The original developer's viability report from December 2020 for application HS/FA/20/00970 stated that the development of 67 units could not support any affordable housing or infrastructure contributions under S106.

This was challenged by HBC Housing during consultation who requested that 26 affordable housing units were provided.

The Officer report to committee confirmed that the application would have 26 affordable housing units and infrastructure contributions. The report refers to an independent RICS valuer's assesment report which led to the developer providing 40% affordable housing (26 uniots and a financial contribution).

No further information was posted against the application from the developer to explain why the developer now considered affordable housing and infrastructure contributions to be acceptable in conflict with their December 2020 viability report.

The application was refused by the planning committee. The developer took the refusal to appeal and won permission for 67 units. The new permission retained infrastructure contributions but reduced the affordable housing contribution from 26 units to zero with HBC consent. There is no information posted against the appeal that explains why HBC changed their position and now considered that the application could not support any affordable housing.

I request the following under FOI:

1. All documents/correspondence between the developer and HBC concerning the change from zero to 26 affordable units following the submission of the Dec 2020 viability report.

2. All documents/correspondence between HBC departments concerning the change from zero to 26 affordable units following the submission of the Dec 2020 viability report.

3. All documents/correspondence between HBC and any other bodies concerning the change from zero to 26 affordable units following the submission of the Dec 2020 viability report.

4. A copy of the independent assesment of the viability report referred to in the officer's report to committee for HS/FA/20/00970.

5. All documents/correspondence between the developer and HBC concerning the reductions from 26 to zero affordable housing units following the refusal of the application.

6. All documents/correspondence between HBC departments concerning the reduction from 26 to zero affordable housing units following the refusal of the application.

7. All documents/correspondence between HBC and any other bodies concerning the reduction from 26 to zero affordable housing units following the refusal of the application.

8. Any documents/correspondence submitted to the appeal concerning affordable housing and infrastructure contributions.

9. Copies of all viability reports for the development at 777 the Ridge.

Yours faithfully,

Chris Hurrell

Information Officer, Hastings Borough Council

1 Attachment

Hastings Borough Council Christmas office closure
 
Council offices will be closed for the festive season from Friday 23
December 2022 (3pm) and will re-open on Tuesday 3 January 2022 (8.30am).
 
Please note that new Freedom of Information requests, queries, internal
reviews and responses to existing requests will not be dealt with during
this time.
 
Thank you for your Freedom of Information request.
 
We aim to respond to requests for information within 20 working days, in
accordance with the requirements of the Freedom of Information Act. 
 
If your request is for personal information (Subject Access request) your
request will be dealt with according to the requirements of the General
Data Protection Regulation (GDPR) and the timescale for response may be
extended to 40 days.
 
You can find out more information about [1]Freedom of Information as well
as all of the services the council provides on [2]our website.
 
Information Officer
Hastings Borough Council
01424 451066
[3]www.hastings.gov.uk
 
 
 
 
 
 
 
 
 

References

Visible links
1. https://www.hastings.gov.uk/my_council/f...
2. https://www.hastings.gov.uk/
3. file:///tmp/www.hastings.gov.uk

Dear Hastings Borough Council,

This request is now overdue. This information is relevant to an open planning application.

Please respond to this query as a matter of urgency.

Yours faithfully,

Chris Hurrell

Information Officer, Hastings Borough Council

1 Attachment

Thank you for your Freedom of Information request.
 
We aim to respond to requests for information within 20 working days, in
accordance with the requirements of the Freedom of Information Act. 
 
If your request is for personal information (Subject Access request) your
request will be dealt with according to the requirements of the General
Data Protection Regulation (GDPR) and the timescale for response may be
extended to 40 days.
 
You can find out more information about [1]Freedom of Information as well
as all of the services the council provides on [2]our website.
 
