This is an HTML version of an attachment to the Freedom of Information request 'Monitoring of emissions from Javelin Park incinerator'.


 
 
 
Notice of variation and consolidation 
with introductory note 

The Environmental Permitting (England & Wales) Regulations 2016 
 
Urbaser Environmental Limited 
Javelin Park Energy Recovery Facility 
Javelin Park 
Haresfield 
Gloucestershire 
GL2 7NQ 
 
 
Variation application number 
EPR/CP3535CK/V004 
 
Permit number 
EPR/CP3535CK 
 
 
 
Variation and consolidation  
application number  
EPR/CP3535CK/V004  


Javelin Park Energy Recovery Facility 
Permit number EPR/CP3535CK 

Introductory note 
This introductory note does not form a part of the notice 
Under the Environmental Permitting (England & Wales) Regulations 2016 (schedule 5, part 1, paragraph 19) 
a variation may comprise a consolidated permit reflecting the variations and a notice specifying the variations 
included in that consolidated permit. 
Schedule 1 of the notice specifies the conditions that have been varied and schedule 2 comprises a 
consolidated permit which reflects the variations being made. Only the variations specified in schedule 1 are 
subject to a right of appeal.  
The permit has been varied to permit the following operational changes: 
  An additional emission point (W2) for the discharge of uncontaminated surface water from the 
installation and relocation of emission point W1.  
  A change to the design of the main exhaust stack and the flue gas conditions as compared to the 
design detailed in the original application.  
The schedules specify the changes made to the permit. 
The status log of a permit sets out the permitting history, including any changes to the permit reference 
number.  
Status log of the permit 
Description Date 
Comments 
Application 
Duly made 
 
EPR/CP3535CK/A001 
12/04/12 
Additional Information Received 
02/07/12 
RPS AQ Background Reports 
Issue of Notice seeking further 
17/08/12 Schedule 

Notice 
information. 
Additional Information Received 
21/09/12 
Response to Schedule 5 Notice 
Additional Information Received 
08/11/12 
Updated Greenhouse Gas Assessment 
Draft permit EPR/CP3535CK 
20/02/13  
made available for consultation 
Permit EPR/CP3535CK issued 
22/05/13 
Original permit issued to Urbaser Environmental 
Limited 
Application 
Duly made 
Application to vary permit to add waste codes. 
EPR/CP3535CK/V002 
15/08/13 
(variation) 
Variation determined 
29/10/13 
Varied permit issued. 
EPR/CP3535CK  
Notified of change of registered 
19/10/15 
Registered office address changed to First Floor, 
office address 
Westmoreland House, 80-86 Bath Road, 
Cheltenham, Gloucestershire, GL53 7JT 
Variation issued 
01/12/15 
Varied permit issued to Urbaser Environmental 
EPR/CP3535CK/V003 
Limited 
Variation and consolidation  
application number  
EPR/CP3535CK/V004  


Status log of the permit 
Description Date 
Comments 
Variation Application 
Duly made 
Application to add an additional discharge point 
EPR/CP3535CK/V004 
23/03/18 
for uncontaminated surface water and amend the 
stack design and flue gas conditions. 
Variation determined  
30/08/18  
EPR/CP3535CK 
PAS billing Ref: KP3439YD 
End of introductory note 
 
Variation and consolidation  
application number  
EPR/CP3535CK/V004  


Notice of variation and consolidation 
The Environmental Permitting (England and Wales) Regulations 2016 
The Environment Agency in exercise of its powers under regulation 20 of the Environmental Permitting 
(England and Wales) Regulations 2016 varies 
Permit number 
EPR/CP3535CK 
Issued to 
Urbaser Environmental Limited (“the operator”) 
whose registered office is 
First Floor 
Westmoreland House 
80-86 Bath Road 
Cheltenham 
Gloucestershire 
GL53 7JT 

company registration number 07888606 
to operate a regulated facility at 
Javelin Park Energy Recovery Facility 
Javelin Park 
Haresfield 
Gloucestershire 
GL2 7NQ 

to the extent set out in the schedules. 
The notice shall take effect from 30/08/18 
 
Name Date 
Philip Lamb 
30/08/2018 
 
Authorised on behalf of the Environment Agency 
 
 
Variation and consolidation  
application number  
EPR/CP3535CK/V004  


Schedule 1 
The following conditions and tables were varied as a result of the application made by the operator: 
Table S1.2, Table S3.2 and the Site Plan in Schedule 7. 
 
Schedule 2 – consolidated permit 
Consolidated permit issued as a separate document. 
 
Variation and consolidation  
application number  
EPR/CP3535CK/V004  


 
Permit 
The Environmental Permitting (England and Wales) Regulations 2016 
Permit number 
EPR/CP3535CK 
This is the consolidated permit referred to in the variation and consolidation notice for application 
EPR/CP3535CK/V004 authorising, 
Urbaser Environmental Limited (“the operator”), 
whose registered office is 
First Floor 
Westmoreland House 
80-86 Bath Road 
Cheltenham 
Gloucestershire 
GL53 7JT 

company registration number 07888606  
to operate a regulated at 
Javelin Park Energy Recovery Facility 
Javelin Park 
Haresfield 
Gloucestershire 
GL2 7NQ 

to the extent authorised by and subject to the conditions of this permit. 
 
Name Date 
Philip Lamb 
30/08/2018 
 
Authorised on behalf of the Environment Agency 
 
 
 
 
 
 
 
 

 
Conditions 

Management 
1.1 General 
management 
1.1.1 
The operator shall manage and operate the activities: 
(a) 
in accordance with a written management system that identifies and minimises risks of 
pollution, including those arising from operations, maintenance, accidents, incidents, non-
conformances, closure and those drawn to the attention of the operator as a result of 
complaints; and 
(b) 
using sufficient competent persons and resources. 
1.1.2 
Records demonstrating compliance with condition 1.1.1 shall be maintained.  
1.1.3 
Any person having duties that are or may be affected by the matters set out in this permit shall have 
convenient access to a copy of it kept at or near the place where those duties are carried out. 
1.2 Energy 
efficiency 
1.2.1 The 
operator 
shall: 
(a) 
take appropriate measures to ensure that energy is recovered with a high level of energy 
efficiency and energy is used efficiently in the activities; 
(b) 
review and record at least every four years whether there are suitable opportunities to 
improve the energy recovery and efficiency of the activities; and   
(c) 
take any further appropriate measures identified by a review.  
1.2.2 
The operator shall provide and maintain steam and/or hot water pass-outs such that opportunities for 
the further use of waste heat may be capitalised upon should they become practicable. 
1.2.3 
The operator shall review the practicability of Combined Heat and Power (CHP) implementation at 
least every 2 years. The results shall be reported to the Agency within 2 months of each review.  
 
1.3 Efficient 
use 
of raw materials 
1.3.1 The 
operator 
shall: 
(a) 
take appropriate measures to ensure that raw materials and water are used efficiently in the 
activities;  
(b) 
maintain records of raw materials and water used in the activities; 
(c) 
review and record at least every four years whether there are suitable alternative materials 
that could reduce environmental impact or opportunities to improve the efficiency of raw 
material and water use; and 
(d) 
take any further appropriate measures identified by a review. 
Permit Number    
EPR/CP3535CK Page 

Javelin 
Park 
ERF 
 
   
          

 
1.4 Avoidance, 
recovery 
and disposal of wastes produced by the 
activities 
1.4.1 
The operator shall take appropriate measures to ensure that: 
(a) 
the waste hierarchy referred to in Article 4 of the Waste Framework Directive is applied to 
the generation of waste by the activities; and  
(b) 
any waste generated by the activities is treated in accordance with the waste hierarchy 
referred to in Article 4 of the Waste Framework Directive; and 
(c)  
where waste disposal is necessary, this is undertaken in a manner which minimises its 
impact on the environment. 
1.4.2 
The operator shall review and record at least every four years whether changes to those measures 
should be made; and take any further appropriate measures identified by a review. 
2 Operations 
2.1 Permitted 
activities 
2.1.1  The operator is only authorised to carry out the activities specified in schedule 1 table S1.1 (the 
“activities”). 
2.1.2 
Waste authorised by this permit in condition 2.3.3 shall be clearly distinguished from any other waste 
on the site. 
2.2 The 
site 
2.2.1 
The activities shall not extend beyond the site, being the land shown edged in green on the site plan 
at schedule 7 to this permit. 
2.3 Operating 
techniques 
2.3.1 
(a)  
The activities shall, subject to the conditions of this permit, be operated using the techniques 
and in the manner described in the documentation specified in schedule 1, table S1.2, unless 
otherwise agreed in writing by the Environment Agency. 
(b) 
If notified by the Environment Agency that the activities are giving rise to pollution, the operator 
shall submit to the Environment Agency for approval within the period specified, a revision of 
any plan specified in schedule 1, table S1.2 or otherwise required under this permit, which 
identifies and minimises the risks of pollution relevant to that plan, and shall implement the 
approved revised plan in place of the original from the date of approval, unless otherwise 
agreed in writing by the Environment Agency. 
2.3.2 
Any raw materials or fuels listed in schedule 2 table S2.1 shall conform to the specifications set out in 
that table. 
2.3.3 
Waste shall only be accepted if: 
(a) 
it is of a type and quantity listed in schedule 2 table S2.2; and  
(b) 
it conforms to the description in the documentation supplied by the producer or holder; 
(c) 
it having been separately collected for recycling, it is contaminated or otherwise unsuitable 
for recycling.   
Permit Number    
EPR/CP3535CK Page 

Javelin 
Park 
ERF 
 
   
          

 
2.3.4 
The operator shall ensure that where waste produced by the activities is sent to a relevant waste 
operation, that operation is provided with the following information, prior to the receipt of the waste: 
 
(a) 
the nature of the process producing the waste; 
 
