Bus Shelter 01289171

Mr P Swift made this Freedom of Information request to Transport for London

Automatic anti-spam measures are in place for this older request. Please let us know if a further response is expected or if you are having trouble responding.

The request was successful.

Dear Transport for London,

Regarding the shelter, I ask to be provided:
1. The pre 03/2021 installation date and invoices relating to the purchase and installation i.e., the cost of the shelter and the cost of the labour to undertake the fitting
2. Details of the electrics installed; the invoices for these and the costs of the labour to undertake the fitting
3. The inspection reports from 01/01/2021 to 04/03/2021
4. Details of the components damaged when struck by a bus 02/03/2021 or 03/03/2021 and
5. The invoices for these replacement components
6. When the replacement commenced and when this concluded (dates/times)

Yours faithfully,

Mr P Swift

FOI, Transport for London

Dear Mr Swift

 

Our Ref:         FOI-0432-2122

 

Thank you for your request received on 2 June 2021 asking for information
about bus shelter 01289171.

 

We will aim to issue a response by 29 June 2021 in accordance with the
Freedom of Information Act 2000 and our information access policy. Please
think carefully about whether the request is essential at this current
time, as answering FOI requests will require the use of limited resources
and the attention of staff who could be supporting other essential
activity. Where requests are made, please note that our response time may
be impacted by the current situation and so you may wish to reconsider the
timing of this request. Please notify us as soon as possible if you would
like to withdraw your request at the current time.

 

We publish a substantial range of information on our website on subjects
including operational performance, contracts, expenditure, journey data,
governance and our financial performance. This includes data which is
frequently asked for in FOI requests or other public queries. Please check
[1]http://www.tfl.gov.uk/corporate/transpar... to see if this helps you.

 

We will publish anonymised versions of requests and responses on the
[2]www.tfl.gov.uk website. We will not publish your name and we will send
a copy of the response to you before it is published on our website.

 

In the meantime, if you would like to discuss this matter further, please
do not hesitate to contact me.

 

Yours sincerely

 

Gemma Jacob

Senior FOI Case Officer

FOI Case Management Team

General Counsel

Transport for London

 

[3][TfL request email]

 

 

show quoted sections

FOI, Transport for London

1 Attachment

Dear Mr Swift

 

Our Ref:         FOI-0432-2122

 

Thank you for your request received on 2 June 2021 asking for information
about bus shelter 01289171.

 

Your request has been considered in accordance with the requirements of
the Freedom of Information Act and our information access policy. I can
confirm we hold some of the information you require. You asked:

 

The pre 03/2021 installation date and invoices relating to the purchase
and installation i.e., the cost of the shelter and the cost of the labour
to undertake the fitting

 

The shelter was installed in December 2012. We are not able to provide
invoices as this was carried out using works orders from our Asset
Management system rather than through an order/invoice system and
therefore we do not hold any invoice documents. However we can provide
this information on cost. Parts: £4,964, Labour: £2,836.

 

Details of the electrics installed; the invoices for these and the costs
of the labour to undertake the fitting.

 

There is lighting installed at the shelter and a countdown unit both of
which have an electrical connection. As above we are not able to provide
invoices for this but can provide costs of labour for electrical
connection: £1,136.95. The cost of the lighting and countdown are part of
the wider shelter costs and we do not hold a breakdown of the labour cost
for this specific element of work.

 

The inspection reports from 01/01/2021 to 04/03/2021 – attached, please

 

No inspections have been carried out between these dates.

 

Details of the components damaged when struck by a bus 02/03/2021 or
03/03/2021 and the invoices for these replacement components

 

As above we do not hold an invoice document but can provide costs. We do
not have a breakdown of the costs of the components because the whole
shelter had to be replaced due to the damage caused in a collision. The
cost of the new shelter installed was £4,624.05 for parts and £4,847.44
for labour. Plus there was a charge of £1,391.23 to disconnect the
electricity from the shelter after being damaged in the collision

 

When the replacement commenced and when this concluded (dates/times)

 

The new shelter was installed on 16 April 2021.

 

If this is not the information you are looking for please feel free to
contact me.

 

Please see the attached information sheet for details of your right to
appeal.

 

Yours sincerely

 

Gemma Jacob

Senior FOI Case Officer

FOI Case Management Team

General Counsel

Transport for London

 

[1][TfL request email]

 

 

show quoted sections

Dear FOI,

Thank you for this.

Yours sincerely,

Mr P Swift