This is an HTML version of an attachment to the Freedom of Information request 'Information relating to Environmental Permits'.


Permit with introductory note 
The Environmental Permitting (England & Wales) Regulations 2010 
Hoddesdon Energy Limited 
Hoddesdon Energy from Waste Plant 
Ratty's Lane 
Hoddeson 
Hertfordshire 
EN11 0RF 
Permit number 
EPR/UP3038WA 
Permit number       
 01/04/2016 
EPR/UP3038WA/A001 


Hoddesdon Energy from Waste Plant 
Permit number EPR/UP3038WA 

Introductory note 
This introductory note does not form a part of the permit 
This permit controls the operation of a waste incineration plant. The relevant listed activity is S5.1 Part A(1) 
(b) the incineration of non-hazardous waste in a waste incineration plant or co-incineration plant with a 
capacity exceeding 3 tonnes per hour . The permit implements the requirements of the EU Directives on 
Industrial Emissions and Waste. 
The main features of the permit are as follows: 
The proposed Installation is located at Ratty’s Lane, (TL 38873 08983) Hoddesdon, Hertfordshire, EN11 
0RF.  
The plant is designed to generate electricity from pre-prepared waste feedstock’s using gasification. The 
feedstock will be refuse derived fuel (RDF). All feedstock arrives on site pre-treated, no further treatment is 
carried out on site. The expected throughput of the waste plant is between 85,000 - 112,915  tonnes per 
annum, this  variation will be dependent upon the calorific value of the feedstock. The typical calorific value 
of the waste feedstock is expected to be 15.5MJ. The operator expects to have no more than 5 days RDF 
stored on site at any one time. The energy within the RDF will be recovered to generate steam and used to 
power a steam turbine with a gross electrical output of 9.98MWe. Electricity from the plant will be exported to 
the Local Distribution Network. 
The plant is comprised of two identical lines (Line 1 linked to emission point A1 and Line 2 linked to emission 
point A2), of a two staged gasification/combustion unit, firstly the gasification unit produces a syngas and 
secondly the syngas is combusted. Heat from this process then goes to the heat recovery boiler, raising 
steam for the turbine and the generation of electricity.  
The abatement of pollutants to air is via a series of recognised techniques, bag filters, selective non-catalytic 
reduction (SNCR), Sorbacal dosing and PAC (powdered activated carbon) injection. The above techniques 
are well established and will allow the operator to meet the ELV’s specified by this permit and  the Industrial 
Emissions Directive (IED).  
Monitoring of all releases will be carried out in line with Chapter IV of the IED. 
There is currently no availability in the area to use recovered heat, however the operator will seek 
out opportunities for heat re-use and the plant is designed to meet the requirements of Article 44 of 
IED. 
Although there are a number of designated sites within the distance criteria the operator has 
shown there will be no significant effects from this process.  
The status log of the permit sets out the permitting history, including any changes to the permit reference 
number. 
Status log of the permit 
Description 
Date 
Comments 
Application 
Duly made 
Application for 9.98MW thermal input Power Station. 
EPR/UP3038WA/A001 
06/02/2015 
Additional information received 
06/02/2015 
Schedule 5  14/05/2015 
14/05/2015 
29/06/2015 
Permit number       
 01/04/2016 
EPR/UP3038WA/A001 


Status log of the permit 
Description 
Date 
Comments 
Permit determined 
01/04/2016 
Permit issued to  Hoddesdon Energy Limited 
End of introductory note 
Permit number       
 01/04/2016 
EPR/UP3038WA/A001 


Permit 
The Environmental Permitting (England and Wales) Regulations 2010 
Permit number 
EPR/UP3038WA 
The Environment Agency hereby authorises, under regulation 13 of the Environmental Permitting (England 
and Wales) Regulations 2010 
Hoddesdon Energy Limited (“the operator”), 
whose registered office is 
9 St. Georges Yard 
Farnham 
Surrey 
England 
GU9 7LW 

company registration number 8955328 
to operate an installation at 
Hoddesdon Energy from Waste Plant 
Ratty's Lane 
Hoddeson 
Hertfordshire 
EN11 0RF 

to the extent authorised by and subject to the conditions of this permit. 
Name 
Date 
Mike Jenkins 
 01/04/2016 
Authorised on behalf of the Environment Agency 
Permit number       
 01/04/2016 
EPR/UP3038WA/A001 


Conditions 

Management 
1.1  General management 
1.1.1  The operator shall manage and operate the activities: 
(a) in accordance with a written management system that identifies and minimises risks of pollution, 
including those arising from operations, maintenance, accidents, incidents, non-
conformances, closure and those drawn to the attention of the operator as a result of 
complaints; and 
(b) using sufficient competent persons and resources. 
1.1.2  Records demonstrating compliance with condition 1.1.1 shall be maintained. 
1.1.3  Any person having duties that are or may be affected by the matters set out in this permit shall have 
convenient access to a copy of it kept at or near the place where those duties are carried out. 
1.2  Energy efficiency 
1.2.1  The operator shall: 
(a) take appropriate measures to ensure that energy is recovered with a high level of energy 
efficiency and energy is used efficiently in the activities. 
(b) review and record at least every four years whether there are suitable opportunities to improve 
the energy efficiency of the activities; and  
(c) take any further appropriate measures identified by a review. 
1.2.2  The operator shall provide and maintain steam and/or hot water pass-outs such that opportunities for 
the further use of waste heat may be capitalised upon should they become practicable. 
1.2.3  The operator shall review the practicability of Combined Heat and Power (CHP) implementation at 
least every 2 years. The results shall be reported to the Agency within 2 months of each review. 
1.3  Efficient use of raw materials 
1.3.1  The operator shall: 
(a) take appropriate measures to ensure that raw materials and water are used efficiently in the 
activities; 
(b) maintain records of raw materials and water used in the activities; 
(c) review and record at least every four years whether there are suitable alternative materials that 
could reduce environmental impact or opportunities to improve the efficiency of raw material 
and water use; and 
(d) take any further appropriate measures identified by a review. 
1.4  Avoidance, recovery and disposal of wastes produced by the 
activities 
1.4.1  The operator shall take appropriate measures to ensure that: 
Permit number       
 01/04/2016 
EPR/UP3038WA/A001 