(b) 
the composition of the waste; 
 
(c) 
the handling requirements of the waste; 
 
(d) 
the hazardous property associated with the waste, if applicable; and 
 
(e) 
the waste code of the waste. 
2.3.5 
The operator shall ensure that where waste produced by the activities is sent to a landfill site, it meets 
the waste acceptance criteria for that landfill. 
2.3.6 
Waste shall not be charged, or shall cease to be charged, if:  
(a) 
the combustion chamber temperature is below, or falls below, 850oC; or 
(b) 
any continuous emission limit value in schedule 3 table S3.1(a) is exceeded; or 
(c) 
any continuous emission limit value in schedule 3 table S3.1 is exceeded, other than under 
abnormal operating conditions ; or 
(d) 
monitoring results required to demonstrate compliance with any continuous emission limit 
value in schedule 3 table S3.1 are unavailable other than under abnormal operating conditions. 
2.3.7 
The operator shall have at least one auxiliary burner in each line at start up or shut down or whenever 
the operating temperature falls below that specified in condition 2.3.6, as long as incompletely burned 
waste is present in the combustion chamber. Unless the temperature specified in condition 2.3.6 is 
maintained in the combustion chamber, such burner(s) may be fed only with fuels which result in 
emissions no higher than those arising from the use of gas oil, liquefied gas or natural gas. 
2.3.8 
The operator shall record the beginning and end of each period of “abnormal operation”. 
2.3.9 
During a period of “abnormal operation”, the operator shall restore normal operation of the failed 
equipment or replace the failed equipment as rapidly as possible. 
2.3.10  Where, during “abnormal operation”, any of the following situations arise, waste shall cease to be 
charged until normal operation can be restored: 
(a) 
continuous measurement shows that an emission exceeds any emission limit value in 
schedule 3 table S3.1 due to disturbances or failures of the abatement systems, or continuous 
emission monitor(s) are out of service, as the case may be, for a total of 4 hours uninterrupted 
duration;  
(b) 
the cumulative duration of “abnormal operation” periods over 1 calendar year has reached 60 
hours;  
(c) 
continuous measurement shows that an emission exceeds any emission limit value in 
schedule 3 table S3.1 (a) due to disturbances or failures of the abatement systems; 
(d) 
continuous emission monitors or alternative techniques to demonstrate compliance with the 
emission limit value(s) for particulates, TOC and / or CO in schedule 3 table S3.1(a), as 
detailed in the application or as agreed in writing with the Environment Agency, are 
unavailable.  
2.3.11  The operator shall interpret the end of the period of “abnormal operation” as the earliest of the 
following: 
(a) 
when the failed equipment is repaired and brought back into normal operation;  
(b) 
when the operator initiates a shut down of the waste combustion activity, as described in the 
application or as agreed in writing with the Environment Agency;  
(c) 
when a period of four hours has elapsed from the start of the “abnormal operation”;  
Permit Number    
EPR/CP3535CK Page 

Javelin 
Park 
ERF 
 
   
          

 
(d) 
when, in any calendar year, an aggregated period of 60 hours “abnormal operation” has been 
reached.  
2.3.12  Bottom ash and APC residues shall not be mixed. 
2.4 Improvement 
programme 
2.4.1   The operator shall complete the improvements specified in schedule 1 table S1.3 by the date specified 
in that table unless otherwise agreed in writing by the Environment Agency. 
2.4.2 
Except in the case of an improvement which consists only of a submission to the Environment Agency, 
the operator shall notify the Environment Agency within 14 days of completion of each improvement. 
2.5 Pre-operational 
conditions 
2.5.1 
The activities shall not be brought into operation until the measures specified in schedule 1 table S1.4 
have been completed. 

Emissions and monitoring 
3.1 Emissions 
to 
water, air or land 
3.1.1 
There shall be no point source emissions to water, air or land except from the sources and emission 
points listed in schedule 3 tables S3.1 and S3.2 except in “abnormal operation”, when there shall be 
no point source emissions to water, air or land except from the sources and emission points listed in 
schedule 3 tables S3.1 (a) and S3.2. 
3.1.2 
The limits given in schedule 3 shall not be exceeded. 
3.1.3  Wastes produced at the site shall, as a minimum, be sampled and analysed in accordance with 
schedule 3 table S3.4.  Additional samples shall be taken and tested and appropriate action taken, 
whenever: 
(a) 
disposal or recovery routes change; or  
(b) 
it is suspected that the nature or composition of the waste has changed such that the route 
currently selected may no longer be appropriate. 
 
3.2 Emissions 
of substances not controlled by emission limits 
3.2.1 
Emissions of substances not controlled by emission limits (excluding odour) shall not cause pollution. 
The operator shall not be taken to have breached this condition if appropriate measures, including, 
but not limited to, those specified in any approved emissions management plan, have been taken to 
prevent or where that is not practicable, to minimise, those emissions. 
3.2.2 The 
operator 
shall: 
Permit Number    
EPR/CP3535CK Page 

Javelin 
Park 
ERF 
 
   
          

 
(a) 
if notified by the Environment Agency that the activities are giving rise to pollution, submit to 
the Environment Agency for approval within the period specified, an emissions management 
plan which identifies and minimises the risks of pollution from emissions of substances not 
controlled by emission limits; 
(b) 
implement the approved emissions management plan, from the date of approval, unless 
otherwise agreed in writing by the Environment Agency. 
3.2.3 
All liquids in containers, whose emission to water or land could cause pollution, shall be provided with 
secondary containment, unless the operator has used other appropriate measures to prevent or where 
that is not practicable, to minimise, leakage and spillage from the primary container.   
3.2.4     The Operator shall carry out monitoring of groundwater and soil in accordance with the protocol 
approved in writing by the Environment Agency under pre-operational condition PO10 in schedule 1 
table S1.4. 
 
3.3 Monitoring 
3.3.1  The operator shall, unless otherwise agreed in writing by the Environment Agency, undertake the 
monitoring specified in the following tables in schedule 3 to this permit: 
(a) 
point source emissions specified in tables S3.1, S3.1(a) and S3.2;  
 
(b) 
process monitoring specified in table S3.3; 
 
(c) 
residue quality in table S3.4 
3.3.2 
The operator shall maintain records of all monitoring required by this permit including records of the 
taking and analysis of samples, instrument measurements (periodic and continual), calibrations, 
examinations, tests and surveys and any assessment or evaluation made on the basis of such data. 
3.3.3  Monitoring equipment, techniques, personnel and organisations employed for the emissions 
monitoring programme and the environmental or other monitoring specified in condition 3.3.1 shall 
have either MCERTS certification or MCERTS accreditation (as appropriate) unless otherwise agreed 
in writing by the Environment Agency.  Newly installed CEMs, or CEMs replacing existing CEMs, shall 
have MCERTS certification and have an MCERTS certified range which is not greater than 1.5 times 
the daily emission limit value (ELV) specified in schedule 3 table S3.1. The CEM shall also be able to 
measure instantaneous values over the ranges which are to be expected during all operating 
conditions. If it is necessary to use more than one range setting of the CEM to achieve this requirement, 
the CEM shall be verified for monitoring supplementary, higher ranges. 
3.3.4  Permanent means of access shall be provided to enable sampling/monitoring to be carried out in 
relation to the emission points specified in schedule 3 tables S3.1 and S3.1(a)  unless otherwise 
agreed in writing by the Environment Agency.  
3.3.5   Where Continuous Emission Monitors are installed to comply with the monitoring requirements in 
schedule 3 table S3.1; the Continuous Emission Monitors shall be used such that;  
(a) 
 the values of the 95% confidence intervals of a single measured result at the daily emission 
limit value shall not exceed the following percentages:  
  Carbon monoxide    
 
 
 
10% 
 
Sulphur 
dioxide 
    20% 
 
  Oxides of nitrogen (NO & NO2 expressed as NO2) 20% 
 
Particulate 
matter 
    30% 
  Total organic carbon (TOC)  
 
 
30% 
Permit Number    
EPR/CP3535CK Page 

Javelin 
Park 
ERF 
 
   
          

 
  Hydrogen chloride  
 
 
 
40% 
(b) 
valid half-hourly average values shall be determined within the effective operating time 
(excluding the start-up and shut-down periods) from the measured values after having 
subtracted the value of the confidence intervals in condition 3.3.5 (a);  
(c) 
where it is necessary to calibrate or maintain the monitor and this means that data are not 
available for a complete half-hour period, the half-hourly average shall in any case be 
considered valid if measurements are available for a minimum of 20 minutes during the half-
hour period. The number of half-hourly averages so validated shall not exceed 5 per day;  
(d) 
daily average values shall be determined as the average of all the valid half-hourly average 
values within a calendar day. The daily average value shall be considered valid if no more 
than five half-hourly average values in any day have been determined not to be valid;  
(e) 
no more than ten daily average values per year shall be determined not to be valid. 
3.4 Odour 
3.4.1 
Emissions from the activities shall be free from odour at levels likely to cause pollution outside the site, 
as perceived by an authorised officer of the Environment Agency, unless the operator has used 
appropriate measures, including, but not limited to, those specified in any approved odour 
management plan, to prevent or where that is not practicable to minimise the odour.  
3.4.2 The 
operator 
shall: 
(a) 
if notified by the Environment Agency that the activities are giving rise to pollution outside 
the site due to odour, submit to the Environment Agency for approval within the period 
specified, an odour management plan which identifies and minimises the  risks of pollution 
from odour;  
(b) 
implement the approved odour management plan, from the date of approval, unless 
otherwise agreed in writing by the Environment Agency. 
3.5  Noise and vibration 
3.5.1 
Emissions from the activities shall be free from noise and vibration at levels likely to cause pollution 
outside the site, as perceived by an authorised officer of the Environment Agency, unless the operator 
has used appropriate measures, including, but not limited to, those specified in any approved noise 
and vibration management plan to prevent or where that is not practicable to minimise the noise and 
vibration. 
3.5.2 The 
operator 
shall: 
(a) 
if notified by the Environment Agency that the activities are giving rise to pollution outside the 
site due to noise and vibration, submit to the Environment Agency for approval within the 
period specified, a noise and vibration management plan which identifies and minimises the 
risks of pollution from noise and vibration; 
(b) 
implement the approved noise and vibration management plan, from the date of approval, 
unless otherwise agreed in writing by the Environment Agency. 
3.6 Pests 
3.6.1   The activities shall not give rise to the presence of pests which are likely to cause pollution, hazard or 
annoyance outside the boundary of the site. The operator shall not be taken to have breached this 
condition if appropriate measures, including, but not limited to, those specified in any approved pests 
management plan, have been taken to prevent or where that is not practicable, to minimise the 
presence of pests on the site.   
Permit Number    
EPR/CP3535CK Page 

