Dear Staffordshire County Council,

Please treat this as a Freedom of Information/Environmental Information Regulations request.

I would like information about your council’s electricity sources in relation to climate action for the Council Climate Action Scorecards. This information may be held by an estates department or similar.

In particular, please supply me with information relating to the following questions:

a. Does the council have a 100% renewable green electricity tariff for all of the electricity that the council is directly responsible for, and is this tariff with Green Energy UK plc, Good Energy Limited or Ecotricity?
This includes all electricity that the council is directly responsible for, in council offices and any other buildings leased and managed by the council where the council pays the electricity tariff. This does not include homes owned or managed by the council. If unsure, please state your provider and tariff.

b. Does the council generate and use energy from waste? And if so, what percentage of the council’s total electricity use is powered by these energy from waste electricity sources?

c. Does the council buy directly from a local renewable electricity source or have its own renewable electricity sources? And if so, what percentage of the council's total electricity use is powered by this/these renewable electricity sources?
This includes council owned renewable electricity sources that are located outside of the council area, such as solar farms located further south to maximise electricity generation.

I look forward to hearing from you in due course.

Yours faithfully,

Hannah Jewell, Climate Emergency UK

Staffordshire County Council

Dear Hannah Jewell
 
Thank you for your multiple requests about climate change action received
by Staffordshire County Council on 17/01/2023. 
These have been collated and will be dealt with as one single request.
Therefore replies will not be sent separately to each of the
WhatDoTheyKnow email addresses.

Your request is being dealt with and a response will be sent to you within
twenty working days. 

If you have any queries about this request do not hesitate to contact us.
Please remember to quote the case reference number above in any future
communications.
Yours sincerely

Access to Information Team

Corporate Services

1 Staffordshire Place

Tipping Street Stafford ST16 2DH

Email: [1][Staffordshire County Council request email]

[2]www.staffordshire.gov.uk

References

Visible links
1. mailto:[Staffordshire County Council request email]
2. http://www.staffordshire.gov.uk/

Portch, David (Corporate), Staffordshire County Council

3 Attachments

Dear Hannah Jewell

 

Thank you for your request for information.

 

Firstly, please accept my apologies for the delay in being able to provide
you with a full response within the 20 working day deadline.

 

Information provided by service teams so far is included within the
attachment. As far as I can see it is only your first question that
remains unanswered. Unfortunately, despite sending request due reminders
our highways service left it until the deadline before notifying the
Access to Information Team that information to answer this question is not
held but may be held by our contracted highways partner. I hope that we
will be in a position to provide an answer to the following soon.

 

a. Has the Council approved any new*1 or expanded*2 roads or road
junctions in its area from 1st January 2019 until 1st January 2023? Please
list which ones were accepted.

 

*1 The intention of this question is to understand overall increases in
road capacity, rather than recent housing developments. Please exclude
minor roads built exclusively to connect new housing to the pre-existing
road network.

 

*2 An expanded road or road junction is one that has increased capacity
for motor vehicle traffic, not counting bus lanes, cycle infrastructure,
or pedestrian infrastructure. Please include roads and junctions where new
lanes have been added.

 

 

If you have any comments relating to how your request has been handled by
our authority you should contact us in the first instance. Send your
comment or complaint to:

 

Access to Information Team Manager, Access to Information Team,
Staffordshire County Council, 1 Staffordshire Place, Stafford ST16 2DH or
email [1][Staffordshire County Council request email]

 

If you then have any further comments relating to how your request has
been handled by our authority, please contact the Information
Commissioner, Wycliffe House, Water Lane, Wilmslow, Cheshire SK9 5AF, or
[2]Make a complaint | ICO

 

 

Regards

  

David Portch

 

[3]A picture containing  
graphical user interface
Description automatically David Portch │Information Asset Officer
generated
Access to Information Team – Corporate Services

1 Staffordshire Place

Tipping Street Stafford ST16 2DH

Email: [4][email address]

[5]www.staffordshire.gov.uk

 

 

 

From: [Staffordshire County Council request email]
<[Staffordshire County Council request email]>
Sent: 17 January 2023 10:32
To: [FOI #937531 email]
Subject: Your Freedom of Information request case reference F0009259

 

Dear Hannah Jewell

Thank you for your multiple requests about climate change action received
by Staffordshire County Council on 17/01/2023.