(a) the waste hierarchy referred to in Article 4 of the Waste Framework Directive is applied  to the 
generation of  waste by the activities; and 
(b) any waste generated by the activities is treated in accordance with the waste hierarchy referred 
to in Article 4 of the Waste Framework Directive; and 
(c) where disposal is necessary, this is undertaken in a manner which minimises its impact on the 
environment. 
1.4.2  The operator shall review and record at least every four years whether changes to those measures 
should be made and take any further appropriate measures identified by a review. 

Operations 
2.1  Permitted activities 
2.1.1  The operator is only authorised to carry out the activities specified in schedule 1 table S1.1 (the 
“activities”). 
2.1.2  Waste authorised by this permit shall be clearly distinguished from any other waste on the site. 
2.2  The site 
2.2.1  The activities shall not extend beyond the site, being the land shown edged in green on the site plan 
at schedule 7 to this permit. 
2.3  Operating techniques 
2.3.1  The activities shall, subject to the conditions of this permit, be operated using the  techniques and in 
the manner described in the documentation specified in schedule 1, table S1.2, unless otherwise 
agreed in writing by the Environment Agency. 
2.3.2  If notified by the Environment Agency that the activities are giving rise to pollution, the operator shall 
submit to the Environment Agency for approval within the period specified, a revision of any plan 
specified in schedule 1, table S1.2 or otherwise required under this permit which identifies and 
minimises the risks of pollution relevant to that plan , and shall implement the approved revised plan 
in place of the original from the date of approval, unless otherwise agreed in writing by the 
Environment Agency. 
2.3.3  Any raw materials or fuels listed in schedule 2 table S2.1 shall conform to the specifications set out in 
that table. 
2.3.4  Waste shall only be accepted if: 
(a) it is of a type and quantity listed in schedule 2 table S2.2  and 
(b) it conforms to the description in the documentation supplied by the producer or holder; and 
(c) it having been separately collected for recycling, it is subsequently unsuitable for recovery by 
recycling. 
2.3.5  The operator shall ensure that where waste produced by the activities is sent to a relevant waste 
operation, that operation is provided with the following information, prior to the receipt of the waste: 
(a) the nature of the process producing the waste; 
(b) the composition of the waste; 
(c) the handling requirements of the waste; 
(d) the hazardous property associated with the waste, if applicable; and 
Permit number       
 01/04/2016 
EPR/UP3038WA/A001 


(e) the waste code of the waste. 
2.3.6  The operator shall ensure that where waste produced by the activities is sent to a landfill site, it 
meets the waste acceptance criteria for that landfill. 
2.3.7  Waste shall not be charged, or shall cease to be charged, if: 
(a) the combustion chamber  temperature is below, or falls below, 850°C; or 
(b) any continuous emission limit value in schedule 3 table S3.1(a) is exceeded; or 
(c) any continuous emission limit value in schedule 3 table S3.1 is exceeded, other than under 
abnormal operating conditions; or 
(d) monitoring results required to demonstrate compliance with any continuous emission limit value 
in schedule 3 table S3.1 are unavailable other than under abnormal operating conditions. 
2.3.8  The operator shall have at least one auxiliary burner in each line at start up or shut down or 
whenever the operating temperature falls below that specified in condition 2.3.7, as long as 
incompletely burned waste is present in the combustion chamber. Unless the temperature specified 
in condition 2.3.7 is maintained in the combustion chamber, such burner(s) may be fed only with 
fuels which result in emissions no higher than those arising from the use of gas oil, liquefied gas or 
natural gas.   
2.3.9  The operator shall record the beginning and end of each period of “abnormal operation”. 
2.3.10  During a period of “abnormal operation”, the operator shall restore normal operation of the failed 
equipment or replace the failed equipment as rapidly as possible. 
2.3.11  Where, during “ abnormal operation”, on an incineration line, any of  the following situations arise, 
waste shall cease to be charged on that line until normal operation can be restored: 
(a) continuous measurement shows that an emission exceeds any emission limit value in schedule 
3 table S3.1 due to disturbances or failures of the abatement systems, or continuous emission 
monitor(s) are out of service, as the case may be, for a total of 4 hours uninterrupted duration; 
(b) the cumulative duration of “ abnormal operation” periods over 1 calendar year has reached 60 
hours; 
(c) continuous measurement shows that an emission exceeds any emission limit value in schedule 
3 table S3.1 (a) due to disturbances or failures of the abatement systems; 
(d) continuous emission monitors or alternative techniques to demonstrate compliance with the 
emission limit value(s) for particulates, TOC and / or CO in schedule 3 table S3.1 (a), as 
detailed in the application,  are unavailable.  
2.3.12  The operator shall interpret the end of the period of “abnormal operation” as the earliest of the 
following: 
(a) when the failed equipment is repaired and brought back into normal operation; 
(b) when the operator initiates a shutdown of the waste combustion activity, as described in the 
application or as agreed in writing with the Environment Agency; 
(c) when a period of four hours has elapsed from the start of the “abnormal operation”; 
(d) when, in any calendar year, an aggregated period of 60 hours “abnormal operation” has been 
reached.  
2.3.13  Bottom ash and APC residues shall not be mixed. 
2.3  Improvement programme 
2.3.1  The operator shall complete the improvements specified in schedule 1 table S1.3 by the date 
specified in that table unless otherwise agreed in writing by the Environment Agency. 
Permit number       
 01/04/2016 
EPR/UP3038WA/A001 


2.3.2  Except in the case of an improvement which consists only of a submission to the Environment 
Agency, the operator shall notify the Environment Agency within 14 days of completion of each 
improvement. 
2.4  Pre-operational conditions 
2.4.1  The activities shall not be brought into operation until the measures specified in schedule 1 table 
S1.4 have been completed. 

