Dear Middlesbrough Council,

1) Do you have a Climate Change Adaptation Strategy and/or Policy (or similar)? If so please attach.

2) Has this document been adopted by Council or Cabinet (or similar), if so, when?

3) Has a Councillor been assigned to champion this Strategy/Policy (or similar), if so, who?

4) Is the strategy/policy (or similar) supported by an action/programme/project plan? If so, please attach.

5) Is this plan delivering on time and to budget?

6) What are those timescales and budget?

7) Are progress reports provided to Cabinet/Council (or similar), if so, please attach.

Yours faithfully,

Tom Cole

Middlesbrough Council

Dear Mr Cole

REF NO:  4377.1

Thank you for your recent enquiry, received on 17/02/2014, in relation to
Climate Change Adaptation Strategy.  I can confirm that your enquiry is
receiving attention and a response will be provided within 20 working days
following receipt of your enquiry as allowed under the Freedom of
Information Act legislation.

In some circumstances a fee may be payable and if that is the case, I will
let you know the likely charges before proceeding.

Please do not hesitate to contact me direct on (01642) 729696/729698 or
email [Middlesbrough Council request email] should you require any further advice or
assistance with this or any other matter.
Yours sincerely

Nathan Oxnard
Information Governance Assistant

show quoted sections

Middlesbrough Council

2 Attachments

Dear Mr Cole

REF NO:  4377.1
I am writing to confirm that Middlesbrough Council has now completed its
search for the information you requested on 17th February 2014.

In your request you asked for the following information:

1) Do you have a Climate Change Adaptation Strategy and/or Policy (or
similar)?  If so please attach.

Response: This is incorporated into our One Planet Living Action plan - a
copy of the document is attached below. Please note however this is
currently being rewritten to accommodate Council resources. Please also
note that Council Service plans also include Climate change adaptation
priorities too.

2) Has this document been adopted by Council or Cabinet (or similar), if
so, when?  
Response: Yes, this happened in November 2011.

3) Has a Councillor been assigned to champion this Strategy/Policy (or
similar), if so, who?  

Response: No, however the Mayor endorsed the One Planet Living plan
originally. We also have several of our Councillors that are closely
aligned to this work and are very supportive including the Deputy Mayor
Cllr David Budd. Cllr Julia Rostron (Chair of Middlesbrough Environment
City) and Executive Member for Environment Cllr Nicky Walker.

4) Is the strategy/policy (or similar) supported by an
action/programme/project plan? If so, please attach.

Response: Yes, priority actions are assigned each year to reflect the
commitments of the One Planet Living Action Plan and help delivery of the
programme.

5) Is this plan delivering on time and to budget?  

Response: The Plan is currently being reviewed and re-aligned to cope with
the challenges of resource and officer time. Initially progress of this is
very good and we hope to have a much more focused and practical plan in
place soon that will help us achieve all commitments    to climate
adaptation and sustainability.

6)  What are those timescales and budget?

Response:  The Plan has short, medium and long term actions/goals up to
2025.

7)  Are progress reports provided to Cabinet/Council (or similar), if so,
please attach.
Response:  An Annual Review is provided. A copy of the latest report is
attached below.

If you have any queries about this response, please do not hesitate to
contact me direct on (01642) 729696/729698 or email
[Middlesbrough Council request email].  Please remember to quote the reference number
shown above in any future communications.

If you are unhappy with the way your request has been handled you may ask
for an internal review within 40 days of receipt of the response. You
should write to:-
Sylvia Reynolds,
Information Governance Manager,
P.O. Box 503,
Ground Floor,
Town Hall,
Middlesbrough,
TS1 9FX
If you are not content with the outcome of the internal review, you have
the right to apply directly to the Information Commissioner for an
independent review.  The Information Commissioner can be contacted at: -
Information Commissioner’s Office,
Wycliffe House,
Water Lane,
Wilmslow,
Cheshire,
SK9 5AF
Yours sincerely

Steph Robson
Freedom of Information Officer

Members' Office
P.O. Box 503
Ground Floor
Town Hall
Middlesbrough
TS1 9FX

Tel.  01642 729696

FAX. 01642 729882
Email:   [Middlesbrough Council request email]
 

show quoted sections