This is an HTML version of an attachment to the Freedom of Information request 'Demolition application'.

 
 
 
                                    A8 
THE ROYAL BOROUGH OF KENSINGTON AND CHELSEA 
 
CABINET MEETING – 19 JUNE 2014 
 
REPORT BY THE DIRECTOR OF HOUSING 
 
GRENFELL TOWER MAJOR WORKS AND HIDDEN HOMES PROJECT 
 
 

 
 
  
This  report  updates  Cabinet  on  the  progress  and  the  ongoing 
programme  for  the  major  improvements  works  and  Hidden 
 
Homes  project  at  Grenfell  Tower.  It  also  seeks  agreement  to 
 
 
increase the capital budget for the scheme to £10.3 million   
 
FOR DECISION 
 
 
 
1. 
INTRODUCTION 
1.1  This report seeks to provide Cabinet with an update on the major 
works and addition of seven Hidden Homes at Grenfell Tower on the 
Lancaster West estate. 
2. 
BACKGROUND 
2.1   As a result of the development of vacant basements at Elm Park 
Gardens, (23 flats for sale and 13 affordable homes) sales receipts 
are being generated which are predicted to reach £13 million. 
 
2.2  After funding the costs of enabling works and some hidden homes 
schemes, net receipts of approximately £8 million are expected to 
arise  on the scheme. 
 
2.3   In December 2011 Kensington and Chelsea Tenant Management 
Organisation (KCTMO) were asked to carry out an exercise to 
identify where major investment was needed on the housing estate 
which, would help to regenerate the area and reduce the burden on 
the HRA.  
 
2.4  Grenfell Tower was identified and a report approved by Cabinet on 2 
May 2012. Cabinet agreed to allocate £6 million towards the 
scheme. This is being met from the net capital receipts arising from 
the Elm Park Gardens scheme. The proposed scope of works at this 
time included replacement windows, external cladding, provision of 
additional flats (hidden homes) and the upgrade of the nursery and 
boxing club.  
 


 
 
2.5  Subsequently KCTMO worked up a proposal to upgrade the 
communal mechanical and electrical services, including the renewal 
of the communal heating system.  On July 2013, Cabinet agreed a 
revised budget for the whole Grenfell Tower project of £9.7 million. 
 
2.6  Part of the proposed investment included wider community benefits, 
the re-provision of new premises for the Grenfell Under 3‟s Nursery 
and the Dale Boxing Club which have a long history at Grenfell 
Tower and are well supported by the local community. In addition, 
redundant areas in the lower levels of the building offered the 
opportunity for new „Hidden‟ Homes. Consultation with residents in 
March 2012 produced overwhelming support for the proposals.  
 
2.7   It was the original intention that the Kensington Academy and 
Leisure Centre (KALC) and Grenfell Tower projects would work 
closely together with the same design team, consultants and 
contractor to deliver continuity in design and development process. 
However, as negotiations progressed it became apparent that it 
would not be possible to agree a contract price within the agreed 
budget with Bouygues UK. KCTMO in consultation with the Council 
therefore took the decision to appoint a new contractor through a 
OJEU competitive tender process.  
 
2.8  Resident consultation was undertaken regarding the revised 
proposals which, carried on throughout the process as timescales 
have changed and specifications have become more certain against 
budget.  
 
2.10  A revised planning application was submitted on 29 July 2013 and 
approved on 10 January 2014 following the agreement of a 
Unilateral Undertaking for the required £72,413 s106 sums. 
Simultaneously, an OJEU tender process was carried out with 16 
contractors submitting Pre-Qualification Questionnaires (PQQs) and 
five being taken forward to the Invitation to Tender (ITT) stage. 
Rydon submitted the most economically advantageous tender, 
scoring highest on both price and quality.  
 
2.11  The schedule of works will be:  
 
  Replacement of heating and hot water system for all 
properties within the Tower. 
  Replacement of windows with double glazed units. 
  Thermal cladding of the building. 
  Re-provision of premises for the nursery. 
  Re-provision of premises for the boxing club. 
  Re-provision of office space for the Lancaster West Housing 
Team. 
  Smoke/fire safety and ventilation works 
 


 
  Redecoration of the communal areas of the building. 
  Demolition of specific ramps and staircases to improve access 
through the site. 
  Associated environmental works 
  Delivery of seven new hidden homes in the lower areas of the 
building  comprising of; 1 x 1 bedroom, 2 x 2 bedroom , 1 x 3 
bedroom (wheelchair unit) and 3 x 4 bedroom flats. 
 