Emissions and monitoring 
3.1  Emissions to water, air or land 
3.1.1  There shall be no point source emissions to water, air or land except from the sources and emission 
points listed in schedule 3 tables S3.1, S3.2 and S3.3 except in “abnormal operation”, when there 
shall be no point source emissions to water, air or land except from the sources and emission points 
listed in schedule 3 tables S3.1(a), S3.2 and S3.3. 
3.1.2  The limits given in schedule 3 shall not be exceeded. 
3.1.3  For the following activities referenced in schedule 1, table S1.1. Where a substance is specified in 
schedule 3 table S3.2 or S3.3 but no limit is set for it, the concentration of such substance in 
emissions to water from the relevant emission point shall be no greater than the background 
concentration. 
3.1.4  Wastes produced at the site shall, as a minimum, be sampled and analysed in accordance with 
schedule 3 table S 3.5 Additional samples shall be taken and tested and appropriate action taken, 
whenever: 
(a) disposal or recovery routes change; or 
(b) it is suspected that the nature or composition of the waste has changed such that the route 
currently selected may no longer be appropriate. 
3.2  Emissions of substances not controlled by emission limits 
3.2.1  Emissions of substances not controlled by emission limits (excluding odour) shall not cause pollution. 
The operator shall not be taken to have breached this condition if appropriate measures, including, 
but not limited to, those specified in any approved emissions management plan, have been taken to 
prevent or where that is not practicable, to minimise, those emissions. 
3.2.2  The operator shall: 
(a) if notified by the Environment Agency that the activities are giving rise to pollution, submit to the 
Environment Agency for approval within the period specified, an emissions management plan 
which identifies and minimises the risks of pollution from emissions of substances not 
controlled by emission limits; 
(b) implement the approved emissions management plan, from the date of approval, unless 
otherwise agreed in writing by the Environment Agency. 
3.2.3  All liquids in containers, whose emission to water or land could cause pollution, shall be provided 
with secondary containment, unless the operator has used other appropriate measures to prevent or 
where that is not practicable, to minimise, leakage and spillage from the primary container. 
3.2.4  The Operator shall carry out monitoring of soil and groundwater in accordance with IED articles 
14(1)(b), 14(1)(e) and 16(2) to the protocol agreed in writing with the Environment Agency under 
PO8 
Permit number       
 01/04/2016 
EPR/UP3038WA/A001 


3.3   Odour 
3.3.1  Emissions from the activities shall be free from odour at levels likely to cause pollution outside the 
site, as perceived by an authorised officer of the Environment Agency, unless the operator has used 
appropriate measures, including, but not limited to, those specified in any approved odour 
management plan, to prevent or where that is not practicable to minimise the odour.  
3.3.2  The operator shall: 
(a) if notified by the Environment Agency that the activities are giving rise to pollution outside the 
site due to odour, submit to the Environment Agency for approval within the period specified, 
an odour management plan which identifies and minimises the  risks of pollution from odour; 
(b) implement the approved odour management plan, from the date of approval, unless otherwise 
agreed in writing by the Environment Agency. 
3.4  Noise and vibration 
3.4.1  Emissions from the activities shall be free from noise and vibration at levels likely to cause pollution 
outside the site, as perceived by an authorised officer of the Environment Agency, unless the 
operator has used appropriate measures, including, but not limited to, those specified in any 
approved noise and vibration management plan to prevent or where that is not practicable to 
minimise the noise and vibration. 
3.4.2  The operator shall: 
(a) if notified by the Environment Agency that the activities are giving rise to pollution outside the 
site due to noise and vibration, submit to the Environment Agency for approval within the 
period specified, a noise and vibration management plan which identifies and minimises the 
risks of pollution from noise and vibration; 
(b) implement the approved noise and vibration management plan, from the date of approval, 
unless otherwise agreed in writing by the Environment Agency. 
3.5  Monitoring  
3.5.1  The operator shall, unless otherwise agreed in writing by the Environment Agency, undertake the 
monitoring specified in the following tables in schedule 3 to this permit: 
(a) point source emissions specified in tables S3.1 and S3.1(a)  
(b) process monitoring specified in table S3.4; 
(c) residue quality in table S3.5 
3.5.2  The operator shall maintain records of all monitoring required by this permit including records of the 
taking and analysis of samples, instrument measurements (periodic and continual), calibrations, 
examinations, tests and surveys and any assessment or evaluation made on the basis of such data. 
3.5.3  Monitoring equipment, techniques, personnel and organisations employed for the emissions 
monitoring programme and the environmental or other monitoring specified in condition 3.5.1 shall 
have either MCERTS certification or MCERTS accreditation (as appropriate) unless otherwise 
agreed in writing by the Environment Agency. Newly installed CEMs, or CEMs replacing existing 
CEMs, shall have MCERTS certification and have an MCERTS certified range which is not greater 
than 1.5 times the daily emission limit value (ELV) specified in schedule 3 table S3.1. The CEM shall 
also be able to measure instantaneous values over the ranges which are to be expected during all 
operating conditions. If it is necessary to use more than one range setting of the CEM to achieve this 
requirement, the CEM shall be verified for monitoring supplementary, higher ranges. 
3.5.4  Permanent means of access shall be provided to enable sampling/monitoring to be carried out in 
relation to the emission points specified in schedule 3 tables S3.1 and S3.1(a), unless otherwise 
agreed in writing by the Environment Agency. 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 