Javelin 
Park 
ERF 
 
   
          

 
 
3.6.2   The operator shall: 
 
(a)         if notified by the Environment Agency, submit to the Environment Agency for approval within 
the period specified, a pests management plan which identifies and minimises risks of 
pollution from pests; 
(b)         implement the pests management plan, from the date of approval, unless otherwise agreed 
in writing by the Environment Agency. 
4 Information 
4.1 Records 
4.1.1 
All records required to be made by this permit shall: 
(a) 
be legible; 
(b) 
be made as soon as reasonably practicable; 
(c) 
if amended, be amended in such a way that the original and any subsequent amendments 
remain legible, or are capable of retrieval; and 
(d) 
be retained, unless otherwise agreed in writing by the Environment Agency, for at least 6 years 
from the date when the records were made, or in the case of the following records until permit 
surrender: 
(i) 
off-site environmental effects; and 
(ii) 
matters which affect the condition of the land and groundwater. 
4.1.2  The operator shall keep on site all records, plans and the management system required to be 
maintained by this permit, unless otherwise agreed in writing by the Environment Agency.  
4.2 Reporting 
4.2.1 
The operator shall send all reports and notifications required by the permit to the Environment Agency 
using the contact details supplied in writing by the Environment Agency. 
Permit Number    
EPR/CP3535CK Page 

Javelin 
Park 
ERF 
 
   
          

 
4.2.2 
A report or reports on the performance of the activities over the previous year shall be submitted to 
the Environment Agency by 31 January (or other date agreed in writing by the Environment Agency) 
each year.  The report(s) shall include as a minimum: 
(a)  a review of the results of the monitoring and assessment carried out in accordance with the permit 
including an interpretive review of that data;  
(b)  the annual production /treatment data set out in schedule 4 table S4.2; and 
(c)  the performance parameters set out in schedule 4 table S4.3 using the forms specified in table 
S4.4 of that schedule. 
(d)  the functioning and monitoring of the incineration plant in a format agreed with the Environment 
Agency. The report shall, as a minimum requirement (as required by Chapter IV of the Industrial 
Emissions Directive) give an account of the running of the process and the emissions into air and 
water compared with the emission standards in the IED.  
4.2.3 
Within 28 days of the end of the reporting period the operator shall, unless otherwise agreed in writing 
by the Environment Agency, submit reports of the monitoring and assessment carried out in 
accordance with the conditions of this permit, as follows: 
(a)     in respect of the parameters and emission points specified in schedule 4 table S4.1; 
(b)  for the reporting periods specified in schedule 4 table S4.4 and using the forms specified in 
schedule 4 table S4.4 ; and 
(c)  giving the information from such results and assessments as may be required by the forms 
specified in those tables. 
4.2.4 
The operator shall, unless notice under this condition has been served within the preceding four years, 
submit to the Environment Agency, within six months of receipt of a written notice, a report assessing 
whether there are other appropriate measures that could be taken to prevent, or where that is not 
practicable, to minimise pollution. 
4.2.5 
Within 1 month of the end of each quarter, the operator shall submit to the Environment Agency using 
the form made available for the purpose, the information specified on the form relating to the site and 
the waste accepted and removed from it during the previous quarter.       
4.3 Notifications 
4.3.1 
The Operator shall: 
(a)  
in the event that the operation of the activities gives rise to an incident or accident which 
significantly affects or may significantly affect the environment, the operator must immediately: 
(i)   inform the Environment Agency,  
(ii)  take the measures necessary to limit the environmental consequences of such an 
incident or accident, and 
(iii) take the measures necessary to prevent further possible incidents or accidents; 
(b)  
  in the event of a breach of any permit condition, the operator must immediately:   
(i)   inform the Environment Agency, and 
(ii) 
take the measures necessary to ensure that compliance is restored within the shortest 
possible time; 
(c)  
in the event of a breach of permit condition which poses an immediate danger to human health 
or threatens to cause an immediate significant adverse effect on the environment, the operator 
must immediately suspend the operation of the activities or the relevant part of it until 
compliance with the permit conditions has been restored. 
Permit Number    
EPR/CP3535CK Page 

Javelin 
Park 
ERF 
 
   
          

 
4.3.2 
Any information provided under condition 4.3.1 (a)(i), or 4.3.1 (b)(i) where the information relates to 
the breach of a limit specified in the permit, shall be confirmed by sending the information listed in 
schedule 5 to this permit within the time period specified in that schedule. 
4.3.3 
Where the Environment Agency has requested in writing that it shall be notified when the operator is 
to undertake monitoring and/or spot sampling, the operator shall inform the Environment Agency when 
the relevant monitoring and/or spot sampling is to take place. The operator shall provide this 
information to the Environment Agency at least 14 days before the date the monitoring is to be 
undertaken. 
4.3.4 
The Environment Agency shall be notified within 14 days of the occurrence of the following matters, 
except where such disclosure is prohibited by Stock Exchange rules:  
Where the operator is a registered company: 
(a) 
any change in the operator’s trading name, registered name or registered office address; and 
(b) 
any steps taken with a view to the operator going into administration, entering into a company 
voluntary arrangement or being wound up. 
Where the operator is a corporate body other than a registered company: 
(a) 
any change in the operator’s name or address; and 
(b) 
any steps taken with a view to the dissolution of the operator. 
4.3.5 
Where the operator proposes to make a change in the nature or functioning, or an extension of the 
activities, which may have consequences for the environment and the change is not otherwise the 
subject of an application for approval under the Regulations or this permit: 
(a) 
the Environment Agency shall be notified at least 14 days before making the change; and 
(b) 
the notification shall contain a description of the proposed change in operation. 
4.3.6 
The Environment Agency shall be given at least 14 days notice before implementation of any part of 
the site closure plan. 
4.4 Interpretation 
4.4.1 
In this permit the expressions listed in schedule 6 shall have the meaning given in that schedule. 
4.4.2 
In this permit references to reports and notifications mean written reports and notifications, except 
where reference is made to notification being made “without delay”, in which case it may be provided 
by telephone.  
Permit Number    
EPR/CP3535CK Page 
10 
Javelin 
Park 
ERF 
 
   
          

 
Schedule 1 - Operations 
Table S1.1 activities 
Activity listed in 
Description of 
Limits of specified activity  
Schedule 1 of the EP 
specified activity  
Regulations  
S5.1 A1 (b) 
The incineration of non-
From receipt of waste to 
hazardous waste in a 
emission of exhaust gas, 
waste incineration plant 
treatment and storage of 
with a capacity 
Incinerator Bottom Ash and 
exceeding 3 tonnes per 
disposal of Air Pollution 
hour.  
Control Residues waste 
arising.  
 
Waste types and quantities as 
specified in Table S2.2 of this 
permit. 
Directly Associated Activities 
Electricity Generation 
Generation of electrical 
 
 
power using a steam 
turbine from energy 
recovered from the flue 
gases. 
 
Back up diesel generator 
For providing 
 
emergency electrical 
power to the plant in the 
event of supply 
interruption. 
 
 
Table S1.2 Operating techniques 
Description Parts 
Date 
Received 

Application 
Parts B2 and B3 of the Application Form. 
Duly Made 
EPR/CP3535CK/A
The Supporting Information Document including 
12/04/12 
001 
associated Annex sections. 
Responses to questions 1, 4 and 5 of the Not Duly 
Made letter. 
Response to 
Responses to questions 4, 5, 6, 7, 8, 9, 12, 14 and 
21/09/12 
Information 
15.   
Request Notice 
issued 17/08/12 
Variation 
Response to questions in Part C2 & C3 of the 
23/03/18 
Application 
application form; and supporting document titled 
EPR/CP3535CK/V
‘EP Variation’. 
004 
 
 
Permit Number    
EPR/CP3535CK 
Page 11 
Javelin Park ERF 
 
   
          

 
 
 
 
 
 
Table S1.3 Improvement programme requirements 
Reference Requirement 
Date 
IC1 
The Operator shall submit a written report to the 
Within 15 
Environment Agency on the implementation of its 
months of the 
Environmental Management System and the progress made 
completion of 
in the certification of the system by an external body or if 
commissioning
appropriate submit a schedule by which the EMS will be 

certified. 
 
IC2 
The  Operator shall submit a written proposal to the 
Within 6 
Environment Agency to carry out tests to determine the size 
months of the 
distribution of the particulate matter in the exhaust gas 
completion of 
emissions to air from emission point A1, identifying the 
commissioning
fractions within the PM10 and PM2.5 ranges. The proposal 

shall include a timetable for approval by the Environment 
Agency to carry out such tests and produce a report on the 
results.  
On receipt of written agreement by the Environment Agency 
to the proposal and the timetable, the Operator shall carry 
out the tests and submit to the Environment Agency a report 
on the results. 
 
