Dear Sutton Borough Council,

This is to ask for:

1. Copies of all correspondence between Sutton Council officers and/or members and Viridor and/or its representatives

2. Minutes of meetings between Sutton Council officers and/or members and Viridor and/or its representatives

since 1 January 2017 in relation to implementation of the planning conditions for Viridor's Beddington Energy Recovery Facility relating to conservation management and restoration of Beddington Farmlands.

Yours faithfully,

Tony Burton

LBS FOI, Sutton Borough Council

Dear Mr Burton
FREEDOM OF INFORMATION ACT 2000 - INFORMATION REQUEST - REF NO -
F12101 (please quote in correspondence)
I acknowledge your request for information dated 22nd March 2018
Your request is being considered and, if it is held, you will receive the
information requested within the statutory timescale of 20 working days as
defined by the Freedom of Information Act 2000, subject to the information
not being exempt or containing a reference to a third party.
If appropriate, the information may be provided in paper copy, normal font
size.  If you require alternative formats, e.g. language, audio, large
print, etc. then please let us know.
For your information, the Act defines a number of exemptions which may
prevent release of the information you have requested.  There will be an
assessment and if any of the exemption categories apply then the
information will not be released.  You will be informed if this is the
case, including your rights of appeal.
If the information you request contains reference to a third party then
they may be consulted prior to a decision being taken on whether or not to
release the information to you.  You will be informed if this is the case.
A fee may be payable for this information.  This will be considered and
you will be informed if a fee is payable.  In this event the fee must be
paid before the information is processed and released.  The 20 working day
time limit is suspended until receipt of the payment.
Please be advised that in line with London Borough of Sutton's commitment
to transparency, in due course an anonymous copy of your request and our
response may be published on our website.
Yours sincerely
FOI Admin Officer
London Borough of Sutton

show quoted sections

Andy Webber, Sutton Borough Council

Dear Sir/Madam
I am writing in relation to the above freedom of information request.
I wish to inform you that the Council is responding to this request but is
unable to meet the deadline of 24 April 2018. 
As such, we are writing to inform you that we will endeavour to respond as
soon as possible after that date and, in any event, no later than 27 April
2018.
I hope that this has been of assistance in the meantime.
Yours sincerely

Andy Webber
Head of Development Management and Strategic Planning

Environment, Housing and Regeneration

London Borough of Sutton

24 Denmark Road, Carshalton SM5 2JG

T: 020 8770 6119
M: 07738 349175

[1]www.sutton.gov.uk

Follow us on [2]LinkedIn | [3]Twitter | [4]Facebook

Disclaimers apply, for full details see : 
(https://www.sutton.gov.uk/info/200436/cu...)

References

Visible links
1. http://www.sutton.gov.uk/
2. https://www.linkedin.com/company/london-...
3. https://twitter.com/SuttonCouncil?ref_sr...
4. https://facebook.com/SuttonCouncil

Andy Webber, Sutton Borough Council

Dear Sir/Madam
I am writing further to my email below.
I am sorry to advise that it is taking longer than anticipated to collect
the information you have requested and we 
will be delayed in responding until week beginning 30 April 2018.  
We will provide you with this information as soon as possible next week.
Yours sincerely

Andy Webber
Head of Development Management and Strategic Planning

Environment, Housing and Regeneration

London Borough of Sutton

24 Denmark Road, Carshalton SM5 2JG

T: 020 8770 6119
M: 07738 349175

[1]www.sutton.gov.uk

Follow us on [2]LinkedIn | [3]Twitter | [4]Facebook

show quoted sections

Andy Webber, Sutton Borough Council

3 Attachments

Dear Sir/Madam

FREEDOM OF INFORMATION ACT 2000 - INFORMATION REQUEST - REF NO - F12101

I refer to your request for information received on 22 March 2018
concerning correspondence relating to the planning conditions for
Viridor's Beddington energy Recovery Facility relating to conservation
management and restoration

of Beddington Farmlands; all from January 2017.


[1][IMG][2] DW Correspondence 2018 - Redacted.pdf

Further to my previous emails advising that there would be a delay in
replying, I attach three pdf documents and a google link (the file size
does not permit this being sent as a pdf) which cover the request you have
made.

If you are unhappy with the way in which your request has been handled you
have the right to ask for an internal review.  Please notify us in writing
as soon as possible with the grounds upon which you feel the appeal is
justified to : [3][Sutton Borough Council request email]  or by post to Customer Care and
Improvement Team, Civic Offices, St Nicholas Way, Sutton, Surrey, SM1 1EA.

We aim to respond to you within 20 working days of receiving your request.
If it is going to take longer we will let you know.

Should you still be dissatisfied with the outcome you have the right to
refer to the Information Commissioner: Wycliffe House, Water Lane,
Wilmslow, Cheshire, SK9 5AF [4]www.ico.org.uk

Yours sincerely

Andy Webber
Head of Development Management and Strategic Planning

Environment, Housing and Regeneration

London Borough of Sutton

24 Denmark Road, Carshalton SM5 2JG

T: 020 8770 6119
M: 07738 349175

[5]www.sutton.gov.uk

Follow us on LinkedIn | Twitter | Facebook

Disclaimers apply, for full details see : 
(https://www.sutton.gov.uk/info/200436/cu...)

References

Visible links
1. https://drive.google.com/a/sutton.gov.uk...
2. https://drive.google.com/a/sutton.gov.uk...
3. mailto:[Sutton Borough Council request email]
4. http://www.ico.org.uk/
5. http://www.sutton.gov.uk/