3.5.5  Where Continuous Emission Monitors are installed to comply with the monitoring requirements in 
schedule 3 table S3.1; the Continuous Emission Monitors shall be used such that;  
(a) the values of the 95% confidence intervals of a single measured result at the daily emission limit 
value shall not exceed the following percentages of the emission limit values:  
• 
Carbon monoxide    
 
 
 
 
10% 
• 
Sulphur dioxide 
 
 
 
 
20%  
• 
Oxides of nitrogen (NO & NO2 expressed as NO2) 
20% 
• 
Particulate matter 
 
 
 
 
30% 
• 
Total organic carbon (TOC)  
 
 
 
30% 
• 
Hydrogen chloride  
 
 
 
 
40% 
(b) valid half-hourly average values shall be determined within the effective operating time 
(excluding the start-up and shut-down periods) from the measured values after having 
subtracted the value of the confidence intervals in condition 3.5.5 (a);  
(c) where it is necessary to calibrate or maintain the monitor and this means that data are not 
available for a complete half-hour period, the half-hourly average shall in any case be 
considered valid if measurements are available for a minimum of 20 minutes during the half-
hour. The number of half-hourly  averages so validated shall not exceed 5 per day;  
(d) daily average values shall be determined as the average of all the valid half-hourly average 
values within a calendar day. The daily average value shall be considered valid if no more 
than five half-hourly average values in any day have been determined not to be valid;  
(e) no more than ten daily average values per year shall be determined not to be valid. 
3.6  Pests 
3.6.1  The activities shall not give rise to the presence of pests which are likely to cause pollution, hazard or 
annoyance outside the boundary of the site. The operator shall not be taken to have breached this 
condition if appropriate measures, including, but not limited to, those specified in any approved pests 
management plan, have been taken to prevent or where that is not practicable, to minimise the 
presence of pests on the site.   
3.6.2  The operator shall: 
 
(a) if notified by the Environment Agency, submit to the Environment Agency for approval within the 
period specified, a pests management plan which identifies and minimises risks of pollution 
from pests; 
(b) implement the pests management plan, from the date of approval, unless otherwise agreed in 
writing by the Environment Agency. 

Information 
4.1  Records 
4.1.1  All records required to be made by this permit shall: 
(a) be legible; 
(b) be made as soon as reasonably practicable; 
(c) if amended, be amended in such a way that the original and any subsequent amendments 
remain legible, or are capable of retrieval; and 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
10 

(d) be retained, unless otherwise agreed in writing by the Environment Agency, for at least 6 years 
from the date when the records were made, or in the case of the following records until permit 
surrender: 
(i) 
off-site environmental effects; and 
(ii)  matters which affect the condition of the land and groundwater. 
4.1.2  The operator shall keep on site all records, plans and the management system required to be 
maintained by this permit, unless otherwise agreed in writing by the Environment Agency. 
4.2  Reporting 
4.2.1  The operator shall send all reports and notifications required by the permit to the Environment 
Agency using the contact details supplied in writing by the Environment Agency. 
4.2.2  A report or reports on the performance of the activities over the previous year shall be submitted to 
the Environment Agency by 31 January (or other date agreed in writing by the Environment Agency) 
each year.  The report(s) shall include as a minimum: 
(a) a review of the results of the monitoring and assessment carried out in accordance with the 
permit including an interpretive review of that data; 
(b) the annual production /treatment data set out in schedule 4 table S4.2; and 
(c) the performance parameters set out in schedule 4 table S4.3 using the forms specified in table 
S4.4 of that schedule. 
(d) the functioning and monitoring of the incineration plant in a format agreed with the Environment 
Agency. The report shall, as a minimum requirement (as required by Chapter IV of the 
Industrial Emissions  Directive) give an account of the running of the process and the 
emissions into air and water compared with the emission standards in the IED. 
4.2.3  Within 28 days of the end of the reporting period the operator shall, unless otherwise agreed in 
writing by the Environment Agency, submit reports of the monitoring and assessment carried out in 
accordance with the conditions of this permit, as follows: 
(a) in respect of the parameters and emission points specified in schedule 4 table S4.1; 
(b) for the reporting periods specified in schedule 4 table S4.1 and using the forms specified in 
schedule 4 table S4.4 ; and 
(c) giving the information from such results and assessments as may be required by the forms 
specified in those tables. 
4.2.4  The operator shall, unless notice under this condition has been served within the preceding four 
years, submit to the Environment Agency, within six months of receipt of a written notice, a report 
assessing whether there are other appropriate measures that could be taken to prevent, or where 
that is not practicable, to minimise pollution. 
4.2.5  Within 1 month of the end of each quarter, the operator shall submit to the Environment Agency 
using the form made available for the purpose, the information specified on the form relating to the 
site and the waste accepted and removed from it during the previous quarter. 
4.3  Notifications 
4.3.1  In the event: 
(a) that the operation of the activities gives rise to an incident or accident which  significantly affects 
or may significantly affect the environment, the operator must immediately— 
(i) 
inform the Environment Agency, 
Permit number       
 01/04/2016 
EPR/UP3038WA/A001 
11 