Information Officer
Hastings Borough Council
01424 451066
[3]www.hastings.gov.uk
 
 
 
 
 
 
 
 
 

References

Visible links
1. https://www.hastings.gov.uk/my_council/f...
2. https://www.hastings.gov.uk/
3. file:///tmp/www.hastings.gov.uk

Information Officer, Hastings Borough Council

5 Attachments

Dear Mr Hurrell
 
I refer to your recent Freedom of Information request ref: FOIR-469692705.
 
Please find attached our response.
 
 
 
Yours sincerely
 
Lisa Greathead
Information Officer
Hastings Borough Council
Muriel Matters House
Breeds Place
Hastings
TN34 3UY
01424 451722
 
[1][IMG]
 
 
 

References

Visible links
1. file:///tmp/my.hastings.gov.uk

Dear Information Officer,

Thanks for the information.

My request question 4. asked for a copy of the independent assesment of the viablity report referred to in the officers report for HS/FA/20/00970. This report has not been supplied and is not available online.The assesment supplied is a later report that accepts that no afforable housing can be provided. I require the earlier report that stated that 26 units could be provided. Please provide.

You state that all other information is online. There are no records of emails and correspondence between HBC departments recorded online. I think it unlikely that HBC holds no correspondence/emails as requested by questions 1 to 3 and questions 5 to 7. Please confirm that HBC holds no correspondence / emails as requested by these questions.

Yours sincerely,

Chris Hurrell

Information Officer, Hastings Borough Council

1 Attachment

Thank you for your Freedom of Information request.
 
We aim to respond to requests for information within 20 working days, in
accordance with the requirements of the Freedom of Information Act. 
 
If your request is for personal information (Subject Access request) your
request will be dealt with according to the requirements of the General
Data Protection Regulation (GDPR) and the timescale for response may be
extended to 40 days.
 
You can find out more information about [1]Freedom of Information as well
as all of the services the council provides on [2]our website.
 
Information Officer
Hastings Borough Council
01424 451066
[3]www.hastings.gov.uk
 
 
 
 
 
 
 
 
 

References

Visible links
1. https://www.hastings.gov.uk/my_council/f...
2. https://www.hastings.gov.uk/
3. file:///tmp/www.hastings.gov.uk

Information Officer, Hastings Borough Council

5 Attachments

Dear Mr Hurrell
 
I refer to your email dated 10 January 2023 requesting an Internal Review
following our response to a recent Freedom of Information request ref:
FOIR-469692705. Subject: 777 the Ridge - Application HS/FA/20/00970 and
Appeal.
 
I have been asked, as a senior officer of the council who has not been
involved in your case to look into how we handled your request.
 
Hastings Borough Council received the following request on 3 December 2022
 
The original developer's viability report from December 2020 for
application HS/FA/20/00970 stated that the development of 67 units could
not support any affordable housing or infrastructure contributions under
S106.
 
This was challenged by HBC Housing during consultation who requested that
26 affordable housing units were provided.
 
The Officer report to committee confirmed that the application would have
26 affordable housing units and infrastructure contributions. The report
refers to an independent RICS valuer's assessment report which led to the
developer providing 40% affordable housing (26 units and a financial
contribution).
 
No further information was posted  against the application from  the
developer to explain why the developer now considered affordable housing
and infrastructure contributions to be acceptable in conflict with their
December 2020 viability report.
 
The application was refused by the planning committee. The developer took
the refusal to appeal and won permission for 67 units. The new permission
retained infrastructure contributions but reduced the affordable housing
contribution from 26 units to zero with HBC consent. There is no
information posted against the appeal that explains why HBC changed their
position and now considered that the application could not support any
affordable housing.
 
I request the following under FOI:
 
1. All documents/correspondence between the developer and HBC concerning
the change from zero to 26 affordable  units following the submission of
the Dec 2020 viability report.
 
2. All documents/correspondence between HBC departments  concerning the
change from zero to 26 affordable units following the submission of the
Dec 2020 viability report.
 
3. All documents/correspondence between  HBC and any other bodies
concerning the change from zero to 26 affordable units following the
submission of the Dec 2020 viability report.
 