IC3 
The Operator shall submit a written report to the 
Within 4 
Environment Agency on the commissioning of the 
months of the 
installation.  The report shall summarise the environmental 
completion of 
performance of the plant as installed against the design 
commissioning
parameters set out in the Application.  The report shall also 

include a review of the performance of the facility against 
the conditions of this permit and details of procedures 
developed during commissioning for achieving and 
demonstrating compliance with permit conditions.   
 
IC4 
The Operator shall carry out checks to verify the residence 
Within 4 
time, minimum temperature and oxygen content of the 
months of the 
exhaust gases in the furnace whilst operating under the 
completion of 
anticipated most unfavourable operating conditions. The 
commissioning
results shall be submitted in writing to the Environment 

Agency. 
 
Permit Number    
EPR/CP3535CK 
Page 12 
Javelin Park ERF 
 
   
          

 
Table S1.3 Improvement programme requirements 
Reference Requirement 
Date 
IC5 
The Operator shall submit a written report to the 
Within 4 
Environment Agency describing the performance and 
months of the 
optimisation of the Selective Non Catalytic Reduction 
completion of 
(SNCR) system and combustion settings to minimise oxides 
commissioning
of nitrogen (NOx) emissions within the emission limit values 

described in this permit with the minimisation of nitrous 
oxide emissions.  The report shall include an assessment of 
the level of NOx and N2O emissions that can be achieved 
under optimum operating conditions. 
 
The report shall also provide details of the optimisation 
(including dosing rates) for the control of acid gases, metals 
and dioxins. 
 
IC6 
The Operator shall submit a written summary report to the 
Initial 
Environment Agency to confirm by the results of calibration 
calibration 
and verification testing that the performance of Continuous 
report to be 
Emission Monitors for parameters as specified in Table S3.1 
submitted to 
and Table S3.1(a) complies with the requirements of BS EN 
the Agency 
14181, specifically the requirements of QAL1, QAL2 and 
within 3 
QAL3. 
months of 
completion of 
commissioning

 
Full summary 
evidence 
compliance 
report to be 
submitted 
within 18 
months of 
completion of 
commissioning

IC7 
The Operator shall carry out an assessment of the impact of 
15 months 
emissions to air of the following component metals subject 
from 
to emission limit values,  Cd, As and Ni.   A report on the 
commenceme
assessment shall be made to the Environment Agency. 
nt of 
 
operations 
Emissions monitoring data obtained during the first year of 
operation shall be used to compare the actual emissions 
with those assumed in the impact assessment submitted 
with the Application. An assessment shall be made of the 
impact of each metal against the relevant EQS/EAL.  In the 
event that the assessment shows that an EQS/EAL can be 
exceeded, the report shall include proposals for further 
investigative work.   
 
Permit Number    
EPR/CP3535CK 
Page 13 
Javelin Park ERF 
 
   
          

 
Table S1.3 Improvement programme requirements 
Reference Requirement 
Date 
IC8 
The Operator shall carry out the monitoring approved under 
6 months from 
pre-operational condition PO8 and provide the Environment 
commenceme
Agency with a written report of the impact of noise from the 
nt of 
installation.   
operations 
 
In the event that the report shows that noise could have a 
significant impact, the report shall include proposals for the 
further attenuation and/or management of noise. 
 
 
Table S1.4   Pre-operational measures 
Reference Pre-operational 
measures 
PO1 
Prior to the commencement of commissioning, the Operator shall send a 
summary of the site Environment Management System (EMS) to the 
Environment Agency and make available for inspection all documents and 
procedures which form part of the EMS.  The EMS shall be developed in line 
with the requirements set out in Section 1 of ‘How to comply with your 
environmental permit’.  The documents and procedures set out in the EMS 
shall form the written management system referenced in condition 1.1.1 (a) of 
the permit. 
 
PO2 
Prior to the commencement of commissioning, the Operator shall send a 
report to the Environment Agency which will contain a comprehensive review 
of the options available for utilising the heat generated by the waste 
incineration process in order to ensure that it is recovered as far as 
practicable. The review shall detail any identified proposals for improving the 
recovery and utilisation of waste heat and shall provide a timetable for their 
implementation. 
 
PO3 
Prior to the commencement of commissioning, the Operator shall submit to the 
Environment Agency for approval a protocol for the sampling and testing of 
incinerator bottom ash for the purposes of assessing its hazard status.  
Sampling and testing shall be carried out in accordance with the protocol as 
approved. 
 
PO4 
Prior to the commencement of commissioning, the Operator shall provide a 
written commissioning plan, including timelines for completion, for approval by 
the Environment Agency.  The commissioning plan shall include the expected 
emissions to the environment during the different stages of commissioning, the 
expected durations of commissioning activities and the actions to be taken to 
protect the environment and report to the Environment Agency in the event 
that actual emissions exceed expected emissions.  Commissioning shall be 
carried out in accordance with the commissioning plan as approved. 
 
Permit Number    
EPR/CP3535CK 
Page 14 
Javelin Park ERF 
 
   
          

 
Table S1.4   Pre-operational measures 
Reference Pre-operational 
measures 
PO5 
Prior to the commencement of commissioning, the Operator shall submit a 
written report to the Agency detailing the waste acceptance procedure to be 
used at the site.  The waste acceptance procedure shall include the process 
and systems by which wastes unsuitable for incineration at the site will be 
controlled.   
The procedure shall be implemented in accordance with the written approval 
from the Agency.   
 
PO6 
After completion of furnace design and at least three calendar months before 
any furnace operation; the operator shall submit a written report to the Agency 
of the details of the computational fluid dynamic (CFD) modelling. The report 
shall demonstrate whether the design combustion conditions comply with the 
residence time and temperature requirements as defined by the Industrial 
Emissions Directive. 
PO7 
Prior to the commencement of commissioning, the operator shall submit a 
written report to the Agency for approval that includes ‘as built’ detailed site 
drainage plans (internal process water) and the specific design detail of the 
external surface water drainage systems and containment infrastructure at the 
site, including all sub-surface structures and equipment.  The report shall also 
include an inspection and maintenance programmes for the containment 
infrastructure and equipment at the site.   
 
PO8 
Prior to the commencement of commissioning, the operator shall provide the 
Environment Agency with a written report for approval describing a detailed 
programme of noise and vibration monitoring that will be carried out at the site 
both during the commissioning stage and also when the plant is fully 
operational. The report shall include confirmation of locations, time, frequency 
and methods of monitoring.  
 
PO9 
Prior to the commencement of commissioning, the Operator shall submit a 
report on the baseline conditions of soil and groundwater at the installation.  
The report shall contain the information necessary to determine the state of 
soil and groundwater contamination so as to make a quantified comparison 
with the state upon definitive cessation of activities provided for in Article 22(3) 
of the IED.  The report shall contain information, supplementary to that already 
provided in application Site Condition Report, needed to meet the information 
requirements of Article 22(2) of the IED.   
PO10 
Prior to the commencement of commissioning the Operator shall submit the 
written protocol referenced in condition 3.2.4 for the monitoring of soil and 
groundwater for approval by the Environment Agency.  The protocol shall 
demonstrate how the Operator will meet the requirements of Articles 14(1)(b), 
14(1)(e) and 16(2) of the IED. 
Permit Number    
EPR/CP3535CK 
Page 15 
Javelin Park ERF 
 
   
          

 
Schedule 2 - Waste types, raw materials and 
fuels 

Table S2.1 Raw materials and fuels 
 
Raw materials and fuel description  
Specification 
Gas Oil 
< 0.1% sulphur content 
 
Table S2.2 Permitted waste types and quantities for incineration. 
Maximum 
190,000 tonnes per annum in total 
quantity 
Waste code 
Description 
02 
Wastes from Agriculture, Horticulture, Aquaculture, Forestry, Hunting 
and Fishing, Food Preparation and Processing 

02 01 
wastes from agriculture, horticulture, aquaculture, forestry, hunting and 
fishing. 

02 01 03 
Plant tissue waste 
02 01 04 
Waste plastic (except packaging) 
02 01 07 
Wastes from forestry 
02 01 09 
Agrochemical waste other than those mentioned in 02 01 08* 
02 03 
wastes from fruit, vegetable, cereal or other vegetable origin material 
preparation and processing 

02 03 04 
Materials unsuitable for consumption or processing 
02 05 
wastes from the dairy products industry 
02 05 01 
Materials unsuitable for consumption or processing 
02 06 
wastes from the baking and confectionery industry 
02 06 01 
Materials unsuitable for consumption or processing 
02 06 02 
Wastes from preserving agents 
03 
Wastes from Wood Processing and the Production of Panels and 
Furniture, Pulp, paper and Cardboard. 

03 01 
wastes from wood processing and the production of panels and 
furniture. 