(ii)  take the measures necessary to limit the environmental consequences of such an incident 
or accident, and 
(iii)  take the measures necessary to prevent further possible incidents or accidents; 
(b) of a breach of any permit condition the operator must immediately— 
(i) 
inform the Environment Agency, and 
(ii)  take the measures necessary to ensure that compliance is restored within the shortest 
possible time; 
(c) of a breach of permit condition which poses an immediate danger to human health or threatens 
to cause an immediate significant adverse effect on the environment, the operator must 
immediately suspend the operation of the activities or the relevant part of it until compliance 
with the permit conditions has been restored. 
4.3.2  Any information provided under condition 4.3.1 (a)(i), or 4.3.1 (b)(i) where the information relates to 
the breach of a limit specified in the permit, shall be confirmed by sending the information listed in 
schedule 5 to this permit within the time period specified in that schedule. 
4.3.3  Where the Environment Agency has requested in writing that it shall be notified when the operator is 
to undertake monitoring and/or spot sampling, the operator shall inform the Environment Agency 
when the relevant monitoring and/or spot sampling is to take place. The operator shall provide this 
information to the Environment Agency at least 14 days before the date the monitoring is to be 
undertaken. 
4.3.4  The Environment Agency shall be notified within 14 days of the occurrence of the following matters, 
except where such disclosure is prohibited by Stock Exchange rules: 
Where the operator is a registered company: 
(a) any change in the operator’s trading name, registered name or registered office address; and 
(b) any steps taken with a view to the operator going into administration, entering into a company 
voluntary arrangement or being wound up. 
Where the operator is a corporate body other than a registered company: 
(a) any change in the operator’s name or address; and 
(b) any steps taken with a view to the dissolution of the operator. 
4.3.5  Where the operator proposes to make a change in the nature or functioning, or an extension of the 
activities, which may have consequences for the environment and the change is not otherwise the 
subject of an application for approval under the Regulations or this permit: 
(a) the Environment Agency shall be notified at least 14 days before making the change; and 
(b) the notification shall contain a description of the proposed change in operation. 
4.3.6  The Environment Agency shall be given at least 14 days notice before implementation of any part of 
the site closure plan. 
4.4  Interpretation 
4.4.1  In this permit the expressions listed in schedule 6 shall have the meaning given in that schedule. 
4.4.2  In this permit references to reports and notifications mean written reports and notifications, except 
where reference is made to notification being made “immediately”, in which case it may be provided 
by telephone 
Permit number       
 01/04/2016 
EPR/UP3038WA/A001 
12 

Schedule 1 – Operations  
Table S1.1 activities 
Activity listed in Schedule  Description of specified 
Limits of specified activity  
1 of the EP Regulations  
activity  
S5.1 A1 (b) 
The incineration of non-
From receipt of waste to emission of exhaust 
hazardous waste in a waste  gas, water treatment plant, Reverse Osmosis 
incineration plant with a 
Plant and disposal of wastes arising.  
capacity of 3 tonnes per 
Waste types and quantities as specified in 
hour or more. 
Table S2.2 of this permit. 
Directly Associated Activities 
Electricity Generation 
Generation of 9.98MWe 
 
electrical power for the 
 
operation of a single steam 
turbine 
Back up electrical generator  For providing emergency 
 
electrical power to the plant 
critical operating systems to 
enable a safe shutdown in 
the event of supply 
interruption.   
Firewater pump 
For providing emergency  
 
fire water in the event of a 
fire and plant supply 
interruption. 
 
 
Table S1.2 Operating techniques 
Description 
Parts 
Date Received 
Application 
Responses to Part B and Appendix 6 of the application form 
Duly Made 
06/02/2015 
and referenced supporting documents. 
Response to RFI dated 
All of response 
06/02/2015  
29/01/2015 
Response to Schedule 5   All of document including Air Quality Assessment Revision 5,  29/06/2015,  
Notice dated 14/05/2015
27/07/2015 
Human Health Risk Assessment July 2015 , plus emails with 
 
 
22/09/2015 
follow up information 
RFI dated 10/07/2015 
All of email 
10/07/2015 
RFI dated 05/08/2015 
All of email  
02/09/2015 
Response to RFI dated 
All of document plus follow up emails 
15/10/2015, 
28/08/2015  
13/11/2015 
 
 
 
 
 
 
 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
13 

Table S1.3 Improvement programme requirements 
Reference 
Requirement 
Date 
IC1 
The Operator shall submit a written report to the Environment Agency on the 
Within 12 months 
implementation of its Environmental Management System and the progress made 
of the date on 
in the certification of the system by an external body or if appropriate submit a 
which waste is 
schedule by which the EMS will be certified. 
first burnt. 
 
IC2 
The  Operator shall submit a written proposal to the Environment Agency to carry 
Within 6 months 
out tests to determine the size distribution of the particulate matter in the exhaust 
of the completion 
gas emissions to air from emission point A1, identifying the fractions within the 
of 
PM10, and PM2.5 ranges. The proposal shall include a timetable for approval by the  commissioning. 
Environment Agency to carry out such tests and produce a report on the results.  
On receipt of written agreement by the Environment Agency to the proposal and 
the timetable, the Operator shall carry out the tests and submit to the Environment 
Agency a report on the results. 
 
IC3 
The Operator shall submit a written report to the Environment Agency on the 
Within 4 months 
commissioning of the installation.  The report shall summarise the environmental 
of the completion 
performance of the plant as installed against the design parameters set out in the 
of 
Application.  The report shall also include a review of the performance of the 
commissioning. 
facility against the conditions of this permit and details of procedures developed 
during commissioning for achieving and demonstrating compliance with permit 
conditions.   
 
IC4 
The Operator shall carry out checks to verify the residence time, minimum 
Within 4 months 
temperature and oxygen content of the exhaust gases in the furnace whilst 
of the completion 
operating under the anticipated most unfavourable operating conditions. The 
of 
results shall be submitted in writing to the Environment Agency. 
commissioning. 
 
IC5 
The Operator shall submit a written report to the Environment Agency describing 
Within 4 months 
the performance and optimisation of the Selective Non Catalytic Reduction 
of the completion 
(SNCR) system and combustion settings to minimise oxides of nitrogen (NOx) 
of 
emissions within the emission limit values described in this permit with the 
commissioning. 
minimisation of nitrous oxide emissions.  The report shall include an assessment 
of the level of NOx and N2O emissions that can be achieved under optimum 
operating conditions. 
 