4. A copy of the independent assessment of the viability report referred
to in the officer's report to committee for HS/FA/20/00970.
 
5. All documents/correspondence between the developer and HBC concerning
the reductions from 26 to zero affordable housing units  following the
refusal of the application.
 
6. All documents/correspondence between HBC departments  concerning the
reduction from 26 to zero affordable housing units following the refusal
of the application.
 
7. All documents/correspondence between HBC  and any other bodies 
concerning the reduction from 26 to zero affordable housing units 
following the refusal of the application.
 
8. Any documents/correspondence submitted to the appeal concerning
affordable housing and infrastructure contributions.
 
9. Copies of all viability reports for the development at 777 the Ridge.
 
Hastings Borough Council responded on the 9 January 2023
 
Most of the information requested can be found on the files which are held
online
[1]https://www.hastings.gov.uk/planning/sea...
 
The attached are the only files that do not appear to be available to view
publicly.
 
Please note that names/addresses/telephone numbers and e mail addresses
have been redacted as these fall under
Section 40 (2) of the Freedom of Information Act: Personal data. This is
an absolute exemption and will not be provided.
 
 
You requested an internal review on the 10 January 2023
 
My request question 4.  asked for a copy of the independent assessment of
the viability report referred to in the officers report for
HS/FA/20/00970. This report has not been supplied and is not available
online. The assessment supplied is a later report that accepts that no
affordable housing can be provided. I require the  earlier report that
stated that 26 units could be provided.  Please provide.
 
You state that all other information is online. There are no records of
emails and correspondence between HBC departments recorded online.  I
think it unlikely that HBC holds no correspondence/emails as requested by
questions 1 to 3 and questions 5 to 7.
 
Please confirm that HBC holds no correspondence / emails as requested by
these questions.
 
Review
 
I have now had the opportunity to review your request and can advise as
follows.
 
Please accept my apologies, the Bruton Knowles assessment and email
correspondence was omitted from the original documents provided.
 
The viability report is now available to view publicly on our website:
[2]https://publicaccess.hastings.gov.uk/onl...
 
Please find attached email correspondence originally requested. 
 
Please note that names/addresses/telephone numbers and e mail addresses
have been redacted as these fall under Section 40 (2) of the Freedom of
Information Act: Personal data. This is an absolute exemption and will not
be provided.
 
 
 
If you remain dissatisfied then you may complain to the Information
Commissioners Office (ICO) who will decide whether the Council has handled
your request correctly.
 
Information Commissioners Office
Wycliffe House
Wilmslow
Cheshire
SK9 5AF
 
Tel: 08456 30 60 60
[3]www.ico.org.uk 
 
Yours sincerely
 
 
Kevin Boorman
Marketing & Major Projects Manager
 
 
 
[4][IMG]
 
 
 

References

Visible links
1. https://www.hastings.gov.uk/planning/sea...
2. https://publicaccess.hastings.gov.uk/onl...
3. http://www.ico.org.uk/
4. file:///tmp/my.hastings.gov.uk

Dear Information Officer,

The response to the review is disappointing and does not address the questions raised. The review has still not provided the documents requested nor given specific exception reasons for why no reports have been provided for each question.

Please respond to each question in turn giving an exception reason if the information is not supplied..

My request question 9 asked for Copies of all viability reports for the development at 777 the Ridge.

Not all developers affordable housing viability reports have been provided. The following viability reports have not been provided:
1.The latest Viability report for application HS/FA/20/970 which reverted to claiming no affordable housing is possible - this is not online
2. The viability report submitted to the planning inspectorate
3. The viability report for application HS/FA/22/00906 - this is not online
4. The viability report for application HS/FA/23/00016 - this is not online
5. The viability report for HS/OA/17/00645 - this is not onlne

Yours sincerely,

Chris Hurrell

Information Officer, Hastings Borough Council

1 Attachment

Thank you for your Freedom of Information request.
 
