Dear all,

I hope you're well. It's Ashna here from Sky News.

I'm getting in touch with an FOI request to be used as part of a Sky News piece.

We'd appreciate a response as soon as possible.

Questions requiring response:

1) How many bridges on motorways or A-roads have sections which are in a "poor" or "very poor condition"?

2) How many pedestrian and highway bridges have reinforced autoclaved aerated concrete present within them and their fixtures?

3) In the past three years, how much has been spent on repairing and upgrading bridge structures to remove reinforced autoclaved aerated concrete from them?

4) In the past three years, how much has been spent on repairing and upgrading bridge structures?

I look forward to hearing from you.

Kind regards,
Ashna

Freedom Of Information (NELC), North East Lincolnshire Council

Dear Sir / Madam

 

I am pleased to acknowledge your request for information, which has been
allocated the reference number NELC/29857/2324.

Your request has been passed to the relevant department and you can expect
your response within the 20 working day limit. If it will take us longer
than 20 working days to respond to you, we will inform you of this and
provide you with the expected date for receiving a response.

 

Further information about how we will deal with your Freedom of
Information requests is available on our website at:

 

[1]https://www.nelincs.gov.uk/your-council/...

 

Please feel free to contact me if you require any further information or
assistance quoting the reference number above.

Yours sincerely

 

North East Lincolnshire Council

 

 

show quoted sections

Freedom Of Information (NELC), North East Lincolnshire Council

Dear Sir / Madam

 

Thank you for your information request, reference number NELC/29857/2324.
I can confirm that North East Lincolnshire Council holds the following
information:

1)    How many bridges on motorways or A-roads have sections which are in
a "poor" or "very poor condition"? 

4.

This is based on the Bridge Condition Index score of 65 or less (poor) or
where we do not have BCI scores engineering judgement has been used.

2)    How many pedestrian and highway bridges have reinforced autoclaved
aerated concrete present within them and their fixtures? 

0

3)    In the past three years, how much has been spent on repairing and
upgrading bridge structures to remove reinforced autoclaved aerated
concrete from them? 

£0

4)    In the past three years, how much has been spent on repairing and
upgrading bridge structures? 

£1.83 million

Please note the cost of repairs provided is expenditure on reactive
maintenance and planned maintenance undertaken through the Local Transport
Plan Delivery programme and does not include specific grant funded repair
works to highway bridges.  

If you believe that your request for information has not been handled in
accordance with the Freedom of Information Act, you have the right to
request an internal review by the Council. If you wish to request an
internal review, please write to us detailing the reasons why. Please be
clear about which elements of the Council’s response or handling of the
request you are unhappy with, and would like the Council to address during
the internal review process.  If following this you are still dissatisfied
you may contact the Office of the Information Commissioner.

 

Yours sincerely

 

North East Lincolnshire Council

 

 

 

show quoted sections

We don't know whether the most recent response to this request contains information or not – if you are Ashna Hurynag please sign in and let everyone know.