03 01 01 
Waste bark and cork 
03 01 05 
Sawdust, shavings, cuttings, wood, particle board and veneer other than those 
mentioned in 03 01 04*. 
03 03 
wastes from pulp, paper and cardboard production and processing 
03 03 01 
Waste bark wood 
03 03 07 
Mechanically separated rejects from pulping of waste paper and cardboard 
03 03 08 
Wastes from sorting of paper and cardboard destined for recycling 
04   
Wastes from the Leather, Fur and Textile Industries 
04 02 
wastes from the textile industry 
04 02 09 
Wastes from composite materials (impregnated textile, elastomer, plastomer) 
Permit Number    
EPR/CP3535CK 
Page 16 
Javelin Park ERF 
 
   
          

 
Table S2.2 Permitted waste types and quantities for incineration. 
Maximum 
190,000 tonnes per annum in total 
quantity 
Waste code 
Description 
04 02 10 
Organic matter from natural products (eg. grease, wax) 
04 02 21 
Wastes from unprocessed textile fibres 
04 02 22 
Wastes from processed textile fibres 
07   
Wastes from Organic Chemical Processes 
07 02 
wastes from the MFSU of plastics, synthetic rubber and man-made fibres 
07 02 13 
waste plastic 
15   
Waste Packaging, Absorbants, Wiping Cloths, Filter Materials and 
Protective Clothing not otherwise specified 

15 01 
packaging (including separately collected municipal packaging waste) 
15 01 01 
Paper and cardboard packaging 
15 01 02 
Plastic packaging 
15 01 03 
Wooden packaging 
15 01 05 
Composite packaging 
15 01 06 
Mixed packaging 
15 01 09 
Textile packaging 
15 02 
absorbants, filter materials, wiping cloths and protective clothing 
15 02 03 
Absorbents, filter materials, wiping cloths and protective clothing other than 
those mentioned in 15 02 02* 
17   
Construction and Demolition Wastes (including excavated soil from 
contaminated sites) 

17 01 
wood, glass and plastic 
17 02 01 
Wood 
17 02 03 
Plastic 
17 09 
other construction and demolishion wastes 
17 09 04 
Mixed construction and demolition wastes other than those mentioned in 17 
09 01*, 17 09 02* and 17 09 03* 
19   
Wastes from Waste Management Facilities, Off-Site Waste Water 
Treatment Plants and the Preparation of Water for Human Consumption 
and Water for Industrial Use 

19 02 
wastes from the physiochemical treatments of waste (including 
dechromatation, decyanidation, neutralization) 

19 02 03 
premixed wastes composed only of non-hazardous wastes 
19 02 10 
combustible wastes other than those mentioned in 19 02 08* and 19 02 09* 
19 05 
wastes from aerobic treatment of solid wastes 
19 05 01 
Non-composted fraction of municipal and similar wastes 
19 05 02 
Non-composted fraction of animal and vegetable waste 
19 05 03 
Off-specification compost 
Permit Number    
EPR/CP3535CK 
Page 17 
Javelin Park ERF 
 
   
          

 
Table S2.2 Permitted waste types and quantities for incineration. 
Maximum 
190,000 tonnes per annum in total 
quantity 
Waste code 
Description 
19 05 99 
Wastes not otherwise specified – reject waste from composting – no liquor 
19 06 
wastes from anaerobic treatment of waste 
 19 06 04 
  digestate from anaerobic treatment of municipal waste – no liquor 
 19 06 99 
wastes not otherwise specified – reject waste from anaerobic digestion – no  
liquor 
19 08 
wastes from waste water treatment plants not otherwise specified 
19 08 14 
sludges from other treatment of industrial waste water other than those 
mentioned in 19 08 13* 
19 12 
wastes from the mechanical treatment of waste (eg. sorting, crushing, 
compacting, pelletising) not otherwise specified 

19 12 01 
Paper and cardboard 
19 12 04 
Plastic and rubber 
19 12 07 
Wood other than that mentioned in 19 12 06*  
19 12 08 
Textiles 
19 12 10 
Combustible waste (refuse derived fuel) 
19 12 12 
Other wastes (including mixtures of materials) from mechanical treatment of 
wastes other than those mentioned in 19 12 11* 
20   
Municipal Wastes (Household Waste and Similar Commercial, Industrial 
and Institutional Wastes) 

20 01 
separately collected fractions (except 15 01) 
20 01 01 
Paper and cardboard 
20 01 08 
Bio-degradable kitchen and canteen waste 
20 01 10 
Clothes 
20 01 11 
Textiles 
20 01 25 
edible oil and fat 
20 01 28 
paint, inks, adhesives and resins other than those mentioned in 20 01 27* 
20 01 30 
detergents other than those mentioned in 20 01 29* 
20 01 32 
medicines other than those mentioned in 20 01 31* 
20 01 36 
discarded electrical and electronic equipment other than those mentioned in 
20 01 21*, 20 01 23* and 20 01 35* 
20 01 38 
Wood other than that mentioned in 20 01 37* (i.e. other than that containing 
dangerous substances) 
20 01 39 
Plastics 
20 02 
garden and park wastes (including cemetery waste) 
20 02 01 
Bio-degradable wastes 
20 03 
other municipal wastes 
20 03 01 
Mixed municipal wastes 
20 03 02 
Wastes from markets 
Permit Number    
EPR/CP3535CK 
Page 18 
Javelin Park ERF 
 
   
          

 
Table S2.2 Permitted waste types and quantities for incineration. 
Maximum 
190,000 tonnes per annum in total 
quantity 
Waste code 
Description 
20 03 03 
Street cleaning residues 
20 03 07 
Bulky waste 
20 03 99 
Municipal wastes not otherwise specified 
Permit Number    
EPR/CP3535CK 
Page 19 
Javelin Park ERF 
 
   
          

 
Schedule 3 – Emissions and monitoring 
Table S3.1  Point source emissions to air – emission limits and monitoring requirements 
Emission 
Parameter   
Source 
Limit 
Reference period 
Monitoring frequency 
Monitoring 
point ref. 
(including 
standard(s) or 
& location 
unit)  
method(s) 
A1 - as 
Particulate matter 
Incineration 
30 mg/m3 
½-hr average 
Continuous measurement 
 
shown on 
exhaust gases 
 
BS EN 14181 
the Site 
via heat 
Plan in 
recovery boiler 
Schedule 
and APC plant 

A1 - as 
Particulate matter 
Incineration 
10 mg/m3 
daily average 
Continuous measurement 
BS EN 14181 
shown on 
exhaust gases 
 
the Site 
via heat 
Plan in 
recovery boiler 
Schedule 
and APC plant 

A1 - as 
Total Organic 
Incineration 
20 mg/m3 
½-hr average 
Continuous measurement 
BS EN 14181 
shown on 
Carbon 
exhaust gases 
the Site 
(TOC) 
via heat 
Plan in 
recovery boiler 
Schedule 
and APC plant 

A1 - as 
Total Organic 
Incineration 
10 mg/m3 
daily average 
Continuous measurement 
BS EN 14181 
shown on 
Carbon 
exhaust gases 
the Site 
(TOC) 
via heat 
Plan in 
recovery boiler 
Schedule 
and APC plant 

Permit Number    
EPR/CP3535CK Page 
20 
Javelin 
Park 
ERF 
 
   
          

 
Table S3.1  Point source emissions to air – emission limits and monitoring requirements 
Emission 
Parameter   
Source 
Limit 
Reference period 
Monitoring frequency 
Monitoring 
point ref. 
(including 
standard(s) or 
& location 
unit)  
method(s) 
A1 - as 
Hydrogen 
Incineration 
60 mg/m3   
½-hr average 
Continuous measurement  
BS EN 14181 
shown on 
chloride 
exhaust gases 
the Site 
 
via heat 
Plan in 
recovery boiler 
Schedule 
and APC plant 

A1 - as 
Hydrogen 
Incineration 
10 mg/m3 
daily average 
Continuous measurement 
BS EN 14181 
shown on 
chloride 
exhaust gases 
 
the Site 
via heat 
Plan in 
recovery boiler 
Schedule 
and APC plant 

A1 - as 
Hydrogen fluoride 
Incineration 
2 mg/m3  
periodic over 
Quarterly in first year. Then 
BS ISO 15713 
shown on 
exhaust gases 
 
minimum 1-hour 
Bi-annual 
the Site 
via heat 
period 
Plan in 
recovery boiler 
Schedule 
and APC plant 

A1 - as 
Carbon  
Incineration 
100  mg/m3 
½-hr average 
Continuous measurement 
BS EN 14181 
shown on 
monoxide 
exhaust gases 
 
 
the Site 
via heat 
Plan in 
recovery boiler 
Schedule 
and APC plant 

Permit Number    
EPR/CP3535CK Page 
21 
Javelin 
Park 
ERF 
 
   
          

 
Table S3.1  Point source emissions to air – emission limits and monitoring requirements 
Emission 
Parameter   
Source 
Limit 
Reference period 
Monitoring frequency 
Monitoring 
point ref. 
(including 
standard(s) or 
& location 
unit)  
method(s) 
A1 - as 
Carbon  
Incineration 
50  mg/m3  
daily average 
Continuous measurement 
BS EN 14181 
shown on 
monoxide 
exhaust gases 
 
the Site 
via heat 
Plan in 
recovery boiler 
Schedule 
and APC plant 

A1 - as 
Sulphur dioxide 
Incineration 
200  mg/m3   
½-hr average 
Continuous measurement  
BS EN 14181 
shown on 
exhaust gases 
 
the Site 
via heat 
Plan in 
recovery boiler 
Schedule 
and APC plant 

A1 - as 
Sulphur dioxide 
Incineration 
50 mg/m3  
daily average 
Continuous measurement  
BS EN 14181 
shown on 
exhaust gases 
 
the Site 
via heat 
Plan in 
recovery boiler 
Schedule 
and APC plant 

A1 - as 
Oxides of 
Incineration 
400  mg/m3   
½-hr  average 
Continuous measurement 
BS EN 14181 
shown on 
nitrogen (NO and 
exhaust gases 
the Site 
NO2 expressed 
via heat 
Plan in 
as NO2)  
recovery boiler 
Schedule 
and APC plant 

Permit Number    
EPR/CP3535CK Page 
22 
Javelin 
Park 
ERF 
 
   
          

 
Table S3.1  Point source emissions to air – emission limits and monitoring requirements 
Emission 
Parameter   
Source 
Limit 
Reference period 
Monitoring frequency 
Monitoring 
point ref. 
(including 
standard(s) or 
& location 
unit)  
method(s) 
A1 - as 
Oxides of 
Incineration 
200 mg/m3  
daily average 
Continuous measurement 
BS EN 14181 
shown on 
nitrogen (NO and 
exhaust gases 
the Site 
NO2 expressed 
via heat 
Plan in 
as NO2)  
recovery boiler 
Schedule 
and APC plant 