We aim to respond to requests for information within 20 working days, in
accordance with the requirements of the Freedom of Information Act. 
 
If your request is for personal information (Subject Access request) your
request will be dealt with according to the requirements of the General
Data Protection Regulation (GDPR) and the timescale for response may be
extended to 40 days.
 
You can find out more information about [1]Freedom of Information as well
as all of the services the council provides on [2]our website.
 
Information Officer
Hastings Borough Council
01424 451066
[3]www.hastings.gov.uk
 
 
 
 
 
 
 
 
 

References

Visible links
1. https://www.hastings.gov.uk/my_council/f...
2. https://www.hastings.gov.uk/
3. file:///tmp/www.hastings.gov.uk

Dear Hastings Borough Council,

Additional Documents requested under FOI following review

Following a detailed review of the documents supplied at review I have identified other relevant documents that are referred to in the documents supplied but have not been supplied.

I request the following documents:

1. The email sent on the 14/04/21 @09.19 referred to in the 15/04/21 email sent by Park Lane Group.

2. A copy of Park Lane Group’s additional viability information received on the 26/03/21 referred to in the email of 12/04/21.

3. All Park Lane Group’s responses (in any format) to the Bruton Knowles comments contained within the email of 12/04/21 including park Lane Group’s review of these comments.

4. The Email of 14/04/21 referred to in the 15/04/21 08.19 HBC email

5. The two documents referred to in the 14/04/21 email:
a. A copy of the review of the Cost plan
b. A copy of the cost plan produced by BPC

6. All correspondence with Bruton Knowles and Silver referred to in the HBC email dated 15/04/21 08.09

7. Park Lane Group’s updated viability statement dated 23/03/22 referred to in the statement of common ground and in appendix D of the statement of common ground

8. HBC’s review of the above 23/03/22 viability statement

9. Park Lane Group’s updated viability statement dated 21/04/22 referred to in the statement of common ground and in appendix E of the statement of common ground

10. HBC’s review of the above 21/04/22 viability statement

11. PLG’s viability report from Tom Hegan of Turner Merum

12. The FVA statement dated April 22 referred to in para 1.4 of the Altair viability assessment

Please note that the emails are contained in the file provided at review called “Email FOI469692705 LH Redacted”

Please note that this request is in addition to my request of the 24/02/23.

Yours faithfully,

Chris Hurrell

Information Officer, Hastings Borough Council

1 Attachment

Thank you for your Freedom of Information request.
 
We aim to respond to requests for information within 20 working days, in
accordance with the requirements of the Freedom of Information Act. 
 
If your request is for personal information (Subject Access request) your
request will be dealt with according to the requirements of the General
Data Protection Regulation (GDPR) and the timescale for response may be
extended to 40 days.
 
You can find out more information about [1]Freedom of Information as well
as all of the services the council provides on [2]our website.
 
Information Officer
Hastings Borough Council
01424 451066
[3]www.hastings.gov.uk
 
 
 
 
 
 
 
 
 

References

Visible links
1. https://www.hastings.gov.uk/my_council/f...
2. https://www.hastings.gov.uk/
3. file:///tmp/www.hastings.gov.uk

Dear Hastings Borough Council,

This request is supplementary to my two follow ups to the review dated 24/02/23 and 25/02/23.

I have now had the opportunity to read the documents supplied by the review in further detail. I have now identified references to the following documents which have not been supplied:

1. BPC Cost plan dated 19/04/22
2. Rapleys affordable housing report dated 23/03/22
3. Turner Morum's appraisal
4. Rapleys affordable housing / viability report dated 19/7/17
5. Bruton Knowles Review dated 12/2/18
6. BPC review dated 11/11/20

Please provide copies of these documents.

Yours faithfully,

Chris Hurrell

Information Officer, Hastings Borough Council

1 Attachment

Thank you for your Freedom of Information request.
 
