

show quoted sections

FOI (SOUTHPORT AND ORMSKIRK HOSPITAL NHS TRUST), Southport and Ormskirk Hospital NHS Trust

Dear Daniel

 

Re: FOI 1920 623

 

Please find within a response to your request for information submitted
under the Freedom of Information Act 2000 to Southport and Ormskirk
Hospital NHS Trust, which for clarity I have included below.

 

Request with response below in red:

1. Does the trust currently have an Electronic Document Management System
(EDMS) in place? - Yes

2. If so, what EDMS is deployed? – Kainos Evolve

3. When was the system deployed? - 2012

4. When does the contract with the EDMS supplier end or when is the review
date? 19.10.22

5. What is the rough spend on the EDMS either annually or total contract
value (TCV) - £123,059 annually

6. How was the EDMS procured, i.e. via framework and if so, which one? -
Procurement

7. .Does the trust have an Electronic Patient Record (EPR) system in
place? - Yes

8. If so, what EPR is deployed? – System C - Medway

9. When was the EPR deployed? – Oct 2014

10. What is the value of the EPR contract, either annually or total
contract value (TCV) – Commercial in Confidence

11. When is the current EPR contract due for renewal? – OCT 2023 with
option for 5 further years

12. Does the trust store active physical patient files in-house or
off-site 13. If off-site, who is the current storage provider? –In house

13 a - When is the contract due for renewal? – N/A

14. How many files/boxes are stored off-site 15. If physical files are
stored on-site, roughly how many files/boxes are in the trusts library?
–We have notes stored of site

16. How many WTE/FTE work within the library 17. How many clinical
appointments does the trust average each day/week/month? – This Trust does
have some case notes in the library around 4000, We see roughly 3000
patients a week

18. Please supply the details of your CCIO, COO and CIO (where relevant)
including names and email addresses – CCIO position currently vacant, COO
– Mr Steve Christian. [1][email address]

 

 

 

 

The Trust is continually striving to improve the way it handles FOI
requests. To help us, we would be grateful if you could spend a few
minutes to complete our FOI customer care survey -
[2]http://www.smart-survey.co.uk/s/78233NVEPO

Responses are anonymous unless you enter your reference number or name.

 

We hope that you will find the information provided both informative and
helpful. We also hope that you will be satisfied with the manner in which
we have dealt with your Freedom of Information request. If not, please do
let me know or you may ask for a formal review under the FOI internal
review procedure at Southport and Ormskirk Hospital NHS Trust. If you
would like a formal review please write to:

 

Trish Armstrong-Child

Chief Executive Officer

Southport and Ormskirk Hospital

Town Lane

Kew
Southport
PR8-6PN

Internal review requests should be submitted within two months of the date
of receipt of this response.

 

If you remain dissatisfied after the internal review, you may make an
approach to the Information Commissioner.

Further Information about your rights is available from the Information
Commissioner at: Information Commissioner's Office

Wycliffe House, Water Lane, Wilmslow, Cheshire, SK9 5AF,

Telephone: 0303 123 1113, [3]www.ico.gov.uk

 

If there is anything you need clarification on, please do not hesitate to
contact me by return email to [4][email address] quoting your FOI
reference number.

 

Yours Sincerely,

 

FOI Team

 

 

show quoted sections

Dear FOI (SOUTHPORT AND ORMSKIRK HOSPITAL NHS TRUST),

in Question 12 you state the records are stored in-house, whereas question 14 states they are stored off-site. If there is a provision for off-site storage could you please confirm who the provider is and when the current contract is due for renewal?

Yours sincerely,

Daniel Stonard

FOI (SOUTHPORT AND ORMSKIRK HOSPITAL NHS TRUST), Southport and Ormskirk Hospital NHS Trust

Good Afternoon Daniel,

 

Question 14- How many files/boxes are stored off-site 15. If physical
files are  stored on-site, roughly how many files/boxes are in the trusts
library?

 

The Response for this question should be "We have no notes stored off
site". Sorry for the confusion. Hope this helps.

 

Kind regards,

FOI Team

 

 

 