This is an HTML version of an attachment to the Freedom of Information request 'Liverpool's Chinatown: 5 years of disputes, delays [extraneous material removed]'.



Enquiries to:  
Information Team 
Our Ref:  
 
FOI6648710 
 
 
xxxxxxxxxxxxxxxxxxxxxxx@xxxxxxxxxxxxxx.xxx 
 
 
 
Dear Mr Pickford… 
 
Freedom of Information Request 6648710 
Your request was actioned under the Freedom of Information Act 2000 in which you 
requested the following information – 
 
' 1. What is the situation now 2021 with this site and what is the outstanding fees due 
to LCC with all past overdue payments is it over £2.3 million? 
 
2. Why was such a high-profile CEO (Sue Grindrod) sent in to GGSD Ltd, Sue 
Grindrod is a partner of Nick Kavanagh and has working for LCC, the Mayor, and is 
linked to: xxxxx xxxxx xxxxx xxxxx xx who according to records works with the LCC 
and the Mayor? 
 
3. Will the LCC (Liverpool City Council) explain if Nick Kavanagh is a part of this 
company GGSD Ltd or has been a consultant for (Kerry Tomlinson) and or Sue 
Grindrod?  
 
4. Are the LCC going to launch any investigation into GGDS Ltd or ask for advice from 
the SFO? 
 
5. Cllr’s Ann O’Byrne, Steve Munby, Gary Millar, all was involved in setting up this 
horrific Chinatown £240 million project, along with others in 2014/15 will these be 
coming forward to give any information to the SFO? 
 
6. Are the LCC just going to let this site in Chinatown and at the Metalworks in 
Vauxhall rot and could devastate these communities or will it act and call in the SFO or 
do a full investigation? 
 
7. If the LCC fails to answer these serious concerns along with these councilors who 
were involved in Chinatown and one with Coconut Grove, then {Max Caller }needs to 
investigate and see the the full report on these developers and links to several in-
house members of the staff at the LCC, talk to the many witness and outside reporters 
have been intimidated, will the LCC assist {Max Caller} and pass over the paper- work 
on this matter along with Mark Kitts involvement in PHD1 and NPG Ltd? 
 
Response 
 
Liverpool City Council would advise as follows – 
 
1. 
The relevant invoice has been raised and is being progressed through the Council’s 
corporate debt recovery procedure. 
 
2. 
This is a statement, comment and speculation and is therefore not valid under 
Freedom of Information legislation.  
 
Li verpool City Council Information Team 
Cunard Building, Water Street, Liverpool, L3 1AH 
E: xxxxxxxxxxxxxxxxxxx@xxxxxxxxx.xxx.xx 
 
 


3. 
GSOD Ltd is a separate and distinct company in respect of which Liverpool City 
Council has no role, involvement or responsibility. Please refer directly to either the 
company or Companies House.  
 
4. 
This is a statement, comment and speculation and is therefore not valid under 
Freedom of Information legislation. As indicated in responses to previous Freedom of 
Information requests, the City Council will engage and constructively assist the 
investigation of any statutory enforcement agencies.  
 
5. 
This is a statement, comment and speculation and is therefore not valid under 
Freedom of Information legislation. As indicated in responses to previous Freedom of 
Information requests, the City Council will engage and constructively assist the 
investigation of any statutory enforcement agencies.  
 
6. 
This is a statement, comment and speculation and is therefore not valid under 
Freedom of Information legislation. 
 
7. 
This is a statement, comment and speculation and is therefore not valid under 
Freedom of Information legislation. As indicated in responses to previous Freedom of 
Information requests, the City Council will engage and constructively assist the 
investigation of any statutory enforcement agencies.  
  
This concludes our response.  
 
The City Council will consider appeals, referrals or complaints in respect of your Freedom of 
Information Act 2000 and you must submit these in writing to 
xxxxxxxxxxxxxxxxxxx@xxxxxxxxx.xxx.xx within 28 days of receiving your response. The matter 
will be dealt with by an officer who was not previously involved with the response and we 
will look to provide a response within 40 days. 
 
If you remain dissatisfied you may also apply to the Information Commissioner for a 
decision about whether the request for information has been dealt with in accordance with 
the Freedom of Information Act 2000. The Information Commissioner’s website is  
www.ico.gov.uk and the postal address and telephone numbers are:- Information 
Commissioner’s Office, Wycliffe House, Water Lane, Wilmslow, Cheshire SK9 5AF. 
Telephone: 0303-123-113.  Email –xxxx@xxx.xxx.xxx.xx (they advise that their email is not 
secure) 
 
Yours sincerely 
Information Team 
 
Li verpool City Council Information Team 
Cunard Building, Water Street, Liverpool, L3 1AH 
E: xxxxxxxxxxxxxxxxxxx@xxxxxxxxx.xxx.xx