DWI timescales for completion of work on AMP 4 sites (2005 - 2010)

The request was successful.

Dear Drinking Water Inspectorate,

(i) Please would you provide the actual completion dates for each phase (given below) for all Anglian Water AMP 4 sites.

Phase 1: Detailed investigations completed to confirm improvements required
Phase 2: Planning, design and procurement completed
Phase 3: Construction, installation and commissioning completed

(ii) Please would you also give the date of issue of the completion certificate for each site.

Thank you for your assistance.

Yours faithfully,

Anonymous

------------------------------------------------------------

Please see guidance from the Information Commissioner [January
2009]; which states that it is good practice for a public authority
to still consider a request made using an obvious pseudonym.

DWI Enquiries (DWI), Drinking Water Inspectorate

Thank you for your e-mail.  Your enquiry has been received by the Drinking
Water Inspectorate and we aim to respond within 5 working days.

All Freedom of Information and Environmental Information Regulations
requests will be dealt with within the statutory 20 working days.

Drinking Water Inspectorate

Department for Environment, Food and Rural Affairs (Defra)

This email and any attachments is intended for the named recipient only.
If you have received it in error you have no authority to use, disclose,
store or copy any of its contents and you should destroy it and inform the
sender.
Whilst this email and associated attachments will have been checked for
known viruses whilst within Defra systems we can accept no responsibility
once it has left our systems.
Communications on Defra's computer systems may be monitored and/or
recorded to secure the effective operation of the system and for other
lawful purposes.

DWI Enquiries (DWI), Drinking Water Inspectorate

Dear Anonymous

REQUEST FOR INFORMATION: DWI timescales for completion of work on AMP 4 sites (2005 - 2010)

Thank you for your request for information about DWI timescales for completion of work on AMP4 sites , which we received on 23rd June 2014 . We are handling your request under the Environmental Information Regulations 2004 (EIRs).

The EIRs apply to requests for environmental information, which is a broad category of information defined in regulation 2 of the EIRs. Public authorities are required to handle requests for environmental information under the EIRs. They give similar access rights to the Freedom of Information Act 2000 (FOIA).

Before we can assist, please can I clarify a few points regarding your request and the information DWI holds.

i) Request for each Anglian AMP4 site the following : Phase 1: Detailed investigations completed to confirm improvements required Phase 2: Planning, design and procurement completed Phase 3: Construction, installation and commissioning completed.

DWI holds the 'statutory instruments' (legal agreements) that relate to AMP4 schemes - a scheme may or may not cover one site. There are occasions when a scheme might cover a number of sites. There are generally a number of key milestones within these documents however they may or may not be the completion dates for each stage you have requested. The stage dates you have requested are dates that exist within the details of the project management between the water company and any contractor involved in the scheme.

ii) Date of issue of completion certificates

DWI holds dates of when DWI released the company from its legal obligations under the statutory instrument. This will frequently (but not always) be a year after the installation of the solution as water companies are required to demonstrate that the benefits the scheme was to designed to bring have been delivered. DWI do not hold dates of issue of the completion certificate for the work, again this is for the project managers within the companies.

Please let me know if, in light of the information above you wish to redefine your request. The 20-working-day timescale for responding to your request will commence from that date.

Regards

Judith Bibaud

Mrs Judith Bibaud
Drinking Water Inspectorate
Area 7E, 9 Millbank
c/o Nobel House
17 Smith Square
London
SW1P 3JR

Tel: 0300 068 6400
Email: [DWI request email]

show quoted sections