The report shall also provide details of the optimisation (including dosing rates) for 
the control of acid gases and dioxins 
 
IC6 
The Operator shall carry out an assessment of the impact of emissions to air of 
15 months from 
the following component metals subject to emission limit values, As, Cr.  A report 
commencement 
on the assessment shall be made to the Environment Agency. 
of operations 
 
Emissions monitoring data obtained during the first year of operation shall be used 
to compare the actual emissions with those assumed in the impact assessment 
submitted with the Application. An assessment shall be made of the impact of 
each metal against the relevant EQS/EAL.  In the event that the assessment 
shows that an EQS/EAL can be exceeded, the report shall include proposals for 
further investigative work.   
 
IC7 
The Operator shall submit a written summary report to the Agency to confirm by 
Initial calibration 
the results of calibration and verification testing that the performance of 
report to be 
Continuous Emission Monitors for parameters as specified in Table S3.1 and 
submitted to the 
Table S3.1(a) complies with the requirements of BS EN 14181, specifically the 
Agency within 3 
requirements of QAL1, QAL2 and QAL3. 
months of 
completion of 
commissioning. 
 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
14 

Table S1.3 Improvement programme requirements 
Reference 
Requirement 
Date 
Full summary 
evidence 
compliance 
report to be 
submitted within 
18 months of 
commissioning. 
 
Table S1.4A Pre-operational measures 
Reference 
Pre-operational measures 
PO1 
Prior to the commencement of commissioning, the Operator shall send a summary of 
the site Environment Management System (EMS) to the Environment Agency and 
make available for inspection all documents and procedures which form part of the 
EMS.  The EMS shall be developed in line with the requirements set out in Section 1 of 
How to comply with your environmental permit – Getting the basics right.  
The documents and procedures set out in the EMS shall form the written management 
system referenced in condition 1.1.1 (a) of the permit.  
PO2 
 Prior to the commencement of commissioning, the Operator shall send a report to the 
Environment Agency which will contain a comprehensive review of the options 
available for utilising the heat generated by the waste incineration process in order to 
ensure that it is recovered as far as practicable. The review shall detail any identified 
proposals for improving the recovery and utilisation of waste heat and shall provide a 
timetable for their implementation. 
 
PO3 
Prior to the commencement of commissioning, the Operator shall submit to the 
Environment Agency for approval a protocol for the sampling and testing of incinerator 
bottom ash, char and or liquor for the purposes of assessing its hazard status.  
Sampling and testing shall be carried out in accordance with the protocol as approved. 
PO4 
Prior to the commencement of commissioning; the Operator shall provide a written 
commissioning plan, including timelines for completion, for approval by the 
Environment Agency.  The commissioning plan shall include the expected emissions to 
the environment during the different stages of commissioning, the expected durations 
of commissioning activities and the actions to be taken to protect the environment and 
report to the Environment Agency in the event that actual emissions exceed expected 
emissions.  Commissioning shall be carried out in accordance with the commissioning 
plan as approved. 
PO5 
Prior to the commencement of commissioning, the Operator shall submit a written 
report to the Agency detailing the waste acceptance procedure to be used at the site.  
The waste acceptance procedure shall include the process and systems by which 
wastes unsuitable for incineration at the site will be controlled.   
The procedure shall be implemented in accordance with the written approval from the 
Agency.   
PO6 
After completion of furnace design and at least three calendar months before any 
furnace operation; the operator shall submit a written report to the Agency of the 
details of the computational fluid dynamic (CFD) modelling. The report shall 
demonstrate whether the design combustion conditions comply with the residence time 
and temperature requirements as defined by Chapter IV and Annex VI of the IED. 
PO7 
Prior to the commencement of commissioning, the Operator shall submit a report on 
the baseline conditions of soil and groundwater at the installation.  The report shall 
contain the information necessary to determine the state of soil and groundwater 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
15 

Table S1.4A Pre-operational measures 
Reference 
Pre-operational measures 
contamination so as to make a quantified comparison with the state upon definitive 
cessation of activities provided for in Article 22(3) of the IED.  The report shall contain 
information, supplementary to that already provided in application Site Condition 
Report, needed to meet the information requirements of Article 22(2) of the IED. 
PO8 
The Operator shall submit the written protocol referenced in condition 3.2.4 for the 
monitoring of soil and groundwater for approval by the Environment Agency.  The 
protocol shall demonstrate how the Operator will meet the requirements of Articles 
14(1)(b), 14(1)(e) and 16(2) of the IED.   
The procedure shall be implemented in accordance with the written approval from the 
Agency.   
 
PO9 
At least three months before operation, the Operator shall submit a written report to the 
Environment Agency specifying arrangements for continuous and periodic monitoring 
of emissions to air to comply with Environment Agency guidance notes M1 and M2. 
The report shall include the following: 
•  Plant and equipment details, including accreditation to MCERTS 
•  Methods and standards for sampling and analysis  
•  Details of monitoring locations, access and working platforms 
 
 
 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
16 

Schedule 2 – Waste types, raw materials and fuels 
 
Table S2.1 Raw materials and fuels 
Raw materials and fuel description 
Specification 
RDF  
As per application, EPR Permit 
Application Support Document 
SOL1409HE01 Section 3.5 Raw 
Materials, Table 3.2. 
 
 
Table S2.2 Permitted waste types and quantities for  incineration by gasification plant 
Maximum quantity  The total quantity of waste types that can be accepted at the site shall be 
112,915 tonnes. The total maximum storage of wastes on site will be 3380 
tonnes . 

