Protocol for joint working on Highway Cleansing issues between 
Sub Regional Local Authority Districts, Highways England and their 
Contractors 

Introduction 
The cleansing of any public highway that is not a motorway and where responsibility 
for its cleaning has not been transferred to a highways authority (Highways England 
or County Highways) under EPA S86(11) is the responsibility of the local authority. 
Section 89(2) of the Environmental Protection Act 1990 places a duty on the 
Secretary of State in respect of motorways, and on local authorities in respect of all 
other publicly maintainable highways in their area, to ensure that the highway or road 
is, so far as is practicable, kept clean. This is in addition to the section 89(1) 
requirement which relates to litter and refuse and therefore means removal of 
detritus. 
In such cases the EPA requires the duty bodies to ensure their roads are kept clear 
of litter and refuse as far as is “practicable”. 
“Practicable” however simply means “physically possible” without the need to take 
account of cost, time and trouble. This is in contrast to “reasonably practicable” 
where these considerations would come into play. Local authorities cannot therefore 
use traffic management as an excuse for not carrying out cleansing work on trunk 
roads; however such works are labour intensive, costly and hazardous.   
In order to fulfil these obligations representatives from local authorities within the 
sub-region, Highways England and the Highways Contractor have joined together to 
produce this protocol, a shared approach for public highway cleansing.  
The aim being by improving communication and co-operation sub-regionally safer 
working practices can be implemented and efficiency savings can be made. 
Members signed up to the protocol: 
Highways England  
Contractors of Highways England
Warwickshire County Council Highways 
Rugby Borough Council 
Warwick District Council  
Stratford District Council 
North Warwickshire Borough Council 
Nuneaton & Bedworth Borough Council 
Coventry City Council 
Solihull Metropolitan Borough Council 
Tamworth Borough Council 

PROTOCOL 
Co-operation & Co-ordination 
1. We commit to working together wherever practicable, sharing resources in
terms of crews and equipment in order to improve the general appearance of
the road network
2. We will promote the work that we carry out sub regionally to illustrate the
benefit of joint working
3. Highways England and/or their contractor will produce quarterly and annual
programmes of work and circulate them to the relevant local authority at the
earliest opportunity
4. A weekly list of road closures will be produced and circulated by the Press
Office, Highways England. There will be a presumption that LAs will be able to
share those road closures and undertake works alongside the contractor
unless specifically told otherwise. Local Authority Officers will access this list
weekly and wherever possible act on the information provided in order to
carry out cleansing works within road closure areas, liaising with the Contract
Officer on site responsible for the traffic management arrangement.
5. All Local Authorities will send a relevant person for induction with HE
contractor. This induction training will be cascaded through the team. We will
not send anyone who has not been inducted or certified by HE. Trained
personnel will be added to the central EM register.
6. Operational staff will attend site inductions as and when required prior to
carrying out works
7. Highways England or their contractor ‘site supervisor’ will be the lead officer
on site and shall direct crews accordingly.  Any issue with works should be
reported to the site supervisor immediately. Where possible a Local Authority
Supervisor will attend the start/completion of works and conduct a debrief.
8. It is the responsibility of each Local Authority to ensure appropriate PPE is
provided and worn at all times within the designated working area. All to
conform to the minimum standard colour of orange and reflective strips must
be to EN471 class 3 (reflectivity classification.) Must have two reflective strips
on the leg of the trousers, must have belt and braces on the long sleeved top.
9. Where practicable, Local Authorities will endeavour to take a common sense
approach to cross border working and will cease works at a convenient and
predetermined point, i.e road junction, which may encroach into a
neighbouring authority’s area.

10. Local Authorities will communicate regarding cross border working, providing 
extra resources, physical and mechanical, as necessary. All to make available 
an Asset List of available plant 
 
11. Highways England and their Contractors will provide timely information via the 
generic Inbox regarding road closures, in order that the LA’s can access the 
closure (whenever practicable) to carry out cleansing works 
 
12. Should road closures be cancelled or deferred Highways England contractors 
will notify respective Local Authorities Immediately and have a ’back up plan’ 
to direct crews elsewhere if practicable 
 
13. Should Local authorities be unable to commit to resources and works agreed, 
they shall notify Highways England or their contractor as soon as possible 
before the works are due to commence. 
 
14. Local Authorities will commit to a working arrangement which allows for staff 
to undertake a flexible working approach, mirroring night time road closures, 
whilst complying with working time directives and drivers hour’s 
responsibilities. 
 
15. Local Authority operational staff will be the responsibility of the Local 
Authorities, not HE contractor.  Any ‘on site’ incidents should be reported to 
the named contact in this agreement ASAP. A debriefing session will be held 
on completion of each closure 
 
16. Appropriate risk assessments and safe systems of work will be the 
responsibility of each local authority to provide, though information will be 
shared.   
 
17. All generic requirements and amendments will be shared with group members 
for Risk Assessment inclusion, as required and reviewed every six months 
 
18. Half yearly reviews of practices and appendices as necessary 
 
 
 
 
Grievances 
 
In such instances where there may be a grievance between one or more of the 
parties a grievance procedure will be invoked and a team of Officers not involved in 
the grievance will be allocated to arbitrate. The senior officers of the local Contractor 
and Authority will investigate and try to resolve in the first instance, if necessary HE 
will be the final arbitrator.