We aim to respond to requests for information within 20 working days, in
accordance with the requirements of the Freedom of Information Act. 
 
If your request is for personal information (Subject Access request) your
request will be dealt with according to the requirements of the General
Data Protection Regulation (GDPR) and the timescale for response may be
extended to 40 days.
 
You can find out more information about [1]Freedom of Information as well
as all of the services the council provides on [2]our website.
 
Information Officer
Hastings Borough Council
01424 451066
[3]www.hastings.gov.uk
 
 
 
 
 
 
 
 
 

References

Visible links
1. https://www.hastings.gov.uk/my_council/f...
2. https://www.hastings.gov.uk/
3. file:///tmp/www.hastings.gov.uk

Information Officer, Hastings Borough Council

Dear Mr Hurrell

I refer to your email dated 24 February 2023, please see below our response to your queries raised:

1.The latest Viability report for application HS/FA/20/970 which reverted to claiming no affordable housing is possible - this is not online

This is now available online – ‘Statement of Common Ground – S106 Covering Letter’ dated 09 05 22 and ‘Statement of Common Ground – Viability Study’ dated 09 05 2022’

2. The viability report submitted to the planning inspectorate

As above

3. The viability report for application HS/FA/22/00906 - this is not online

This has now been made available online.

4. The viability report for application HS/FA/23/00016 - this is not online

This has now been made available online.

5. The viability report for HS/OA/17/00645 - this is not online

This is on line (dated 14.10.2019)

Yours sincerely

Lisa Greathead
Information Officer
Hastings Borough Council
Muriel Matters House
Breeds Place
Hastings
TN34 3UY
01424 451722

show quoted sections

Dear Information Officer,

Thanks for your reply to my request of the 9th March responding to my request of 24/02/2023.

I have found the first 4 reports. Thank you.

The fifth viability report for HS/OA/17/00645 is not online. The document dated 14.10.2019 is a section 106 agreement not the viability report. Please provide the viability report for HS/OA/17/00645

Yours sincerely,

Chris Hurrell

Information Officer, Hastings Borough Council

1 Attachment

Thank you for your Freedom of Information request.
 
We aim to respond to requests for information within 20 working days, in
accordance with the requirements of the Freedom of Information Act. 
 
If your request is for personal information (Subject Access request) your
request will be dealt with according to the requirements of the General
Data Protection Regulation (GDPR) and the timescale for response may be
extended to 40 days.
 
You can find out more information about [1]Freedom of Information as well
as all of the services the council provides on [2]our website.
 
Information Officer
Hastings Borough Council
01424 451066
[3]www.hastings.gov.uk
 
 
 
 
 
 
 
 
 

References

Visible links
1. https://www.hastings.gov.uk/my_council/f...
2. https://www.hastings.gov.uk/
3. file:///tmp/www.hastings.gov.uk

Dear Hastings Borough Council,

I have now had the opportunity to read the Viability report as described in your response of the 09/02/2023:

"1.The latest Viability report for application HS/FA/20/970 which reverted to claiming no affordable housing is possible - this is not online
This is now available online – ‘Statement of Common Ground – S106 Covering Letter’ dated 09 05 22 and ‘Statement of Common Ground – Viability Study’ dated 09 05 2022’"

The information now posted is partial and incomplete. No appendices to the documents have been posted. In order to review viability it is essential that the appendices are in the public domain.

The S106 covering letter is now posted as described. However the covering letter refers to 6 appendices - none of these have been posted or supplied. Please provide these 6 appendices.

The Viability Study dated 09.05.22 has been posted as described. However the report has 7 appendices which have not been posted. Please provide these 7 appemdices.

Yours faithfully,

Chris Hurrell

Information Officer, Hastings Borough Council

1 Attachment

Thank you for your Freedom of Information request.
 
We aim to respond to requests for information within 20 working days, in
accordance with the requirements of the Freedom of Information Act. 
 
