Dear Bristol City Council,
You have stated that you do not have specific costs for those parts of the A4018 proposals that are not being proceeded with.
Please provide the total cost of putting together the proposals in their entirety and consulting on them, from inception to the present day, or the most recent date for which you have figures.
Where possible please break these figures down so that they provide more detailed information.

Yours faithfully,

Paul Brooks

No Reply @ Bristol, Bristol City Council

Dear paul brooks 
This is a courtesy email to let you know your Public Information
Request has been received on : 22/05/2019. 
Your unique reference number is "CRN00227744 ". Please keep this
number safe, as you may be required to provide it in the future. 
If you need to add further information concerning your case or
require an update about your response date, please email
[email address
Regards,
Customer Relations Team

--------------------------------------------------------------------------

Council services: http://www.bristol.gov.uk/service
Latest council news: http://www.bristol.gov.uk/ournews
Consultations: http://www.bristol.gov.uk/consult

"No Reply @ Bristol" <noreply@bristol.gov.uk>, Bristol City Council

You sent us a Freedom of Information request on 22/05/2019

Your request number is CRN00227744

We’ve looked at your request and you should receive a reply on or before 20/06/2019 This will be 20 working days since your original request.

The request

show quoted sections

Transport Projects, Bristol City Council

Dear Mr Brooks,

 

We are writing in response to the above request submitted under the
Freedom of Information Act on the 21^st May 2019 regarding the A4018
Improvements consultation. In this request, you specified that you were
seeking:

 

“the total cost of putting together the proposals in their entirety and consulting on them, from inception to the present day, or the most recent date for which you have figures. Where possible please break these figures down so that they provide more detailed information.”

 

Please see table below for the figures, accurate for costs invoiced and paid as of 21^st May 2019, and broken down into constituent elements by year. Please note that all costs have been rounded to the nearest £1000:

 

Category 2016/17 2017/18 2018/19 2019/20 Total
BCC Transport Staff Costs   £1,000 £65,000 £22,000 £88,000
Contractor Surveys and Modelling £37,000   £5,000   £42,000
Survey Equipment Contributions         £0
Print, postage, fulfilment of
leaflets     £8,000   £8,000
Internal Engineering Design     £167,000 £32,000 £199,000
Total £37,000 £1,000 £245,000 £54,000 £337,000

 

Kind Regards,

 

 

The Transport Projects Team

Strategic City Transport

Bristol City Council

 

100 Temple Street

BS1 6AG

[1][email address]

 

--------------------------------------------------------------------------

Council services: http://www.bristol.gov.uk/service
Latest council news: http://www.bristol.gov.uk/ournews
Consultations: http://www.bristol.gov.uk/consult

References

Visible links
1. mailto:[email address]