A1 - as 
Cadmium & 
Incineration 
0.05 mg/m3  
periodic over 
Quarterly in first year. Then 
BS EN 14385 
shown on 
thallium and their 
exhaust gases 
minimum 30 
Bi-annual 
the Site 
compounds 
via heat 
minute, maximum 
Plan in 
(total) 
recovery boiler 
8 hour period 
Schedule 
and APC plant 

A1 - as 
Mercury and its 
Incineration 
0.05 mg/m3 
periodic over 
Quarterly in first year. Then 
BS EN 13211 
shown on 
compounds  
exhaust gases 
minimum 30 
Bi-annual 
the Site 
via heat 
minute, maximum 
Plan in 
recovery boiler 
8 hour period 
Schedule 
and APC plant 

A1 - as 
Sb, As, Pb, Cr, 
Incineration 
0.5 mg/m3 
periodic over 
Quarterly in first year. Then 
BS EN 14385 
shown on 
Co, Cu, Mn, Ni 
exhaust gases 
minimum 30 
Bi-annual 
the Site 
and V and their 
via heat 
minute, maximum 
Plan in 
compounds 
recovery boiler 
8 hour period 
Schedule 
(total)  
and APC plant 

Permit Number    
EPR/CP3535CK Page 
23 
Javelin 
Park 
ERF 
 
   
          

 
Table S3.1  Point source emissions to air – emission limits and monitoring requirements 
Emission 
Parameter   
Source 
Limit 
Reference period 
Monitoring frequency 
Monitoring 
point ref. 
(including 
standard(s) or 
& location 
unit)  
method(s) 
A1 - as 
Ammonia (NH3)  
Incineration 
No Limit Set 
daily average 
Continuous 
BS EN 14181 
shown on 
exhaust gases 
the Site 
via heat 
Plan in 
recovery boiler 
Schedule 
and APC plant 

A1 - as 
Nitrous oxide 
Incineration 
No Limit Set 
periodic over 
Quarterly in the first year of 
BS EN ISO 21258 
shown on 
(N2O)  
exhaust gases 
minimum 1-hour 
operation, then bi-annual  
the Site 
via heat 
period 
Plan in 
recovery boiler 
Schedule 
and APC plant 

A1 - as 
Dioxins / furans 
Incineration 
0.1 ng/m3 
periodic over 
Quarterly in first year. Then 
BS EN 1948 Parts 1, 
shown on 
(I-TEQ) 
exhaust gases 
minimum 6 hours, 
Bi-annual 
2 and 3 
the Site 
via heat 
maximum 8 hour 
Plan in 
recovery boiler 
period 
Schedule 
and APC plant 

A1 - as 
Dioxins / furans 
Incineration 
No Limit Set 
periodic over 
Quarterly in first year. Then 
BS EN 1948 Parts 1, 
shown on 
(WHO-TEQ 
exhaust gases 
minimum 6 hours, 
Bi-annual 
2 and 3 
the Site 
Humans / 
via heat 
maximum 8 hour 
Plan in 
Mammals)  
recovery boiler 
period 
Schedule 
and APC plant 

Permit Number    
EPR/CP3535CK Page 
24 
Javelin 
Park 
ERF 
 
   
          

 
Table S3.1  Point source emissions to air – emission limits and monitoring requirements 
Emission 
Parameter   
Source 
Limit 
Reference period 
Monitoring frequency 
Monitoring 
point ref. 
(including 
standard(s) or 
& location 
unit)  
method(s) 
A1 - as 
Dioxins / furans 
Incineration 
No Limit Set 
periodic over 
Quarterly in first year. Then 
BS EN 1948 Parts 1, 
shown on 
(WHO-TEQ Fish)  
exhaust gases 
minimum 6 hours, 
Bi-annual 
2 and 3 
the Site 
via heat 
maximum 8 hour 
Plan in 
recovery boiler 
period 
Schedule 
and APC plant 

A1 - as 
Dioxins / furans 
Incineration 
No Limit Set 
periodic over 
Quarterly in first year. Then 
BS EN 1948 Parts 1, 
shown on 
(WHO-TEQ 
exhaust gases 
minimum 6 hours, 
Bi-annual 
2 and 3 
the Site 
Birds)  
via heat 
maximum 8 hour 
Plan in 
recovery boiler 
period 
Schedule 
and APC plant 

A1 - as 
Dioxin-like PCBs 
Incineration 
No Limit Set 
periodic over 
Quarterly in first year. Then 
BS EN 1948-4 
shown on 
(WHO-TEQ 
exhaust gases 
minimum 6 hours, 
Bi-annual 
the Site 
Humans / 
via heat 
maximum 8 hour 
Plan in 
Mammals) 
recovery boiler 
period 
Schedule 
and APC plant 

A1 - as 
Dioxin-like PCBs 
Incineration 
No Limit Set 
periodic over 
Quarterly in first year. Then 
BS EN 1948-4 
shown on 
(WHO-TEQ  Fish) 
exhaust gases 
minimum 6 hours, 
Bi-annual 
the Site 
via heat 
maximum 8 hour 
Plan in 
recovery boiler 
period 
Schedule 
and APC plant 

Permit Number    
EPR/CP3535CK Page 
25 
Javelin 
Park 
ERF 
 
   
          

 
Table S3.1  Point source emissions to air – emission limits and monitoring requirements 
Emission 
Parameter   
Source 
Limit 
Reference period 
Monitoring frequency 
Monitoring 
point ref. 
(including 
standard(s) or 
& location 
unit)  
method(s) 
A1 - as 
Dioxin-like PCBs 
Incineration 
No Limit Set 
periodic over 
Quarterly in first year. Then 
BS EN 1948-4 
shown on 
(WHO-TEQ  
exhaust gases 
minimum 6 hours, 
Bi-annual 
the Site 
Birds) 
via heat 
maximum 8 hour 
Plan in 
recovery boiler 
period 
Schedule 
and APC plant 

A1 - as 
Specific individual 
Incineration 
No Limit Set 
periodic over 
Quarterly in first year. Then 
BS ISO 11338 Parts 
shown on 
poly-cyclic 
exhaust gases 
minimum 6 hours, 
Bi-annual 
1 and 2. 
the Site 
aromatic 
via heat 
maximum 8 hour 
Plan in 
hydrocarbons 
recovery boiler 
period 
Schedule 
(PAHs), as 
and APC plant 

specified in 
Schedule 6. 
A2 - IBA 
No parameter set 
Local exhaust 
No Limits Set 
 
 
 
Process 
ventilation via 
Building at 
filtration system 
the 
from IBA 
eastern 
Processing 
end of the 
building 
building 
complex 
 
 
Permit Number    
EPR/CP3535CK Page 
26 
Javelin 
Park 
ERF 
 
   
          

 
Table S3.1(a)  Point source emissions to air during abnormal operation of incineration plant – emission limits and monitoring requirements 
Emission 
Parameter   
Source 
Limit (including 
Reference period 
Monitoring 
Monitoring standard or 
point ref. 
unit)  
frequency 
method 
& location 
[1] 

A1 - as 
Particulate 
Incineration 
150 mg/m3   
½-hr average 
Continuous 
BS EN 15267-3 during 
shown on 
matter 
exhaust gases 
measurement  
abatement plant failure 
the Site 
via heat 
Plan in 
recovery boiler 
Schedule 7 
and APC plant 
A1 - as 
Total Organic 
Incineration 
20 mg/m3  
½-hr average 
Continuous 
BS EN 15267-3 during 
shown on 
Carbon (TOC) 
exhaust gases 
measurement  
abatement plant failure 
the Site 
via heat 
Plan in 
recovery boiler 
Schedule 7 
and APC plant 
A1 - as 
Carbon  
Incineration 
100  mg/m3 
½-hr average 
Continuous 
BS EN 15267-3 during 
shown on 
monoxide 
exhaust gases 
measurement  
abatement plant failure 
the Site 
via heat 
Plan in 
recovery boiler 
Schedule 7 
and APC plant 
Note [1]:  Location as described in the Application. 
Permit Number    
EPR/CP3535CK Page 
27 
Javelin 
Park 
ERF 
 
   
          

 
 
Table S3.2 Point Source emissions to water (other than sewer) and land – emission limits and monitoring 
requirements 

Emission 
Parameter   
Source 
Limit  
Reference  
Monitoring 
Monitoring 
point ref. 
Period 
frequency 
standard or 

method 
location 
W1 & W2 
Uncontamin
as shown 
ated surface 
on the 
No 
water via 
No 
Site Plan 
parameters 
attenuation 
Limit 
- - 

in 
set 
ponds and 
Set 
Schedule 
oil 

interceptor 
 
Table S3.3  Process  monitoring requirements 
Location [1] or 
Parameter Monitoring Monitoring 
Other specifications 
description of point of 
frequency 
standard or 
measurement 
method 
As agreed with the 
Wind 
Continuous Anemometer 
  
Agency 
Speed and 
Direction 
Location close to the 
Temperatu
Continuous Traceable 
to As agreed in writing with the 
Combustion Chamber 
re (° C) 
national 
Agency. 
inner wall or as 
standards 
identified and justified in 
Application. 
Permit Number    
EPR/CP3535CK Page 
28 
Javelin 
Park 
ERF 
 
   
          

 
A1 - as shown on the 
Exhaust 
Continuous Traceable 
to As agreed in writing with the 
Site Plan in Schedule 7 
gas 
national 
Agency. 
temperatur
standards 

A1 - as shown on the 
Exhaust 
Continuous Traceable 
to As agreed in writing with the 
Site Plan in Schedule 7 
gas 
national 
Agency. 
pressure 
standards 
A1 - as shown on the 
Exhaust 
Continuous BS 
EN 
 
Site Plan in Schedule 7 
gas oxygen 
15267-3 
content 
BS EN 
14181 
A1 - as shown on the 
Exhaust 
Continuous BS 
EN 
Unless gas is dried before 
Site Plan in Schedule 7 
gas water 
15267-3 
analysis of emissions. 
vapour 
BS EN 
content 
14181 
Note [1]:  Location as described in the Application. 
 
