This is an HTML version of an attachment to the Freedom of Information request 'Decision criteria used for developing the proposals for Junction 18a onto M4'.





 
South Gloucestershire Council 
13 June 2017 
Note of Meeting 
 
 
 
 
M4 Junction 18a Link Study  
South Glos Member Briefing 
1.  Need more clarity about potential impacts on local roads north of the M4. 
2.  Concern about the lack of Yate Link; noted that this is a JTS scheme and the 
J18a Link design would not preclude it and that its impact will be subject to a 
traffic forecast sensitivity test. 
3.  Confirmed that the forecast year assessments included future development, as 
per emerging JSP, will be included in assessment. 
4.  The traffic modelling tool for this study is the same as used for the JTS and 
JSP; collection of new traffic volume and origin-destination information will be 
required for the next stage of scheme development. 
5.  There will be a traffic forecast sensitivity test to test the impact of extending the 
Ring Road south of Hicks Gate to the A38. 
6.  Mitigation measures that would be required on local roads as a direct 
consequence of the J18a Link would from part of the scheme. 
7.  The J18a Link would form part of the package of JTS schemes that would 
enhance accessibility to South Bristol. 
8.  What would happen to the section of the M4 bypassed by the western option?  
Too soon to determine. 
9.  Which option would be quicker to build?  Similar. 
10. A similar level of information will be provided for the public consultation, but 
there will be more discussion of the differences between the options. 
11. Need to draw out how the options meet the objectives. 
12. Explain how this study fits into the WECA and Highways England programmes. 
 
 
 
G:\T&SP\Projects\3. Major Schemes\M4 J18a inc M32 J1\3. Members\5. Members\Briefing Jun'17\M4 