Dear Cambridgeshire County Council,
Please treat this as a Freedom of Information/Environmental Information Regulations request.
I would like information about your council’s staff positions in relation to climate action for the Council Climate Action Scorecards. This information is most likely to be held by a HR department or similar.
In particular, please supply me with information relating to the following questions:
1a. How many staff does the Council directly employ (excluding contractors or subcontractors, and excluding teachers), that work directly for the Council as opposed to a school, leisure centres or other venture?
1b. How many directly employed staff spend 3 or more days per week (0.6 Full Time Equivalent (FTE)) on implementing the Climate Action Plan or other climate change projects? Please provide a list of all the roles. Please exclude waste management staff unless they are specifically working 3 or more days per week on implementing the Climate Action Plan or other climate change projects.
If you have answered yes to have a biodiversity planning officer and/or a retrofit staff member below, both these staff members can be included in this question even if they are contracted. This is likely to include all staff in your climate/sustainability team, such as Climate Change Officers or similar. This may include full time staff who spend 60% of their time on climate change projects and 40% of their time on other work.
You might include other staff in other departments, such as a procurement officer if they are spending 3 or more days per week (0.6 FTE) on writing and implementing a sustainable procurement policy or a planner that is working primarily on low carbon policies for new buildings.
2. Does the council have one or more staff member who works on home energy efficiency retrofitting, such as retrofit officers or project managers across the council area, for 3 or more days per week (0.6+ FTE)? This can include both directly employed and contracted staff, provided they work 3 or more days per week (0.6 FTE). The work of this officer may include working on any retrofit projects, including council buildings, council homes or private rented or owned households.
Please list any roles that work in this area, including the full time equivalent (FTE) if they work part time.
Please include staff members that are shared with other councils, such as between county and district councils, and note if they are shared across other areas.
3. How many planning ecologists (ecologists within the planning department) or equivalent working for 3 or more days per week (0.6+ FTE) does the council employ to scrutinise planning reports for Biodiversity Net Gain? This can include both directly employed and contracted staff, provided they work 3 or more days per week (0.6 FTE).
I look forward to hearing from you in due course.
Yours faithfully,
Hannah Jewell, Climate Emergency UK
Dear Hannah Jewell
Re: Freedom of Information Request ref 2029681
Thank you for your email. Your request will be dealt with in line with the Freedom of Information Act and its regulations. In accordance with the Act, the Council aims to respond to all requests within 20 working days, in this instance by 13/02/2023.
If we require further information, clarification or a fee in order to fulfil your request we will contact you again. Please quote the reference number above in all future correspondence concerning this request.
Yours sincerely,
Information Governance Team
Cambridgeshire County Council
Box No. SCO2306,
Scott House,
5 George Street,
Huntingdon,
PE29 3AD
Dear Hannah Jewell
Freedom of Information Act request response – Ref 2029681
Cambridgeshire County Council has now considered your request under the Freedom of Information Act. We can confirm that we do hold the information requested by you. Please find our response as set out below.
Request
I would like information about your council’s staff positions in relation to climate action for the Council Climate Action Scorecards. This information is most likely to be held by a HR department or similar.
In particular, please supply me with information relating to the following questions:
1a. How many staff does the Council directly employ (excluding contractors or subcontractors, and excluding teachers), that work directly for the Council as opposed to a school, leisure centres or other venture?
1b. How many directly employed staff spend 3 or more days per week (0.6 Full Time Equivalent (FTE)) on implementing the Climate Action Plan or other climate change projects? Please provide a list of all the roles. Please exclude waste management staff unless they are specifically working 3 or more days per week on implementing the Climate Action Plan or other climate change projects.
If you have answered yes to have a biodiversity planning officer and/or a retrofit staff member below, both these staff members can be included in this question even if they are contracted. This is likely to include all staff in your climate/sustainability team, such as Climate Change Officers or similar. This may include full time staff who spend 60% of their time on climate change projects and 40% of their time on other work.
You might include other staff in other departments, such as a procurement officer if they are spending 3 or more days per week (0.6 FTE) on writing and implementing a sustainable procurement policy or a planner that is working primarily on low carbon policies for new buildings.
2. Does the council have one or more staff member who works on home energy efficiency retrofitting, such as retrofit officers or project managers across the council area, for 3 or more days per week (0.6+ FTE)? This can include both directly employed and contracted staff, provided they work 3 or more days per week (0.6 FTE). The work of this officer may include working on any retrofit projects, including council buildings, council homes or private rented or owned households.
Please list any roles that work in this area, including the full time equivalent (FTE) if they work part time.
Please include staff members that are shared with other councils, such as between county and district councils, and note if they are shared across other areas.
3. How many planning ecologists (ecologists within the planning department) or equivalent working for 3 or more days per week (0.6+ FTE) does the council employ to scrutinise planning reports for Biodiversity Net Gain? This can include both directly employed and contracted staff, provided they work 3 or more days per week (0.6 FTE).
Our response
Please sees attached
Complaints
I hope this information is helpful but if you are unhappy with the service you have received in relation to your request and wish to make a complaint or request a review, you should write to Information Management, at either [Cambridgeshire County Council request email] or by post at Box No. SCO2306, Cambridgeshire County Council, Scott House, 5 George Street, Huntingdon, PE29 3AD within 40 days of the date of this e-mail.
If you are not content with the outcome of the internal review, you have the right to apply directly to the Information Commissioner for a decision. The Information Commissioner can be contacted at: Information Commissioner's Office, Wycliffe House, Water Lane, Wilmslow, Cheshire, SK9 5AF, or via their website: https://ico.org.uk/.
Generally, the ICO will not undertake a review or make a decision on a request until the internal review process has been completed.
Yours sincerely
David Sayers
Information Management Analyst
Information Governance Team
Cambridge County Council
Box No: SCO2306
Scott House
5 George Street
Huntingdon
PE29 3AD
01223 699137