Permit Number    
EPR/CP3535CK Page 
29 
Javelin 
Park 
ERF 
 
   
          

 
Table S3.4  Residue quality 
Emission point reference 
Parameter Limit 
Monitoring 
Monitoring 
Other 
or source or description 
frequency  
standard or 
specifications  
of point of measurement 
method * 
 
Bottom Ash 
TOC  
<3% 
Monthly in the first 
Environment 
 
 
year of operation. 
Agency ash 
Then Quarterly 
sampling 
protocol. 
Bottom Ash 
Metals (Antimony, Cadmium, Thallium, 
No Limit 
Monthly in the first 
Sampling and 
 
Mercury, Lead, Chromium, Copper, 
Set 
year of operation. 
analysis as per 
Manganese, Nickel, Arsenic, Cobalt, 
Then Quarterly 
Environment 
Vanadium, Zinc) and their compounds, 
Agency ash 
dioxins/furans and dioxin-like PCBs.   
sampling 
protocol. 
Bottom Ash 
Total soluble fraction and metals (Antimony, 
No Limit 
Before use of a 
Sampling and 
 
Cadmium, Thallium, Mercury, Lead, 
Set 
new disposal or 
analysis as per 
Chromium, Copper, Manganese, Nickel, 
recycling route 
Environment 
Arsenic, Cobalt, Vanadium, Zinc) soluble 
Agency ash 
fractions 
sampling 
protocol. 
APC Residues 
Metals (Antimony, Cadmium, Thallium, 
No Limit 
Monthly in the first 
Sampling and 
 
Mercury, Lead, Chromium, Copper, 
Set 
year of operation. 
analysis as per 
Manganese, Nickel, Arsenic, Cobalt, 
Then Quarterly 
Environment 
Vanadium, Zinc) and their compounds, 
Agency ash 
dioxins/furans and dioxin-like PCBs.   
sampling 
protocol. 
APC Residues 
Total soluble fraction and metals (Antimony, 
No Limit 
Before use of a 
Sampling and 
 
Cadmium, Thallium, Mercury, Lead, 
Set 
new disposal or 
analysis as per 
Chromium, Copper, Manganese, Nickel, 
recycling route 
Environment 
Arsenic, Cobalt, Vanadium, Zinc) soluble 
Agency ash 
fractions 
sampling 
protocol. 
Permit number 
EPR/CP3535CK 
 
30 

 
Schedule 4 - Reporting 
Parameters, for which reports shall be made, in accordance with conditions of this permit, are listed below 
 
Table S4.1 Reporting of monitoring data 
Parameter Emission 
or 
Reporting 
Period 
monitoring 
period 
begins 
point/reference 
Emissions to air 
A1 Quarterly 

Jan, 

Apr, 
Parameters as required by 
1 Jul and 1 
condition 3.5.1 
Oct 
TOC  
Bottom Ash 
Quarterly (but 
1 Jan, 1 Apr, 
Parameters as required by 
monthly for 
1 Jul and 1 
condition 3.5.1 
the first year 
Oct 
of operation) 
Metals (Antimony, Cadmium, 
Bottom Ash 
Quarterly (but 
1 Jan, 1 Apr, 
Thallium, Mercury, Lead, 
monthly for 
1 Jul and 1 
Chromium, Copper, 
the first year 
Oct 
Manganese, Nickel, Arsenic, 
of operation) 
Cobalt, Vanadium, Zinc) and 
their compounds, 
dioxins/furans and dioxin-like 
PCBs  
Parameters as required by 
condition 3.5.1  
Total soluble fraction and 
Bottom Ash 
Before use of 
 
metals (Antimony, Cadmium, 
a new 
Thallium, Mercury, Lead, 
disposal or 
Chromium, Copper, 
recycling 
Manganese, Nickel, Arsenic, 
route 
Cobalt, Vanadium, Zinc) 
soluble fractions 
Parameters as required by 
condition 3.5.1 
Metals (Antimony, Cadmium, 
APC Residues 
Quarterly (but 
1 Jan, 1 Apr, 
Thallium, Mercury, Lead, 
monthly for 
1 Jul and 1 
Chromium, Copper, 
the first year 
Oct 
Manganese, Nickel, Arsenic, 
of operation) 
Cobalt, Vanadium, Zinc) and 
their compounds, 
dioxins/furans and dioxin-like 
PCBs 
Parameters as required by 
condition 3.5.1   
Total soluble fraction and 
APC Residues 
Before use of 
 
metals (Antimony, Cadmium, 
a new 
Thallium, Mercury, Lead, 
disposal or 
Chromium, Copper, 
recycling 
Manganese, Nickel, Arsenic, 
route 
Cobalt, Vanadium, Zinc) 
soluble fractions 
Parameters as required by 
condition 3.5.1   
Permit number 
EPR/CP3535CK  
31 

 
Table S4.1 Reporting of monitoring data 
Parameter Emission 
or 
Reporting 
Period 
monitoring 
period 
begins 
point/reference 
Functioning and monitoring of 
 Annually 
 

Jan 
the incineration plant as 
required by condition 4.2.2 
 
Table S4.2: Annual production/treatment 
 
Parameter  
Units  
Total Municipal Waste Incinerated (a) 
tonnes 
Total Commercial and Industrial Waste incinerated (b) 
tonnes 
Total Waste incinerated (a + b) 
tonnes 
Electrical energy exported (c) 
KWh 
Electrical energy produced and used on installation (d) 
KWh 
Total electrical energy produced (c + d) 
KWh 
Heat energy exported from the installation (e) 
KWh 
Total Incinerator Bottom Ash Aggregate (IBAA) exported (f) 
tonnes 
Total quantity  APC Residue produced (g) 
tonnes 
 
Table S4.3 Performance parameters 
Parameter Frequency 
of 
assessment 
Units 
Total waste incinerated 
Quarterly 
tonnes 
Electrical energy exported, 
Quarterly 
KWhrs / tonne of waste 
imported and used at the 
incinerated 
installation 
Fuel oil consumption 
Quarterly 
Kg / tonne of waste 
incinerated 
Mass of Bottom Ash produced 
Quarterly 
Kg / tonne of waste 
incinerated 
Mass of Incinerator Bottom Ash 
Quarterly 
Kg / tonne of waste 
Aggregate (IBAA) recovered 
incinerated 
Mass of APC residues produced 
Quarterly 
Kg / tonne of waste 
incinerated 
Mass of other solid residues 
Quarterly 
Kg / tonne of waste 
produced 
incinerated 
Ammonia consumption 
Quarterly 
Kg / tonne of waste 
incinerated 
Activated Carbon consumption 
Quarterly 
Kg / tonne of waste 
incinerated 
Hydrated Lime consumption 
Quarterly 
Kg / tonne of waste 
incinerated 
Water consumption 
Quarterly 
m3 / tonne of waste 
incinerated 
Permit number 
EPR/CP3535CK  
32 

 
Table S4.3 Performance parameters 
Parameter Frequency 
of 
assessment 
Units 
Periods of abnormal operation 
Quarterly 
No of occasions and 
cumulative hours for 
current calendar year. 
 
Table S4.4 Reporting forms 
Media/parameter 
Reporting format 
Date of form 
Air 
Form Air 1-8 or other form as agreed in writing by 
22/05/13 
the Environment Agency  
Residues 
Form Residues 1 or other form as agreed in 
22/05/13 
writing by the Environment Agency 
Energy usage 
Form Energy 1 or other form as agreed in writing 
22/05/13 
by the Environment Agency 
Other performance 
Form Performance 1 or other form as agreed in 
22/05/13 
indicators 
writing by the Environment Agency 
 
Permit number 
EPR/CP3535CK  
33 

 
Schedule 5 - Notification  
These pages outline the information that the operator must provide.   
Units of measurement used in information supplied under Part A and B requirements shall be appropriate to 
the circumstances of the emission. Where appropriate, a comparison should be made of actual emissions 
and authorised emission limits. 
If any information is considered commercially confidential, it should be separated from non-confidential 
information, supplied on a separate sheet and accompanied by an application for commercial confidentiality 
under the provisions of the EP Regulations. 
Part A  
Permit Number 
EPR/CP3535CK 
Name of operator 
Urbaser Environmental Limited 
Location of Facility 
Javelin Park ERF 
Time and date of the detection  
 
 
(a) Notification requirements for any malfunction, breakdown or failure of equipment or 
techniques, accident, or emission of a substance not controlled by an emission limit 
which has caused, is causing or may cause significant pollution 

To be notified within 24 hours of detection 
Date and time of the event 
 
Reference or description of the 
 
location of the event  
Description of where any release 
 
into the environment took place 
Substances(s) potentially 
 
released 
Best estimate of the quantity or 
 
rate of  release of substances 
Measures taken, or intended to 
 
be taken, to stop any emission 
Description of the failure or 
 
accident. 
 
(b) Notification requirements for the breach of a limit 
To be notified within 24 hours of detection unless otherwise specified below 
Emission point reference/ source 
 
Parameter(s)  
Limit  
Measured value and uncertainty 
 
Date and time of monitoring 
 
Measures taken, or intended to 
 
be taken, to stop the emission 
Permit number 
EPR/CP3535CK  
34 

 
 
Time periods for notification following detection of a breach of a limit 
Parameter Notification 
period 
 
 
 
 
 
 
 
(c) Notification requirements for the detection of any significant adverse environmental 
effect 
To be notified within 24 hours of detection 
Description of where the effect on 
 
the environment was detected 
Substances(s) detected 
 
Concentrations of substances 
 
detected 
Date of monitoring/sampling 
 
Part B - to be submitted as soon as practicable 
Any more accurate information on the matters for 
 
notification under Part A. 
Measures taken, or intended to be taken, to 
 
prevent a recurrence of the incident 
Measures taken, or intended to be taken, to rectify, 
 
limit or prevent any pollution of the environment 
which has been or may be caused by the emission 
The dates of any unauthorised emissions from the 
 
facility in the preceding 24 months. 
 