 

These have been collated and will be dealt with as one single request.
Therefore replies will not be sent separately to each of the
WhatDoTheyKnow email addresses.

Your request is being dealt with and a response will be sent to you within
twenty working days.

If you have any queries about this request do not hesitate to contact us.
Please remember to quote the case reference number above in any future
communications.

 

Yours sincerely

 

Access to Information Team

Corporate Services

1 Staffordshire Place

Tipping Street Stafford ST16 2DH

Email: [6][Staffordshire County Council request email]

[7]www.staffordshire.gov.uk

 

 

Disclaimer

This e-mail (including any attachments) is only for the person or
organisation it is addressed to. If you are not the intended recipient you
must let me know immediately and then delete this e-mail. If you use this
e-mail without permission, or if you allow anyone else to see, copy or
distribute the e-mail, or if you do, or don't do something because you
have read this e-mail, you may be breaking the law.

Liability cannot be accepted for any loss or damage arising from this
e-mail (or any attachments) or from incompatible scripts or any virus
transmitted.

E-mails and attachments sent to or received from staff and elected Members
may be monitored and read and the right is reserved to reject or return or
delete any which are considered to be inappropriate or unsuitable.

Do you really need to print this email? It will use paper, add to your
waste disposal costs and harm the environment.

References

Visible links
1. mailto:[Staffordshire County Council request email]
2. https://ico.org.uk/make-a-complaint/
4. mailto:[email address]
5. http://www.staffordshire.gov.uk/
6. mailto:[Staffordshire County Council request email]
7. http://www.staffordshire.gov.uk/

Portch, David (Corporate), Staffordshire County Council

2 Attachments

Dear Hannah Jewell

 

Further to my email below the service has now located some additional
information and send their apologies for the delay. I understand that this
is because the information is not held in such a way that it can be
reported/extracted from a system and they have had to trawl through
records of potentially relevant schemes.

 

The following highway capacity improvements have been delivered since
2019:

 

-       Lichfield Southern Bypass

-       Stafford  Western Access Road

-       I54 junction access on  M54

-       A34 Redhill Marden Grange – widened junction

-       A543 Sutton Rd/B4151 Slade Rd, Mile Oak

-       Kidsgrove Town Centre  improvements

-       A5121 Derby Rd/A511 Horninglow Street, Burton

-       A5189 Evershead Way/Shobnall Rd, Burton

-       A5189 Orchard Street roundabout, Burton

-       A460 Eastern Way Cannock

-       MGOV Churchbridge supervision

-       A5127 Lichfield – capacity improvements at key junctions

-       Stubwood Ln/Oak Rd/Lady Meadow, Rocester

-       Branston Interchange Imps

-       A53 Transport Corridor Improvements

-       A34 Lower Street/ Enderley St

-       Upper Gungate/Aldergate corridor, Tamworth

-       Birmingham Rd/Falkland Rd, Lichfield – junction imps and
carriageway widening

-       A50 Project A

 

However, please note that there may be some other schemes for which the
service has not been able to locate information within the appropriate
limit (18 hours).

 

 

If you have any comments relating to how your request has been handled by
our authority you should contact us in the first instance. Send your
comment or complaint to:

 

Access to Information Team Manager, Access to Information Team,
Staffordshire County Council, 1 Staffordshire Place, Stafford ST16 2DH or
email [1][Staffordshire County Council request email]

 

If you then have any further comments relating to how your request has
been handled by our authority, please contact the Information
Commissioner, Wycliffe House, Water Lane, Wilmslow, Cheshire SK9 5AF, or
[2]Make a complaint | ICO

 

 

Regards

  

David Portch

 

[3]A picture containing  
graphical user interface
Description automatically David Portch │Information Asset Officer
generated
Access to Information Team – Corporate Services

1 Staffordshire Place

Tipping Street Stafford ST16 2DH

Email: [4][email address]

[5]www.staffordshire.gov.uk

 

 

 

From: Portch, David (Corporate)
Sent: 15 February 2023 09:07
To: [FOI #937531 email]
Subject: F0009259 Partial Response

 

Dear Hannah Jewell

 

Thank you for your request for information.