2.12  A newsletter was sent to all residents of Grenfell Tower in April 2014 
announcing Rydon as the project‟s contractor and arrangements are 
being made for Rydon‟s Resident Liaison Officer and KCTMO 
Resident Engagement Officers to have a site presence from the 
beginning of June 2014. 
 
Grenfell Under 3’s Nursery 
 
2.13  Grenfell Nursery is a long established provision serving Lancaster 
West and Henry Dickens Estates in North Kensington. They have 
traditionally operated crèche, childcare, and early years‟ education 
to local families, many on lower income. The service is part of the 
Lancaster West Community Childcare Network (LWCCN). The 
Network provides childcare at other sites, children‟s centre services, 
and early years‟ education for 2, 3, and 4 year olds. They are a key 
provider in North Kensington and are supporting the Council to meet 
statutory requirements for early years education and children‟s 
centre services. The nursery has occupied their current premises for 
a number of years with no lease and making no rent payments. This 
was an error and it is necessary for a lease and rent to be 
implemented for both the new premises at Grenfell Tower and the 
decant premises in accordance with the policy on managing HRA 
commercial stock. 
 
2.14  For the duration of the works period, the nursery will be occupying 
the Resource Centre located within the estate at a rent of £15,500 –
per annum and the ability to offer 20 childcare places. A six month 
rent free period has been offered to allow the nursery time to work 
with Family and Children‟s Services (FCS) to develop a business 
plan. With a viable business model in place it is hoped that Grenfell 
Under 3‟s Nursery will be able to take up the lease at the new 
premises. The new space will allow the provider to offer 40 childcare 
places and should be ready for occupation by August 2015. A lease 
has now been signed for the decant premises and a new lease would 
need to be signed prior to the occupation of the new premises. 
 
2.15  It has been agreed that FCS will work with Grenfell Under 3‟s 
Nursery and by October 2014 it should be clear as to whether the 
nursery will be able to take up the offer of the new premises. If the 
current provider either cannot or chooses not to take up the offer, 
 


 
FCS can begin the process of acquiring a new provider to make sure 
there is no disruption to childcare places in the local area. 
 
2.16  Housing and FCS will continue to work together to ensure that there 
is sustained provision of childcare places in the local area. 
 
Dale Boxing Club 
 
2.17  The Dale Boxing Club currently occupies a space on the ground floor 
of Grenfell Tower. They have a 25 year peppercorn lease agreed by 
KDR on 8 March 1999. Therefore, a 25 year lease for the new 
premises is being offered with a peppercorn rent until 2024 and, a 
market rent to be charged for the remainder of the term. The new 
lease will be signed prior to the occupation of the new premises. In 
addition, KCTMO will only be providing the boxing club with a shell 
as funding from Sports England will allow the club to fit out the area 
to their own specification. 
 
2.18  In order to assist the club during the works period, a part of the 
disused car park at Lowerwood Court has been offered at a 
peppercorn rent. FCS have undertaken to pay the costs to make the 
space fit for occupation up to a maximum amount of £10,000 and 
Rydon expect to have the work completed by the end of June 2014. 
All of the required information for the legal paperwork has been 
collated and the necessary paperwork should be ready for signature 
by the end of June 2014. The boxing club will then be able to move 
during the early part of July 2014 and remain at Lowerwood Court 
until the Grenfell Tower works are completed. 
 
2.19  Dale Boxing Club is an important part of the local community and 
FCS hope to work with them going forward to provide further 
opportunities for those in the area. Links have now been made with 
the FCS team and they intend to work with Dale Boxing Club over 
the coming month to develop an offer for the local community. 
 
Leaseholders 
 
2.20  There are 12 leaseholders in the 120 flats at Grenfell Tower. In 
November 2012, KCTMO wrote a letter to all leaseholders stating 
that no recharges would levied for the proposed work. This decision 
had been taken by the Royal Borough in August 2012 following 
consultation with legal services. It was concluded that the majority 
of the work would be classed as „improvements‟ rather than repairs 
and therefore outside the scope of recharge according to the terms 
of the lease. There was the potential to recharge for a small number 
of items such as redecorating the communal areas, but the Council 
decided against this.  
 
 
 


 
3. 
PROGRAMME 
 
3.1  On 27th March 2014, KCTMO Board agreed to the selection of Rydon 
Property Services Ltd as preferred contractor for the refurbishment 
of Grenfell Tower. 
 
