Dear Belfast Education and Library Board (Northern Ireland),

I am currently looking into performance of public sector
construction projects for a study that I am undertaking. Please
can you give me a list of all construction projects (>£100k)
completed in the last 5 years with the following information:

Name/ description of project
Tier 1 Contractor
location of project
Contract form
Framework Name if Applicable
type of work - ie refurbishment/ new build/ fit out/
Contract price for construction
Final price for construction
Construction start date
Initial construction completion date
Actual construction completion date

I would also like this request to be considered under the
Environmental Information Regulations 2004.

Yours faithfully,

Ms Z K Lovett

Sent request to Belfast Education and Library Board (Northern Ireland) again.

Info(BELB), Belfast Education and Library Board (Northern Ireland)

1 Attachment

Thank you for your enquiry. It has been forwarded to the appropriate board
officers. Please refer to the attachment advising how your request will be
handled.
 
PLEASE NOTE: I have been advised by the site, what do they know .com that
this request was originally sent to us in JANUARY 2013.  I can confirm
that BELB did not receive this request- the first time I became aware of
the request was when I looked  at  their web site and noticed it reported
"long overdue" against the request!  I do not understand- if no
acknowledgement or response was received from JANUARY 2013 why the site
did not query what was happening ? Can you let me have a copy of the
original request to show date, time and to whom sent, to enable me to
establish what happened? Thanks
 
Liz Johnston
FOI Manager
028 90564316
 
 
 

show quoted sections

Liz Johnston, Belfast Education and Library Board (Northern Ireland)

2 Attachments

 
I have received the attached response to your information request. I
apologise for the delay however the original request  (January 2013) 
apparently submitted by the agency you used was not received  and we did
not at any stage receive an enquiry as to why we had not acknowledged the
request or failed to respond within the statutory period. I hope the
attached information is helpful.
 
 
Liz Johnston
FOI Manager
028 90564316
 
 
 
 
_____________________________________________

show quoted sections

Dear Liz.

Thanks so much for responding to my query. I hadn't got around to chasing you so the length of time is partly my fault too.

I would just like to ask one clarification question please. can you tell me which contract form you use for the non PFI projects and whether you have lump sum, target price or another way of agreeing price. (I suppose that's 2 clarifications really - a degree in Mathematics and I still can't count!)

Kind regards

Zerrin

Geoff Connor, Belfast Education and Library Board (Northern Ireland)

Zerrin

 

Further to your query below, apologies for the delay in responding – as
follows

 

The non PFI contracts are procured under a Design and Build Target Cost
Form of Contract

 

Hope this helps

 

Thanks

Geoff

 

 

Dear Liz.

 

Thanks so much for responding to my query.  I hadn't got around to chasing
you so the length of time is partly my fault too.

 

I would just like to ask one clarification question please.  can you tell
me which contract form you use for the non PFI projects and whether you
have lump sum, target price or another way of agreeing price. (I suppose
that's 2 clarifications really - a degree in Mathematics and I still can't
count!)

 

Kind regards

 

Zerrin

 

 

 

Geoff Connor

Capital Development Manager

Belfast Education & Library Board

 