 

Firstly, please accept my apologies for the delay in being able to provide
you with a full response within the 20 working day deadline.

 

Information provided by service teams so far is included within the
attachment. As far as I can see it is only your first question that
remains unanswered. Unfortunately, despite sending request due reminders
our highways service left it until the deadline before notifying the
Access to Information Team that information to answer this question is not
held but may be held by our contracted highways partner. I hope that we
will be in a position to provide an answer to the following soon.

 

a. Has the Council approved any new*1 or expanded*2 roads or road
junctions in its area from 1st January 2019 until 1st January 2023? Please
list which ones were accepted.

 

*1 The intention of this question is to understand overall increases in
road capacity, rather than recent housing developments. Please exclude
minor roads built exclusively to connect new housing to the pre-existing
road network.

 

*2 An expanded road or road junction is one that has increased capacity
for motor vehicle traffic, not counting bus lanes, cycle infrastructure,
or pedestrian infrastructure. Please include roads and junctions where new
lanes have been added.

 

 

If you have any comments relating to how your request has been handled by
our authority you should contact us in the first instance. Send your
comment or complaint to:

 

Access to Information Team Manager, Access to Information Team,
Staffordshire County Council, 1 Staffordshire Place, Stafford ST16 2DH or
email [6][Staffordshire County Council request email]

 

If you then have any further comments relating to how your request has
been handled by our authority, please contact the Information
Commissioner, Wycliffe House, Water Lane, Wilmslow, Cheshire SK9 5AF, or
[7]Make a complaint | ICO

 

 

Regards

  

David Portch

 

[8]A picture containing  
graphical user interface
Description automatically David Portch │Information Asset Officer
generated
Access to Information Team – Corporate Services

1 Staffordshire Place

Tipping Street Stafford ST16 2DH

Email: [9][email address]

[10]www.staffordshire.gov.uk

 

 

 

From: [11][Staffordshire County Council request email]
<[12][Staffordshire County Council request email]>
Sent: 17 January 2023 10:32
To: [13][FOI #937531 email]
Subject: Your Freedom of Information request case reference F0009259

 

Dear Hannah Jewell

Thank you for your multiple requests about climate change action received
by Staffordshire County Council on 17/01/2023.

 

These have been collated and will be dealt with as one single request.
Therefore replies will not be sent separately to each of the
WhatDoTheyKnow email addresses.

Your request is being dealt with and a response will be sent to you within
twenty working days.

If you have any queries about this request do not hesitate to contact us.
Please remember to quote the case reference number above in any future
communications.

 

Yours sincerely

 

Access to Information Team

Corporate Services

1 Staffordshire Place

Tipping Street Stafford ST16 2DH

Email: [14][Staffordshire County Council request email]

[15]www.staffordshire.gov.uk

 

 

Disclaimer

This e-mail (including any attachments) is only for the person or
organisation it is addressed to. If you are not the intended recipient you
must let me know immediately and then delete this e-mail. If you use this
e-mail without permission, or if you allow anyone else to see, copy or
distribute the e-mail, or if you do, or don't do something because you
have read this e-mail, you may be breaking the law.

Liability cannot be accepted for any loss or damage arising from this
e-mail (or any attachments) or from incompatible scripts or any virus
transmitted.

E-mails and attachments sent to or received from staff and elected Members
may be monitored and read and the right is reserved to reject or return or
delete any which are considered to be inappropriate or unsuitable.

Do you really need to print this email? It will use paper, add to your
waste disposal costs and harm the environment.

References

Visible links
1. mailto:[Staffordshire County Council request email]
2. https://ico.org.uk/make-a-complaint/
4. mailto:[email address]
5. http://www.staffordshire.gov.uk/
6. mailto:[Staffordshire County Council request email]
7. https://ico.org.uk/make-a-complaint/
9. mailto:[email address]
10. http://www.staffordshire.gov.uk/
11. mailto:[Staffordshire County Council request email]
12. mailto:[Staffordshire County Council request email]
13. mailto:[FOI #937531 email]
14. mailto:[Staffordshire County Council request email]
15. http://www.staffordshire.gov.uk/