Item 
Description 
Action 
1.   
Welcome and introductions 
 
2.   
Minutes of last Board 
 
  ‘Project Execution Plan’ should read ‘Project 
 
Management Plan’. 
 
  Public consultation will be mid-August to end of   
September 2017. 

 
  Actions outstanding: 
o  Assumptions & Actions Log 
HS 
3.   
DfT Offer of Grant 
 
  Submitted to DfT; no response to-date. 
4.   
Highlight Report 
 
  Maintain offer re-scheduling MP meeting. 
EB 
  Engagement events generally well-received 
 
and helpful feed-back provided by attendees. 
  Dates for 2nd round of events are: 
 
o  8th May, stakeholders 
 
o  16th May, South Glos Councillors 
o  18th May, Town and Parish Councils 
 
o  Tbc, businesses 
 
o  Tbc, MPs 
  CH2M completing a schedule of PCF 
 
deliverables and PCF products for dispatch to 
HS 
Highways England and SGC; including a ‘Client 
 
 
 
 
 
 
 
 

Scheme Requirements’ (using a template to be   
provided by RC). 

RC 
  CH2M to provide an essay or summary plan of 
key PCF products 
HS 
  CH2M producing an Appraisal Specification 
HS 
Report, which details transport modelling 
approach, noting: 
 
o  Use of existing models 
HS 
o  Outstanding request for CH2M to access 
the SWRTM (RC to chase) 
RC 
  Draft Phase 1 report issued to AR 16/02 and to  HS, AR 
Board members 21/02 
  Design progressing, the ‘middle’ junction 
 
location looks to be problematic. 
 
  Proposed amendments to objectives discussed 
and agreed; CH2M to circulate revised 
HS 
objectives and their measures (i.e. benefits 
 
realisation) to the Board. 
5.   
DONMs 
 
  Board meets every 2-months. 
 
  DONM, 10:00, 5th April, TQH. 
All 
6.   
AOB 
 
  Feedback from Environment Agency 
received; to be included in Phase 1 report. 
HS 
  CH2M setting up a Comms Log; all 
All 
communications should be copied to HS. 
  Confirmation of HE’s address & contact to 
RC 
permit SGC to raise a purchase order. 
Attachments 