This is an HTML version of an attachment to the Freedom of Information request 'Deed of Variation for PEDL137'.


  
 
 
 
 
Oil and Gas Authority 
21 Bloomsbury Street 
London WC1B 3HF 
 
24 January 2019 
 
 
Dear 

 
PEDL137 Retention Area (“RA”) Work Programme 
 
Due to a significant delay in the grant of necessary regulatory consents for the Horse Hill-1 (“HH-1”) extended 
well  test  (“EWT”),  the  subject  RA’s  timelines  require  minor  amendment.    The  delay  was  beyond  HHDL’s 
immediate control. 
The original RA programme required HHDL to commence the HH-1 EWT by 30 September 2017, subject to 
planning  permission  and  other  regulatory  approvals.  However,  planning  consent  was  not  granted  until  1 
November 2017, with pre-commencement conditions finally waived by SCC in March 2018. The subsequent 
OGA  consent  timeline  was  therefore  also  pushed  back,  with  consent  finally  granted  for  the  HH-1 
recompletion and EWT on 14 June 2018. HHDL commenced the HH-1 EWT as soon as practicable some 10 
days later, on 25 June 2018.  
Consequently, as the EWT is still ongoing, this has also had a knock-on effect to subsequent drilling at Horse 
Hill. The programme’s original HH-2 drilling start date was 30 September 2018, following completion of the 
estimated six month duration EWT.  
Given the above, HHDL hereby requests that OGA amend the RA programme as follows:  
•  Commence the HH-1 EWT by 30 September 2018 
•  Commence drilling of both HH-2 and HH-1z by 30 September 2019 
 
The other timelines within the RA programme would remain unchanged. 
 
 
Yours sincerely, 
 
 
 
 
Stephen Sanderson 
Director 
1 Farnham Rd, Guildford, Surrey GU2 4RG  
T: 
 
   E: xxxx@xxxxxxxxxxxxxxxxxxxxx.xx.xx   W: www.horsehilldevelopments.co.uk