Waste code 
Description 
19 
Wastes from Waste Management Facilities, Off-site Waste Water Treatment Plants 
and the Preparation of Water Intended for Human Consumption and Water for 
Industrial Use 

19 02 
Wastes from physico/chemical treatments of waste (including dechromatation, 
decyanidation, neutralisation) 
19 02 10 
combustible wastes other than those mentioned in 19 02 08 and 19 02 09 
19 12 
wastes from the mechanical treatment of waste (for example sorting, crushing, 
compacting, pelletising) not otherwise specified 

19 12 10  
combustible waste (refuse derived fuel) 
 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
17 

Schedule 3 – Emissions and monitoring 
 
Table S3.1  Point source emissions to air – emission limits and monitoring requirements 
Emission 
Parameter   
Source 
Limit (including  Reference period 
Monitoring frequency 
Monitoring standard(s) 
point ref. 
unit)  
or method(s) 
& location 
A1 & A2 
Particulate matter 
Gasifier/combuster  30 mg/m3 
½-hr average 
Continuous measurement 
BS EN 14181 and BS 
 
EN 15267-3 
A1 & A2 
Particulate matter 
Gasifier/combuster  10 mg/m3 
daily average 
Continuous measurement 
BS EN 14181 and BS 
 
EN 15267-3 
A1 & A2 
Total Organic Carbon 
Gasifier/combuster  20 mg/m3 
½-hr average 
Continuous measurement 
BS EN 14181 and BS 
(TOC) 
EN 15267-3 
A1 & A2 
Total Organic Carbon 
Gasifier/combuster  10 mg/m3 
daily average 
Continuous measurement 
BS EN 14181 and BS 
(TOC) 
EN 15267-3 
A1 & A2 
Hydrogen chloride 
Gasifier/combuster  60 mg/m3   
½-hr average 
Continuous measurement  
BS EN 14181 and BS 
EN 15267-3 
A1 & A2 
Hydrogen chloride 
Gasifier/combuster  10 mg/m3 
daily average 
Continuous measurement 
BS EN 14181 and BS 
 
EN 15267-3 
A1 & A2 
Hydrogen fluoride 
Gasifier/combuster  2 mg/m3  
periodic over 
Quarterly in first year. Then Bi-
BS ISO 15713 
 
minimum 1-hour 
annual 
period 
 
A1 & A2 
Carbon  monoxide 
Gasifier/combuster  a) 100  mg/m3 
a) ½-hr average 
Continuous measurement 
BS EN 14181 and BS 
EN 15267-3 
 
 
A1 & A2 
Carbon  monoxide 
Gasifier/combuster  50  mg/m3  
daily average 
Continuous measurement 
BS EN 14181 and BS 
 
EN 15267-3 
A1 & A2 
Sulphur dioxide 
Gasifier/combuster  200  mg/m3   
½-hr average 
Continuous measurement  
BS EN 14181 and BS 
EN 15267-3 
A1 & A2 
Sulphur dioxide 
Gasifier/combuster  50 mg/m3  
daily average 
Continuous measurement  
BS EN 14181 and BS 
EN 15267-3 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
18 

Table S3.1  Point source emissions to air – emission limits and monitoring requirements 
Emission 
Parameter   
Source 
Limit (including  Reference period 
Monitoring frequency 
Monitoring standard(s) 
point ref. 
unit)  
or method(s) 
& location 
A1 & A2 
Oxides of nitrogen (NO 
Gasifier/combuster  400  mg/m3   
½-hr  average 
Continuous measurement 
BS EN 14181 and BS 
and NO2 expressed as 
EN 15267-3 
NO2)  
A1 & A2 
Oxides of nitrogen (NO 
Gasifier/combuster  200 mg/m3  
daily average 
Continuous measurement 
BS EN 14181 and BS 
and NO2 expressed as 
EN 15267-3 
NO2)  
A1 & A2 
Cadmium & thallium and  Gasifier/combuster  0.05 mg/m3  
periodic over 
Quarterly in first year. Then Bi-
BS EN 14385 
their compounds (total) 
minimum 30 
annual 
minute, maximum 
8 hour period 
A1 & A2 
Mercury and its 
Gasifier/combuster  0.05 mg/m3 
periodic over 
Quarterly in first year. Then Bi-
BS EN 13211 
compounds  
minimum 30 
annual 
minute, maximum 
8 hour period 
A1 & A2 
Sb, As, Pb, Cr, Co, Cu, 
Gasifier/combuster  0.5 mg/m3 
periodic over 
Quarterly in first year. Then Bi-
BS EN 14385 
Mn, Ni and V and their 
minimum 30 
annual 
compounds (total)  
minute, maximum 
8 hour period 
A1 & A2 
Ammonia (NH3)  
Gasifier/combuster  10 mg/m3 
½-hr  average and 
Continuous where CEM 
BS EN 14181 and BS 
/ or daily average 
installed. 
EN 15267-3 
 
 
 
 
A1 & A2 
Dioxins / furans (I-TEQ) 
Gasifier/combuster  0.1 ng/m3 
periodic over 
Quarterly in first year. Then Bi-
BS EN 1948 Parts 1, 2 
minimum 6 hours, 
annual 
and 3 
maximum 8 hour 
period 
A1 & A2 
Dioxins / furans (WHO-
Gasifier/combuster  - 
periodic over 
Quarterly in first year. Then Bi-
BS EN 1948 Parts 1, 2 
TEQ Humans / 
minimum 6 hours, 
annual 
and 3 
Mammals)  
maximum 8 hour 
period 
A1 & A2 
Dioxins / furans (WHO-
Gasifier/combuster  - 
periodic over 
Quarterly in first year. Then Bi-
BS EN 1948 Parts 1, 2 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
19 