There are a number of items in the tender, relating to the scope of 
works and the planning conditions that need to be finalised before a 
contract sum can be finalised. A pre-contract agreement in the sum 
of £350,000 has been put in place with Rydon to resolve a number 
of matters, which include: 
  The  scope  of  environmental  works:  the  tender  included  a  wider 
scope  of  environmental  works  than  is  likely  to  be  required.  This 
was done to ensure that there was a clear cost base that could be 
applied  when  the  exact  scope  of  works  is  defined  in  negotiation 
with  Bouygues,  the  contractor  for  the  KALC  project.  Discussions 
are underway between all parties to agree the boundary between 
the  two  projects  and  to  agree  how  to  manage  the  interface. 
When this is resolved, there should be cost savings in the Rydon 
tender. 
  There are planning conditions to be discharged in relation to the 
detailed design and materials of a number of items, including the 
new  windows  and  the  cladding  material  and  fixing  method. 
Subject  to  agreement  with  planning,  these  could  result  in 
increased  cost,  we  would  therefore  like  to  be  prudent  and  plan 
for this possibility  
  A  requirement  of  the  tender  is  for  Rydon  to  secure  “ECO”  grant 
funding  from  energy  suppliers  to  support  the  project,  it  is 
uncertain  at  the  present  time  how  much  they  can  actually 
achieve.  We would therefore recommend in the budget that we 
plan  not  to  receive  any  ECO  grant  funding  and  if  we  actually 
manage to receive some funding, then this can be used to reduce 
the net expenditure on the scheme.  
 
3.2  While  the  agreed  tender  means  that  the  works  can  be  done  within 
the agreed budget of £9.7m, that leaves absolutely no contingency. 
On any complicated refurbishment project like this, with works being 
done  around  tenants  remaining  in  situ,  it  would  be  prudent  to 
include  a  contingency  of  at  least  5%;  however,  with  the  additional 
risks to budget outlined in para 3.1, it would be prudent to include a 
contingency of at least 6% in this case. It is therefore recommended 
that the budget for this scheme is increased to £10.3 million.  
 
Option 1: 
To increase the budget to £10.3m to include a sum for contingency 
of 6%.  
 


 
Option 2:  
Is  not  to  increase  the  budget  to  £10.3m  but  for  it  to  remain  as 
agreed  at  £9.7m,  this  would  mean  that  there  would  be  no 
contingency,  which  would  not  be  recommended,  and  therefore  a 
reduction is made in the specification of the project to accommodate 
this  budget  risk,  e.g.  the  seven  hidden  homes  are  not  provided  as 
part  of  the  scheme.    However,  if  the  scope  of  works  is  reduced 
significantly,  it  is  likely  that  the  scheme  would  need  to  be  re-
tendered. 
3.3  A further review of the scheme design is currently being considered 
relating  to  the  office  provision  within  Grenfell  Tower.  The  existing 
housing  office  in  the  block  is  being  relocated  to  the  former  EMB 
office. The local community need for community space is also being 
reviewed and the existing Estate Services office may be upgraded to 
provide  a  space  for  use  by  local  community  groups.  An  option  is 
being considered to provide a further two 2-bed flats instead of the 
proposed  office  in  the  tower.  Design  options  have  been  produced 
and  discussions  are  underway  with  planners.  This  change  could  be 
accommodated  within  the  budget  detailed  above.  Members  are 
asked to note this change, subject to planning agreement.   
3.4  Both  Rydon  and  KCTMO  are  currently  working  to  confirm  the 
programme  of  work  which  will  endeavour  to  cause  minimal 
disruption  to  the  KALC  programme.  Early  indications  are  that  work 
to  demolish  the  ramp  at  the  west  side  of  the  site  near  the  old 
nursery  premises  would  commence  in  late  June  2014  with  the 
internal  work  to  the  boiler  starting  in  early  July  2014.  The 
scaffolding  and  mast  climbers  for  the  cladding  and  windows  are 
likely to be installed in late July 2014.  
3.5  Rydon will have a Resident Liaison presence for several weeks prior 
to  the  start  of  the  demolition  programme  in  late  June  2014.  They 
will  try  and  make  contact  with  all  residents  and  both  KCTMO  and 
Rydon  Resident  Liaison  Teams  intend  to  make  contact  with  the 
Lancaster  West  Tenant‟s  Association  to  try  and  promote 
involvement. Rydon have undertaken to work with RBKC to provide 
construction  apprenticeship  places.  A  meeting  with  the  Council‟s 
Housing and Worklessness Coordinator has been arranged for early 
June 2014. 
3.6  Unfortunately,  much  of  the  internal  work  is  likely  to  be  loud  and 
disruptive  for  the  residents.  Furthermore,  the  installation  of  the 
heating  system  and  windows  will  require  access  to  the  individual 
flats for approximately five days. The Lancaster West Housing Team 
are aware of this and Rydon Resident Liaison Officers will do all they 
can  to  ease  the  process.  In  light  of  this,  a  respite  flat  is  being 
arranged, as well as a daytime respite area, and all residents will be 
informed and be invited to use the space. 
 