Name* 
 
Post 
 
Signature 
 
Date 
 
* authorised to sign on behalf of Urbaser Environmental Limited 
 
Permit number 
EPR/CP3535CK  
35 

 
Schedule 6 - Interpretation  
“abatement equipment” means that equipment dedicated to the removal of polluting substances from releases from the 
installation to air or water media
“abnormal operation” means any technically unavoidable stoppages, disturbances, or failures of the abatement plant or 
the measurement devices, during which the concentrations in the discharges into air and the purified waste water of the 
regulated substances may exceed the normal emission limit values.  
“accident” means an accident that may result in pollution. 
“APC residues” means air pollution control residues 
“application” means the application for this permit, together with any additional information supplied by the operator as part 
of the application and any response to a notice served under Schedule 5 to the EP Regulations. 
“authorised officer” means any person authorised by the Environment Agency under section 108(1) of The Environment 
Act 1995 to exercise, in accordance with the terms of any such authorisation, any power specified in section 108(4) of that 
Act
“bi-annual” means twice per year with at least five months between tests; 
“bottom ash” means ash falling through the grate and transported by the grate.  
“CEM” Continuous emission monitor 
“CEN” means Commité Européen de Normalisation 
“daily average”  for releases of substances to air means the average of valid half-hourly averages over a calendar day 
during normal operation.  
dioxin and furans” means polychlorinated dibenzo-p-dioxins and polychlorinated dibenzofurans. 
“disposal”  means any of the operations provided for in Annex IIA to Directive 2008/98/EC of the Waste Framework 
Directive. 
 “emissions to land” includes emissions to groundwater. 
“EP Regulations” means The Environmental Permitting (England and Wales) Regulations SI 2010 No.675 and words and 
expressions used in this permit which are also used in the Regulations have the same meanings as in those Regulations. 
“emissions of substances not controlled by emission limits” means emissions of substances to air, water or land from the 
activities, either from the emission points specified in schedule 3 or from other localised or diffuse sources, which are not 
controlled by an emission limit. 
“groundwater” means all water, which is below the surface of the ground in the saturation zone and in direct contact with 
the ground or subsoil. 
“hazardous property” has the meaning given in Schedule 3 of the Hazardous Waste (England and Wales) Regulations 
2005 No.894 and the Hazardous Waste (Wales) Regulations 2005 No. 1806 (W.138). 
 “incineration line” means all of the incineration equipment related to a common discharge to air location. 
“Industrial Emissions Directive” means DIRECTIVE 2010/75/EU OF THE EUROPEAN PARLIAMENT AND OF THE 
COUNCIL of 24 November 2010 on industrial emissions 
 “ISO” means International Standards Organisation. 
“LOI” means loss on ignition a technique used to determine the combustible material by heating the ash residue to a high 
temperature 
“MCERTS” means the Environment Agency’s Monitoring Certification Scheme
“PAH” means Poly-cyclic aromatic hydrocarbon, and comprises Anthanthrene, Benzo[a]anthracene, Benzo[b]fluoranthene, 
Benzo[k]fluoranthene, Benzo[b]naph(2,1-d)thiophene, Benzo[c]phenanthrene, Benzo[ghi]perylene, Benzo[a]pyrene, 
Cholanthrene, Chrysene, Cyclopenta[c,d]pyrene, Dibenzo[ah]anthracene, Dibenzo[a,i]pyrene Fluoranthene, Indo[1,2,3-
Permit number 
EPR/CP3535CK  
36 

 
cd]pyrene, Naphthalene 
“PCB” means Polychlorinated Biphenyl. Dioxin-like PCBs are the non-ortho and mono-ortho PCBs listed in the table below. 
“quarter” means a calendar year quarter commencing on 1 January, 1 April, 1 July or 1 October. 
 “quarterly”  for reporting/sampling means after/during each 3 month period, January to March; April to June; July to 
September and October to December and, when sampling, with at least 2 months between each sampling date. 
“recovery”  means any of the operations provided for in Annex IIB to Directive 2008/98/EC of the Waste Framework 
Directive. 
shut down” is any period where the plant is being returned to a non-operational state as described in the application or 
agreed in writing with the Environment Agency. 
 “start up” is any period, where the plant has been non-operational, after igniting the auxiliary burner until waste has been 
fed to the plant in sufficient quantity to cover the grate and to initiate steady-state conditions.  
“TOC”  means Total Organic Carbon. In respect of releases to air, this means the gaseous and vaporous organic 
substances, expressed as TOC. In respect of Bottom Ash, this means the total carbon content of all organic species 
present in the ash (excluding carbon in elemental form). 
1. 
“Waste code” means the six digit code referable to a type of waste in accordance with 
the List of Wastes (England)Regulations 2005, or List of Wastes (Wales) Regulations 2005, as appropriate, and in relation 
to hazardous waste, includes the asterisk.  
 “WFD” means Waste Framework Directive (Directive 2008/98/EC of the European Parliament and Council). 
“year” means calendar year ending 31 December. 
Where a minimum limit is set for any emission parameter, for example pH, reference to exceeding the limit shall mean 
that the parameter shall not be less than that limit. 
Unless otherwise stated, any references in this permit to concentrations of substances in emissions into air means: 
(a)  in relation to emissions from non-combustion sources, the concentration at a temperature of 273K and at a 
pressure of 101.3 kPa, with no correction for water vapour content. 
(b)  in relation to gases from incineration and co-incineration plants other than those burning waste oil, the 
concentration in dry air at a temperature of 273K, at a pressure of 101.3 kPa and with an oxygen content of 11% 
dry.   
For dioxins/furans and dioxin-like PCBs the determination of the toxic equivalence concentration (I-TEQ, & WHO-TEQ for 
dioxins/furans, WHO-TEQ for dioxin-like PCBs) stated as a release limit and/ or reporting requirement, the mass 
concentrations of the following congeners have to be multiplied with their respective toxic equivalence factors before 
summing. When reporting on measurements of dioxins/furans and dioxin-like PCBs, the toxic equivalence concentrations 
should be reported as a range based on: all congeners less than the detection limit assumed to be zero as a minimum, 
and all congeners less than the detection limit assumed to be at the detection limit as a maximum.  
 
TEF schemes for dioxins and furans 
Congener I-TEF 
WHO-TEF 
1990 2005  1997/8 
 Humans 

Fish Birds 
Mammals 
Dioxins 
 
 
 
2,3,7,8-TCDD 1 1 


1,2,3,7,8-PeCDD 0.5  1 


1,2,3,4,7,8-HxCDD 0.1 
0.1 
0.5 
0.05 
1,2,3,6,7,8-HxCDD 0.1 
0.1 
0.01 
0.01 
1,2,3,7,8,9-HxCDD 0.1 
0.1 
0.01 
0.1 
Permit number 
EPR/CP3535CK  
37 

 
1,2,3,4,6,7,8-HpCDD 0.01 
0.01 
0.001 
<0.001 
OCDD 0.001 
0.0003 


Furans 
 
 
 
 
2,3,7,8-TCDF 0.1 
0.1 
0.05 

1,2,3,7,8-PeCDF 0.05 0.03 
0.05 
0.1 
2,3,4,7,8-PeCDF 0.5  0.3 
0.5 

1,2,3,4,7,8-HxCDF 0.1 
0.1 
0.1 
0.1 
1,2,3,7,8,9-HxCDF 0.1 
0.1 
0.1 
0.1 
1,2,3,6,7,8-HxCDF 0.1 
0.1 
0.1 
0.1 
2,3,4,6,7,8-HxCDF 0.1 
0.1 
0.1 
0.1 
1,2,3,4,6,7,8_HpCDF 0.01 
0.01 
0.01 
0.01 
1,2,3,4,7,8,9-HpCDF 0.01 
0.01 
0.01 
0.01 
OCDF 0.001 
0.0003 
0.0001 
0.0001 
 
TEF schemes for dioxin-like PCBs 
Congener WHO-TEF 
2005 1997/8 
 Humans 

Fish Birds 
mammals 
Non-ortho PCBs 
 
 
 
3,4,4',5-TCB (81) 
0.0001 
0.0005 
0.1 
3,3',4,4'-TCB (77) 
0.0003 
0.0001 
0.05 
3,3',4,4',5 - PeCB (126) 
0.1 
0.005 
0.1 
3,3',4,4',5,5'-HxCB(169) 0.03 
0.00005 
0.001 
Mono-ortho PCBs 
 
 
 
2,3,3',4,4'-PeCB (105) 
0.00003 
<0.0000
0.0001 
05 
2,3,4,4',5-PeCB (114) 
0.00003 
<0.0000
0.0001 
05 
2,3',4,4',5-PeCB (118) 
0.00003 
<0.0000
0.00001 
05 
2',3,4,4',5-PeCB (123) 
0.00003 
<0.0000
0.00001 
05 
2,3,3',4,4',5-HxCB (156) 
0.00003 
<0.0000
0.0001 
05 
2,3,3',4,4',5'-HxCB (157) 
0.00003 
<0.0000
0.0001 
05 
2,3',4,4',5,5'-HxCB (167) 
0.00003 
<0.0000
0.00001 
05 
2,3,3',4,4',5,5'-HpCB (189) 
0.00003 
<0.0000
0.00001 
05 
 
Permit number 
EPR/CP3535CK  
38 




 
Schedule 7 - Site plan 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Crown Copyright. All rights reserved. Environment Agency, 100026380, 2011.”  
 
END OF PERMIT 
 
Permit number 
EPR/CP3535CK  
39