If your request is for personal information (Subject Access request) your
request will be dealt with according to the requirements of the General
Data Protection Regulation (GDPR) and the timescale for response may be
extended to 40 days.
 
You can find out more information about [1]Freedom of Information as well
as all of the services the council provides on [2]our website.
 
Information Officer
Hastings Borough Council
01424 451066
[3]www.hastings.gov.uk
 
 
 
 
 
 
 
 
 

References

Visible links
1. https://www.hastings.gov.uk/my_council/f...
2. https://www.hastings.gov.uk/
3. file:///tmp/www.hastings.gov.uk

Information Officer, Hastings Borough Council

Dear Mr Hurrell

I refer to your recent email.

Please accept my apologies, the document dated 14.10.2019 is a section 106 agreement not the viability report as you have indicated.

I have been advised that there would not have been a viability report for HS/OA/17/00645, they were providing affordable homes on that application, and were not claiming the development was unviable in that regard.

The default position of large residential developments is that they provide affordable housing or make a contribution towards providing them, in line with planning policy. They only provide a Viability Report if the applicant wants to make a case that it is not financially viable to make that provision, as was the case for later applications on this site.

Yours sincerely

Lisa Greathead
Information Officer
Hastings Borough Council
Muriel Matters House
Breeds Place
Hastings
TN34 3UY
01424 451722

show quoted sections

Information Officer, Hastings Borough Council

Dear Mr Hurrell

I refer to your email dated 25 February 2023.

I am writing to advise you there will be a slight delay into responding to your request for further information below.

Your request is currently being processed and I aim to respond by next Wednesday 28 March 2023.

Yours sincerely

Lisa Greathead
Information Officer
Hastings Borough Council
Muriel Matters House
Breeds Place
Hastings
TN34 3UY
01424 451722

show quoted sections

Information Officer, Hastings Borough Council

Dear Mr Hurrell

I refer to your email dated 27 February 2023.

I am writing to advise you there will be a slight delay into responding to your request for further information below.

Your request is currently being processed and I aim to respond by next Wednesday 28 March 2023.

Yours sincerely

Lisa Greathead
Information Officer
Hastings Borough Council
Muriel Matters House
Breeds Place
Hastings
TN34 3UY
01424 451722

show quoted sections

Information Officer, Hastings Borough Council

2 Attachments

Dear Mr Hurrell
 
I refer to your recent Freedom of Information request ref: FOIR-496739253.
 
Please find attached our response.
 
Yours sincerely
 
Lisa Greathead
Information Officer
Hastings Borough Council
Muriel Matters House
Breeds Place
Hastings
TN34 3UY
01424 451722
 
[1][IMG]
 
 
 

References

Visible links
1. file:///tmp/my.hastings.gov.uk

Information Officer, Hastings Borough Council

1 Attachment

Dear Mr Hurrell

I refer to your email dated 27 February 2023 requesting further information following our Internal review of Freedom of Information request - Affordable Housing for 777 the Ridge - Application HS/FA/20/00970 and Appeal.

Please see below our response.

1. BPC Cost plan dated 19/04/22

Information not held.

2. Rapleys affordable housing report dated 23/03/22

Information not held.

3. Turner Morum's appraisal

Please see attached titled 777 The Ridge (11) Redacted, we believe this is what is being requested.

4. Rapleys affordable housing / viability report dated 19/7/17

Rapleys Report from 2017 is available to view on our website against an earlier application (HS/OA/17/00645) - https://www.hastings.gov.uk/planning/sea...

5. Bruton Knowles Review dated 12/2/18

We are unsure what you are referring to. The application in question was submitted in 2021 therefore, there is no review from 2018 in relation to this application.

6. BPC review dated 11/11/20

As 5 above

Yours sincerely

Lisa Greathead
Information Officer
Hastings Borough Council
Muriel Matters House
Breeds Place
Hastings
TN34 3UY
01424 451722

show quoted sections

Information Officer, Hastings Borough Council

2 Attachments

Dear Mr Hurrell

I refer to your email dated 25 February 2023 requesting further information following our response to your Internal Review - FOIR-469692705. Subject: 777 the Ridge - Application HS/FA/20/00970 and Appeal
sent on the 27 January 2023.