 

4. 
CONSULTATION  
4.1  Consultation  for  this  scheme  has  been  extensive  involving  open 
meetings,  newsletters,  drop  in  sessions  and  door  knocking.  
Residents  have  been  consulted  extensively  during  the  planning 
applications and subsequent procurement processes and were given 
a  number  of  opportunities  to  comment  on  the  proposed  work  and 
materials. 
4.2  In addition, residents were given the opportunity to be involved with 
the  contractor  procurement  process.    Two  residents  were  involved 
with  the  Prequalification  Questionnaire  review,  and  Fay  Edwards, 
Chair of Lancaster West Tenants Association agreed to sit in on the 
interviews of the short listed contractors.  
4.3  Regular  newsletters  are  now  being  produced  and  Rydon  intend  to 
set  up  a  series  of  drop  in  sessions  and  coffee  mornings  once  they 
are  on  site.  Housing  Management  have  been  asked  to  identify  any 
potentially  vulnerable  households  who  may  require  additional 
support and KCTMO will make the necessary arrangements. 
4.4  In the event that the additional two „Hidden‟ Homes units are viable 
(which would take the total number of new homes to nine), further 
consultation will take place with all residents and any other effected 
parties. 
5. 
LEGAL IMPLICATIONS 
 
The Director of Law has been consulted and comments as follows:- 
 
5.1 
The General Consent for the Disposal of Land held for the purposes of Part II 
of the Housing Act 1985 - 2013 
authorises a local authority to dispose of land 
for a consideration equal to its market value.  
 
5.2 
Under section 123 Local Government Act 1972 the Council has an obligation, 
when  disposing  of  land,  to  do  so  for  the  best  consideration  reasonably 
attainable. 
  
5.3 
As the Dale Boxing Club currently have a lease at a peppercorn rent 
until 21st June 2024, it is only after this date that the council will be 
obliged  to  act  in  accordance  with  the  statutory  obligation  to  obtain 
the best consideration. The new lease to Dale Boxing Club therefore 
includes a provision for an open market rent review on the 22nd June 
2024.        
 
6.  
FINANCIAL AND RESOURCES IMPLICATIONS 
6.1  KCTMO has confirmed that it has the staffing resources within their 
establishment to carry out this work. 
 


 
 
6.2  It  is  recommended  that  the  capital  budget  for  this  project  is 
increased  from  £9.7  million  to  £10.3  million.  This  increase  in 
provision  can  be  met  from  a  draw  down  from  the  HRA  working 
balance.  
 
7. 
EQUALITY IMPLICATIONS 
7.1  Advice  has  been  taken  from  the  Council‟s  Equality  and  Diversity 
Team  as  regards  any  possible  equality  implications.  They  have 
advised that there do not appear to be any issues. 
8. 
CONCLUSIONS 
8.1  This report has sought to update Members on a significant capital 
programme and Hidden Homes project being managed by KCTMO 
and over seen by Council officers. 
8.2  The Grenfell Tower project has been subject to several delays but 
Rydon have now been confirmed as contractor with a start on site 
date set for 2 June 2014. 
8.3  Agreement is sought from Cabinet to increase the capital provision 
for the scheme to £10.3 million, enabling a contingency of 
approximately 6% to be established. Funding will be found from 
within the HRA. 
8.4  The Grenfell Tower project is mindful of the KALC scheme and the 
need for both the academy and leisure centre to be delivered on 
time. The boundary issues are being explored and satisfactory 
solution will be reached following the scheduled meetings between 
Rydon, BYUK and RBKC. Any risk will be mitigated as far as possible 
and the completion of the Grenfell Tower work will greatly enhance 
the local area and compliment the KALC project. 
 
9. 
RECOMMENDATION 
9.1  Cabinet is recommended to increase the capital budget for this 
scheme to £10.3 million. 
Laura Johnson 
Director of Housing 
 
Contact  officer:
  Miss  Kitty  Mortimer    Tel:  020  7361  2034    E-mail: 
xxxxx.xxxxxxxx@xxxx.xxx.xx