South Gloucestershire Council 
05 April 2017 
Minutes 
 
 
 
 
M4 J18a Link Study Project Board 
Location: 
Highways England, Temple Quay 
Chair:  
Emma Blackham. 
Attendees: 
Richard Ormerod, Mark King, Helen Spackman, Bruce Slattery, Alistair 
Rice, Rebecca Callaghan, Jeremy Damrel. 
Apologies: 
Rob Llewellyn, Andrew Birch. 
 
Item 
Description 
Action 
1.   
Welcome and introductions. 
 
2.   
Minutes of last Board: 
 
  Approved. 
 
  Actions outstanding: 
o  Assumptions & Actions Log (attached); 
HS 
o  Appraisal Specification Report. 
HS 
3.   
Progress report submitted to DfT 30th March; no 
 
response to-date. 
4.   
Highlight Report: 
 
  Taken as read. 
 
  4 scheme options tabled by CH2M: 
 
o  All options require significant 
improvements to Ring Road junctions 
 
(Hicks Gate to Dramway inclusive), such   
as a ‘hamburger’ layout and extension of 
managed motorway from M4 J19 to 
 
J18a; 
 
o  Option 1 Western alignment 
  New offline J18a north of M4 in 
 
Green Belt 

 
  Westerleigh Rd / Folly Brook Rd 
grade-separation 
 
 
 
 
 
 
 
 
 
 

  Significant improvements to Ring 
 
Road Lyde Green and Rosary 
 
junctions; 
o  Option 2 Central alignment 
 
  Historic alignment 

 
  Online J18a west of old railway 
  Adverse impact on consented 
 
development and Green Belt 

 
  Joins Ring Road at Dramway; 
o  Option 3 East 
 
  Online J18a at B4465 north of 
 
Pucklechurch in Green Belt 
  Three alignments through Green 
 
Belt to a junction with the Ring 
 
Road at/adjacent to Dramway; 
o  Option 4 East & West 
 
  As for options 1 and 3, but with  

 
  East-facing slips only north 
of Pucklechurch 
 
  West-facing slips only at 
 
Westerleigh Rd. 
  Take forward Options 1,2 and 3 to 2nd round of   
events with the following actions: 
o  Discard Option 3a 
HS, BS 
o  Simplified plan of options (HE to provide 
examples); 
HS, BS 
o  Key information (and what we don’t key 
HS, BS 
know); 
o  Press release & FAQs (for use if 
AR 
needed); 
AR, HS, BS 
o  Next steps. 

 
  Plan of action for April leading to Board 
approval of documentation by 26th April. 
HS, BS 
  Dates for 2nd round of events are: 
 
o  3rd May, South Glos Lead Members; 
o  8th May, stakeholders; 
All 
o  16th May, South Glos Councillors; 
o  17th May, local businesses; 
o  18th May, Town and Parish Councils; 
o  19th May, MPs (postponed). 
5.   
DONMs 
 
  DONM, 10:00/15, 7th June, SGC, Yate. 
All 
6.   
AOB 
 
  RO (probably) retiring June. 
  JD secondment finishes mid-May, Nick 
 
Aldworth joining. 
Attachments 
tbc 
 