Due to the size of the documents I am having to split my response into 3 emails.

Please see below and attached the requested information for No's 1 - 2.

1. The email sent on the 14/04/21 @09.19 referred to in the 15/04/21 email sent by Park Lane Group.

Please see attached titled 777 The Ridge (1) redacted.

2. A copy of Park Lane Group’s additional viability information received on the 26/03/21 referred to in the email of 12/04/21.

Please see attached titled 777 The Ridge (2) redacted.

Please note the documents which are referred to in the email dated 26 March 2021 are already available on the Council’s website as they were uploaded as part of public consultation on the application - https://www.hastings.gov.uk/planning/sea...

Please note that names/email addresses and telephone numbers have been redacted as these fall under Section 40(2) of the Freedom of Information Act 'personal data' and will not be provided.

Yours sincerely

Lisa Greathead
Information Officer
Hastings Borough Council
Muriel Matters House
Breeds Place
Hastings
TN34 3UY
01424 451722

show quoted sections

Information Officer, Hastings Borough Council

3 Attachments

Dear Mr Hurrell

Please see below and attached our response to No's 3 - 7.

3. All Park Lane Group’s responses (in any format) to the Bruton Knowles comments contained within the email of 12/04/21 including park Lane Group’s review of these comments.

Please see attached titled 777 The Ridge (3) Redacted.

4. The Email of 14/04/21 referred to in the 15/04/21 08.19 HBC email

Information not held - we are unable to locate an email dated 15/04/21 you refer to.

5. The two documents referred to in the 14/04/21 email:
a. A copy of the review of the Cost plan
b. A copy of the cost plan produced by BPC

a) Hastings Borough Council does hold this information however, we currently do not have consent from the author to disclose. I will advise when/if consent has been obtained.

b) Please see attached titled 777 The Ridge (5b) Redacted - This email correspondence does not include the cost plan as this is not held by Hastings Borough Council. The cost plan was not sent to our planning department by BPC.

6. All correspondence with Bruton Knowles and Silver referred to in the HBC email dated 15/04/21 08.09

Information not held - as above.

7. Park Lane Group’s updated viability statement dated 23/03/22 referred to in the statement of common ground and in appendix D of the statement of common ground

Please see attached titled 777 The Ridge (7) Redacted

Please note that names/email addresses and telephone numbers have been redacted as these fall under Section 40(2) of the Freedom of Information Act 'personal data' and will not be provided.

Yours sincerely

Lisa Greathead
Information Officer
Hastings Borough Council
Muriel Matters House
Breeds Place
Hastings
TN34 3UY
01424 451722

show quoted sections

Information Officer, Hastings Borough Council

3 Attachments

Dear Mr Hurrell

Please see below and attached our response to No's 8 - 12.

8. HBC’s review of the above 23/03/22 viability statement

Please see attached titled 777 The Ridge (8)

9. Park Lane Group’s updated viability statement dated 21/04/22 referred to in the statement of common ground and in appendix E of the statement of common ground

Please see attached titled 777 The Ridge (9) Redacted

10. HBC’s review of the above 21/04/22 viability statement

Please see report attached to No 8

11. PLG’s viability report from Tom Hegan of Turner Morum

Please see attached titled 777 The Ridge (11) Redacted. The Altair Financial Viability Assessment is attached to No's 8 & 10

12. The FVA statement dated April 22 referred to in para 1.4 of the Altair viability assessment

Please see report attached to No 8

Please note that names/email addresses and telephone numbers have been redacted as these fall under Section 40(2) of the Freedom of Information Act 'personal data' and will not be provided.

Yours sincerely

Lisa Greathead
Information Officer
Hastings Borough Council
Muriel Matters House