Dear Poole Borough Council,

It is understood that the paddling pool in Hamworthy Park is to be refurbished.

How is it possible to arrange for a member of the affected public to obtain sight of the relevant construction details to be implemented and the associated briefing material (including any budgetary constraints) that has led to the adopted design approach ?

Yours faithfully,

Gerald Rigler

Strategy Team - Information, Poole Borough Council

Link: [1]File-List

Thank you for your email.

 

Requests submitted under the Freedom of Information Act and Environmental
Information Regulations will be responded to within 20 working days.

 

Reviews of our responses to Freedom of Information or Environmental
Information Regulation requests will also be responded to within 20
working days.

 

Requests for personal information under Subject Access Request will be
responded to within 30 calendar days once we have received all the
[2]information required.

 

If we need more time to respond to any request for any of the above, we
will contact you to advise you.

 

 

DISCLAIMER: This email and any files transmitted with it may be
confidential, legally privileged and protected in law and are intended
solely for the use of the individual to whom it is addressed. The
copyright in all documentation is the property of the Borough of Poole and
this email and any documentation must not be copied or used other than as
strictly necessary for the purpose of this email, without prior written
consent which may be subject to conditions. Any view or opinions presented
are solely those of the author and do not necessarily represent those of
the Borough of Poole. The Borough of Poole reserves the right to inspect
incoming and outgoing emails. If you have received this email in error
please contact the sender by return and confirm that its contents have
been destroyed.

References

Visible links
1. file:///tmp/cid:filelist.xml@01D41463.3D92DDA0
2. http://archive.poole.gov.uk/your-council...

Culture & Community - Recreation Development, Poole Borough Council

7 Attachments

Dear Gerald,

 

Thank you for getting in touch regarding Hamworthy Park paddling pool.

 

I am pleased to share with you our construction drawings as follows;

 

·         0011 – PROPOSED GENERAL ARRANGEMENT

·         0021 – CENTRAL SECTION CONCRETE OUTLINE AND REINFORCEMENT
DETAILS

·         0022 – OUTER SEGMENT TYPE A CONCRETE OUTLINE AND REINFORCEMENT
DETAILS

·         0023 – OUTER SEGMENT TYPE B CONCRETE OUTLINE AND REINFORCEMENT
DETAILS

·         0024 – OUTER SEGMENT TYPE C CONCRETE OUTLINE AND REINFORCEMENT
DETAILS

·         0031 – PILE SETTING LAYOUT

·         0041 – SLAB JOINTS & FINISHING DETAILS

 

Construction began on site earlier this week, and the works, costing
£381,000, will be completed before the coming summer.

 

I hope the above helps to answer your questions.

 

Kind regards,

 