Cost and purpose of the Westbere Railway Crossing Modification

Nicola Mills made this Freedom of Information request to Kent County Council

This request has been closed to new correspondence from the public body. Contact us if you think it ought be re-opened.

The request was partially successful.

Dear Kent County Council,

Please supply details in response to the following FOI request. I previously submitted the request to Canterbury City Council and was told they did not have the information, and that I was to contact KCC.

In Westbere there is one place where a public footpath crosses the railway. In the last 2 years it was modified in a manner which increased the length and was highly fenced off. With regards to this please answer the following specific questions:

1. State the reasons why this work was needed.
2. What public consultation was undertaken to inform this need.
3. A breakdown of expenditure of the works to date, including details of all parties contracted.
4. What future expenditure is foreseen for this project.
5. What is the annual maintenance cost.
6. What was the annual maintenance cost of the old crossing (prior to modification).

Yours faithfully,

Nicola Mills

Kent County Council

Dear Ms Mills

 

Thank you for your email below.

 

Kent County Council acknowledges your request for information under the
Freedom of Information Act 2000. Assuming KCC holds this information, we
will endeavour to supply the data to you as soon as possible but no later
than 16^th May 2017 (20 working days from date of receipt).

 

We will advise you as soon as possible if we do not hold this information
or if there are exemptions to be considered and/or any costs for providing
the information. Please quote our reference - FOI/17/0691 - in any
communication regarding this particular request.

 

Best regards

 

Carly Wattle | Information Access Officer | Information Resilience &
Transparency Team | Kent County Council | Room 2.71, Sessions House,
Maidstone, ME14 1XQ | Phone 03000 417061 | Fax 03000 420303 | 
[1]http://www.kent.gov.uk/about-the-council...
|

--------------------------------------------------------------------------

show quoted sections

Kent County Council

Dear Ms Mills

 

Thank you for your request for information made under the Freedom of
Information Act (FOIA) 2000, relating to the diversion of Public Footpath
CB92. I am pleased to provide the response below:

 

1.    State the reasons why this work was needed.

The County Council received an application from Network Rail to divert
Public Footpath CB92 at Westbere to provide a safer crossing point. The
application was made under the provisions of the Highways Act 1990 section
119A in the interests of the safety of members of the public using the
crossing. The work was required to provide the new crossing point and
access to it, following the successful confirmation of the order to divert
the crossing.

 

2.    What public consultation was undertaken to inform this need.

Kent County Council consulted in line with the requirements set out in
schedule 6 of the Highways Act 1980, details of which may be found here:
[1]http://www.legislation.gov.uk/ukpga/1980....

Consultation included statutory undertakers, user groups and landowners as
well as publication of notices in the local press and on site. The County
Council cannot provide information about any consultation that Network
Rail may have undertaken prior to submitting its application as this
information is not held.

However we advise if you have not already to contact Network Rail directly
using the provided link:
[2]https://www.networkrail.co.uk/who-we-are...

 

3.    A breakdown of expenditure of the works to date, including details
of all parties contracted.

The work was undertaken by Network Rail, Kent County Council does not hold
this information.

 

4.    What future expenditure is foreseen for this project.

The crossing and approaches are maintained by Network Rail. Kent County
Council does not hold this information.

 

5.    What is the annual maintenance cost.

The crossing and approaches are maintained by Network Rail. Kent County
Council does not hold this information.

 

6.    What was the annual maintenance cost of the old crossing (prior to
modification).

The old crossing was maintained by Network Rail, the County Council does
not hold this information.

 

If you are unhappy with this response, and believe KCC has not complied
with legislation, please ask for a review by following our complaints
process; details can be found at this link
[3]http://www.kent.gov.uk/about-the-council...
on our website. Please quote reference FOI/17/0691.

 

If you still remain dissatisfied following an internal review, you can
appeal to the Information Commissioner, who oversees compliance with the
Freedom of Information Act 2000. Details of what you need to do, should
you wish to pursue this course of action, are available from the
Information Commissioner’s website [4]http://www.ico.org.uk/concerns.

 

Yours sincerely

 

Kirsty-Leigh Robertson| Information Access Officer | Information
Resilience & Transparency Team | Room 2.71, Sessions House, Maidstone |
Phone 03000 418301 | Fax 03000 420303 |
[5]http://www.kent.gov.uk/about-the-council...
|

 

show quoted sections

Looking for an EU Authority?