M4 Junction 18a Link Study 
 
Highlight Report 
Project Name: 
M4 J18a Link Study 
Project Sponsor: 
Emma Blackham 
Project Number: 
n/a 
Project Manager:  
Alistair Rice 
 
Reporting Period: 
Nov’16 – Feb’17 
Lifecycle Phase: 
Feasibility 
Project Start Date: 
November 2016 
Project End Date: 
March 2018 
Business Case 
Business Case Web 
n/a 
n/a 
Approval Date: 
/ Hyperlink: 
Business Case Re-
Project Type 
n/a 
SGC Partner Project 
fresh Date: 
Classification: 
 
Section 1: Budget Status (£000’s) 
In £/000’s
Total actual 
 
*Approved 
Forecast (to 
Variance (against 
cumulative 
Outturn Prices 
budget 
completion) 
Approved Budget) 
spend to date 
Revenue  
500 
53 
500 

Capital  




Total 
500 
53 
500 

*Signed off by ECS Committee? 
Yes  
Committee sign-off date 
9th November 2016 
Committee Minute number(s) 
 
Link to Committee report(s) 
Link 
Budget – operating within set parameters:   
Yes 
If no, what actions are to be prepared: 
 
Section 2: Budget Summary (£000’s by Year) 
Pre-
20/21 & 
 
14/15 
15/16 
16/17 
17/18 
18/19 
19/20 
Total 
14/15 
Future 
Revenue  



162 
338 



500 
Capital  









Total 



162 
338 



500 
 
Section 3: Schedule Status: 
Original End 
Mar’18
Latest Forecast 
Variance + / - 
 
Mar’18 

Date 
End Date 
(days) 
Comments: currently on schedule. 
 
 
Section 4: Risk Update: 
Risk Summary: Highlight the key risks below (stating no more than 10) 
 
 
 
 
 
 
 





M4 Junction 18a Link Study 
Date identified  Risk description 
Mitigation 
Risk status  
(Red / Amber / Green) 

Scope/detail of the 
technical work not 
Early and ongoing 
Nov’16 
supported by local 
engagement with 
Amber Green 
decision 
stakeholders. 
makers/stakeholders 
Provide a programme 
Nov’16
Delay in HE sign-off of 
 
identifying when HE 
Amber Green 
technical outputs. 
comments required. 
 
 
Section 5: Issues Update: 
Issues Summary: Highlight the issues that have actually occurred below 
 
Date identified  Issue description 
Mitigation 
Issue status  
(Red / Amber / Green) 

Info required from HE for 
Jan’17 
SGC to set up HE as a 
HE to provide info. 
Amber 
supplier. 
Send presentation to MPs & 
Jan’17 
MP briefing postponed. 
seek alternative date if 
Amber 
requested. 
 
 
Section 6: Key Milestones 
List of milestones and activities for this period (9th November – 3rd February): 
Milestone(s) 
Achieved? 
Due date 
Revised 
Reason for date 
(Y/N) 
date 
revision 
Phase 1 Tasks. 
To allow time to 
No 
31st Jan 
14th Feb 
follow up feedback 
at consultation 
Phase 1 Stakeholder, 
26th Jan to 2nd 
Member & town/parish 
Yes 
n/a 
n/a 
Feb. 
council engagement events. 
Phase 1 MP meeting. 
No 
27th Jan 
Tbc 
MPs cancelled 
 
Phase 1 PCF templates. 
As per comment on 
No 
23rd Jan 
7th Feb 
Phase 1 Tasks 
Key milestones and activities for the next period (4th February – 31st March): 
Milestone(s) 
Due date 
Revised 
Reason for date 
date 
revision 
Phase 1 Report 
Jan’17 
Feb’17 
See above. 
Arrange second round of engagement events. 
Mar’17 
n/a 
n/a 
Submit interim progress report to DfT 
Mar’17 
n/a 
n/a 
 
 
 
 
 
 
 
 





