Considerations and costs for barriers on cycle route off Thoresby Road, Malin Bridge

The request was successful.

Dear Sheffield City Council,

Please can you supply the considerations which were made for equality of opportunity for access when deciding to install barriers on the cycle route between Thoresby Road and Watersmeet Road in Malin Bridge; and when these barriers were decided on and installed.

For context, the report in 2012 of the planning application for this route included the reference: "Clearly, the concept of opening up a footpath to cycle use does have implications for pedestrian users of the path and, in particular, disabled people."
http://sheffielddemocracy.moderngov.co.u...

I would also like to know the cost each of:
- the path upgrade work in total
and
- the barriers at the Thoresby Road end.

Yours faithfully,

Sam Wakeling

FOI, Sheffield City Council

Re – Freedom of Information Request – Reference – FOI / 2443
 
Dear Sam Wakeling
 
Thank you for your recent request for information relating to
Considerations and costs for barriers on cycle route off Thoresby Road,
Malin Bridge which we received on 15/08/2016
 
This has been logged as a Freedom of Information Request, and will be
dealt with under the Freedom of Information Act.  The reference number for
your request can be found above.
 
The Freedom of Information Act states that we must respond to you within
20 working days, therefore, you should expect to hear a response from us
by 13/09/2016.
 
In the meantime, if you have any queries please contact us on the number
below.
 
Thank you.
 
Yours sincerely,
 
Resources Business Support
Moorfoot Level 8 West Wing
Sheffield S1 4PL
Tel : 0114 20 53478
E-mail : [1]FOI @sheffield.gov.uk
? Please don't print this e-mail unless you really need to
 
 
_____________________________________________
From: Sam Wakeling [[2]mailto:[FOI #351657 email]]
Sent: 13 August 2016 11:55
To: FOI
Subject: Freedom of Information request - Considerations and costs for
barriers on cycle route off Thoresby Road, Malin Bridge
 
 
 
Dear Sheffield City Council,
 
Please can you supply the considerations which were made for equality of
opportunity for access when deciding to install barriers on the cycle
route between Thoresby Road and Watersmeet Road in Malin Bridge; and when
these barriers were decided on and installed.
 
For context, the report in 2012 of the planning application for this route
included the reference: "Clearly, the concept of opening up a footpath to
cycle use does have implications for pedestrian users of the path and, in
particular, disabled people."
[3]http://sheffielddemocracy.moderngov.co.u...
 
I would also like to know the cost each of:
- the path upgrade work in total
and
- the barriers at the Thoresby Road end.
 
Yours faithfully,
 
Sam Wakeling
 
-------------------------------------------------------------------
 
Please use this email address for all replies to this request:
[4][FOI #351657 email]
 
Is [5][Sheffield City Council request email] the wrong address for Freedom of Information
requests to Sheffield City Council? If so, please contact us using this
form:
[6]https://www.whatdotheyknow.com/change_re...
 
Disclaimer: This message and any reply that you make will be published on
the internet. Our privacy and copyright policies:
[7]https://www.whatdotheyknow.com/help/offi...
 
For more detailed guidance on safely disclosing information, read the
latest advice from the ICO:
[8]https://www.whatdotheyknow.com/help/ico-...
 
If you find this service useful as an FOI officer, please ask your web
manager to link to us from your organisation's FOI page.
 
 

show quoted sections

FOI, Sheffield City Council

Re – Freedom of Information Request – Reference – FOI / 2443
 
Dear Sam Wakeling
 
Thank you for your recent request for information relating to
Considerations and costs for barriers on cycle route off Thoresby Road,
Malin Bridge which we received on 15/08/2016
 
Please find below, Sheffield City Council’s response to your request:
 
The total cost of the works to create the Watersmeet Cycle/Footway was
£48,903.
The cost of the barrier itself was  £5101.
The type of barrier was instructed by SCC Public Rights of Way Officer,
this being the only access control barrier approved by the councils
Disabled Access Liaison Group.
The barriers were installed during April 2016.
 
I hope the information we have provided is of help to your enquiries.  If
you have any queries about this response, please do not hesitate to
contact us.
 
If you are unhappy with the response you have received in relation to your
request, you are entitled to have this reviewed.  You can ask for an
internal review by either writing to the above address or by emailing
[1][Sheffield City Council request email].
 
If you remain dissatisfied with the outcome of your internal review, you
can contact the Information Commissioners Office. The Information
Commissioner can be contacted at: The Information Commissioner's Office,
Wycliffe House, Water Lane, Wilmslow, Cheshire SK9 5AF, telephone 0303 123
1113, or for further details see their website [2]www.ico.org.uk
 
Kind Regards,
 
Resources Business Support
Moorfoot Level 8 West Wing
Sheffield S1 4PL
Tel : 0114 20 53478
E-mail : [3]FOI @sheffield.gov.uk
? Please don't print this e-mail unless you really need to
 
 
_____________________________________________
From: Sam Wakeling [[4]mailto:[FOI #351657 email]]
Sent: 13 August 2016 11:55
To: FOI
Subject: Freedom of Information request - Considerations and costs for
barriers on cycle route off Thoresby Road, Malin Bridge
 
 
 
Dear Sheffield City Council,
 
Please can you supply the considerations which were made for equality of
opportunity for access when deciding to install barriers on the cycle
route between Thoresby Road and Watersmeet Road in Malin Bridge; and when
these barriers were decided on and installed.
 
For context, the report in 2012 of the planning application for this route
included the reference: "Clearly, the concept of opening up a footpath to
cycle use does have implications for pedestrian users of the path and, in
particular, disabled people."
[5]http://sheffielddemocracy.moderngov.co.u...
 
I would also like to know the cost each of:
- the path upgrade work in total
and
- the barriers at the Thoresby Road end.
 
Yours faithfully,
 
Sam Wakeling
 
-------------------------------------------------------------------
 
Please use this email address for all replies to this request:
[6][FOI #351657 email]
 
Is [7][Sheffield City Council request email] the wrong address for Freedom of Information
requests to Sheffield City Council? If so, please contact us using this
form:
[8]https://www.whatdotheyknow.com/change_re...
 
Disclaimer: This message and any reply that you make will be published on
the internet. Our privacy and copyright policies:
[9]https://www.whatdotheyknow.com/help/offi...
 
For more detailed guidance on safely disclosing information, read the
latest advice from the ICO:
[10]https://www.whatdotheyknow.com/help/ico-...
 
If you find this service useful as an FOI officer, please ask your web
manager to link to us from your organisation's FOI page.
 
 

show quoted sections