M4 Junction 18a Link Study 
Section 7: General Commentary 
 
Workstream 
Phase 1 Tasks 
Progress 
Project 
  Highlight Reports 
  Highlight Report 1 completed. 
management 
  Client Scheme Requirements. 
  Project Management Plan prepared and 
  Risk Management Plan. 
circulated, including risk management plan 
  Risk Register. 
and list of PCF products. 
  Product Checklist. 
  Risk Register to be prepared. 
  Project Schedule. 
  Project schedule prepared and updated for 
latest consultation dates. 
Business case    Understand implication of Joint Spatial 
  Well-progressed, to be reported in the Phase 
Plan (JSP) and Joint Transport Study 
1 report. 
(JTS) 
  Consider emerging local/central 
government policy 
  Use of existing data/models to evidence 
problems/opportunities 
  Formulate objectives 
Stakeholder 
  Review of JTS and other recent relevant    Three engagement events were undertaken: 
Engagement 
consultation/engagement 
o  Technical stakeholders (highway 
  Stakeholder engagement strategy 
authority officers, business reps and 
  Set up a stakeholder steering group 
statutory environmental bodies); 

o  South Glos Members (27 attendees); 
  Stakeholder meetings 1 - develop scheme 
o  Town & Parish Councils (14 Attendees). 
objectives  
  Some helpful feedback regarding the 
scheme and its objectives were received. 
  Unfortunately, the MPs had to postpone the 
scheduled meeting.. 
 
Design 
  Collate engineering baseline information,    C2 information has been requested – waiting 
including C2 inquiries 
for responses. 
  Review previous scheme plans and plans    Reviewed plans forwarded on by SGC – all 
for other proposals in the area 
previous alignment options pass through the 
  Specify additional data collection 
Lyde Green development. 
requirements 
  Requested Collision Data from SGC, BANES 
  Define constraints 
and HE – all received and data being 
  Develop scheme concepts to inform other 
processed. 
Phase 1 activities 
  Constraints map updated with environmental 
constraints. 
  Scheme option concepts under way. 
Transport 
  Review model GBATS validation in and 
  GBATS validation in the area is sufficient for 
modelling 
around the study (including regional 
a SOBC. 
models) 
  SWRTM data outstanding. 
  Review modelling of JSP/JTS 
  Recent ATC data on the Ring Road 
  Model specification 
compromised by capital maintenance 
schemes. 
 
 
 
 
 
 





M4 Junction 18a Link Study 
  Specify additional data collection 
  Use of JTS GBATS modelling to develop DM 
requirements 
models has commenced 
  Model Specification - in progress 
  Work to date indicates no additional surveys 
are required.  
Economic 
  Baseline data collation 
  Baseline assessment of economic conditions 
assessment 
  Speciation of approach 
in the area has commenced 
Environmental    Desktop assessment to establish 
  Constraints identified 
assessment 
environmental baseline and constraints 
  Specify data collection requirements (if 
required) 
 
 
 
 
Control & Approval 
Author 
Emma Blackham 
Alistair Rice 
Approver / Title: 
 
Sponsor 
Submission Date: 
Feb’17 
Approval Date: 
Feb’17 
 
 
 
Project Sponsor comments 
The stakeholder, Member and Town/Parish council engagement events were all productive and the data 
shared well received. Good progress noting the delayed milestone of the Phase 1 tasks by 2 weeks to 
ensure engagement issues can be fed in and accommodated.  
 
 
Programme Sponsor comments 
n/a 
 
 
Project Sponsor RAG Assessment 
Cost 
Green 
 
Quality 
Green 
Time 
Green 
Programme Sponsor overall RAG assessment 
n/a 
 
 
G:\T&SP\Projects\3. Major Schemes\M4 J18a inc M32 J1\2. Project Governance\Project Board\170209\M4 J18a Link Study 
Highlight Report Feb'17.docx 
 
 
 
 
 
 
 
 





M4 Junction 18a Link Study