Table S3.1  Point source emissions to air – emission limits and monitoring requirements 
Emission 
Parameter   
Source 
Limit (including  Reference period 
Monitoring frequency 
Monitoring standard(s) 
point ref. 
unit)  
or method(s) 
& location 
TEQ Fish)  
minimum 6 hours, 
annual 
and 3 
maximum 8 hour 
period 
A1 & A2 
Dioxins / furans (WHO-
Gasifier/combuster  - 
periodic over 
Quarterly in first year. Then Bi-
BS EN 1948 Parts 1, 2 
TEQ Birds)  
minimum 6 hours, 
annual 
and 3 
maximum 8 hour 
period 
A1 & A2 
Dioxin-like PCBs (WHO-
Gasifier/combuster  - 
periodic over 
Quarterly in first year. Then Bi-
BS EN 1948-4 
TEQ Humans / 
minimum 6 hours, 
annual 
Mammals) 
maximum 8 hour 
period 
A1& A2 
Dioxin-like PCBs (WHO-
Gasifier/combuster  - 
periodic over 
Quarterly in first year. Then Bi-
BS EN 1948-4 
TEQ  Fish) 
minimum 6 hours, 
annual 
maximum 8 hour 
period 
A1 & A2 
Dioxin-like PCBs (WHO-
Gasifier/combuster  - 
periodic over 
Quarterly in first year. Then Bi-
BS EN 1948-4 
TEQ  Birds) 
minimum 6 hours, 
annual 
maximum 8 hour 
period 
A1 & A2 
Specific individual poly-
Gasifier/combuster  - 
periodic over 
Quarterly in first year. Then Bi-
BS ISO 11338 Parts 1 
cyclic aromatic 
minimum 6 hours, 
annual 
and 2. 
hydrocarbons (PAHs), as 
maximum 8 hour 
specified in Schedule 6. 
period 
 
 
 
 
 
 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
20 

Table S3.1(a)  Point source emissions to air during abnormal operation of incineration plant – emission limits and monitoring requirements 
Emission 
Parameter   
Source 
Limit (including 
Reference period 
Monitoring 
Monitoring standard or 
point ref. & 
unit)  
frequency 
method 
location 
A1& A2 
Particulate matter 
Gasifier/combuster  150 mg/m3   
½-hr average 
Continuous 
[BS EN 14181 and BS EN 
measurement  
15267-3 
 
A1& A2 
Total Organic 
Gasifier/combuster  20 mg/m3  
½-hr average 
Continuous 
BS EN 14181 and BS EN 15267-
Carbon (TOC) 
measurement  

 
A1& A2 
Carbon  monoxide  Gasifier/combuster  100  mg/m3 
½-hr average 
Continuous 
BS EN 14181 and BS EN 15267-
measurement  

 
A1& A2 
SO2 
Gasifier/combuster  79  mg/m3 
½-hr average 
Continuous 
BS EN 14181 and BS EN 15267-
measurement  

 
 
Table S3.2 Point Source emissions to water (other than sewer) and land – emission limits and monitoring requirements 
Emission point ref. & 
Source 
Parameter   
Limit (incl. 
Reference Period 
Monitoring 
Monitoring 
location 
unit) 
frequency 
standard or method 
W1 
Surface water via 
No parameters set 
Uncontaminated  - 


interceptor 
surface water 
free of visible oil 
and grease 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
21 

 
Table S3.3 Point source emissions to sewer, effluent treatment plant or  other transfers off-site– emission limits and monitoring requirements 
Emission point ref. & 
Source 
Parameter   
Limit (incl. 
Reference period 
Monitoring 
Monitoring 
location 
Unit) 
frequency 
standard or 
method 

S1  as on plan in 
Water Treatment plant 
No parameter set  
No limit set 



Schedule 7 
permeate, cooling waters 
& boiler blowdown 
 
 
Table S3.4  Process monitoring requirements 
Emission point reference 
Parameter 
Monitoring 
Monitoring standard  Other specifications  
or source or description 
frequency  
or method  
of point of measurement 
A1 & A2 As identified in the 
Wind Speed and Direction 
Continuous 
Anemometer  
 
Application 
A1 & A2 Location close to 
Temperature (° C) 
Continuous 
Traceable to national 
As agreed in writing with the Agency. 
the Combustion Chamber 
standards 
inner wall or as identified 
and justified in Application. 
A1 & A2 
Exhaust gas temperature 
Continuous 
Traceable to national 
As agreed in writing with the Agency. 
standards 
A1 & A2 
Exhaust gas pressure 
Continuous 
Traceable to national 
As agreed in writing with the Agency. 
standards 
A1 & A2 
Exhaust gas oxygen content 
Continuous 
BS EN 15267-3 
 
BS EN 14181 
A1 & A2 
Exhaust gas water vapour content 
Continuous 
BS EN 15267-3 
Unless gas is dried before analysis of 
BS EN 14181 
emissions. 
 
 
 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
22 

Table S3.5  Residue quality 
Emission point reference or 
Parameter 
Limit 
Monitoring 
Monitoring 
Other 
source or description of 
frequency  
standard or 
specifications  
point of measurement 
method * 
 
Bottom Ash 
TOC  
<3% 
Monthly in the first 
Environment 

Agency 
 
year of operation. 
Then Quarterly 
Guidance, ‘TGN 
M4 – Guidelines 
for Ash Sampling 
and Analysis’ 
Bottom Ash 
Metals (Antimony, Cadmium, 

Monthly in the first 
Environment 

Thallium, Mercury, Lead, 
year of operation. 
Agency 
Chromium, Copper, 
Then Quarterly 
Guidance, ‘TGN 
Manganese, Nickel, Arsenic, 
M4 – Guidelines 
Cobalt, Vanadium, Zinc) and 
for Ash Sampling 
their compounds, dioxins/furans 
and Analysis’ 
and dioxin-like PCBs.   
Bottom Ash 
Total soluble fraction and 

Before use of a new 
Environment 

metals (Antimony, Cadmium, 
disposal or recycling 
Agency 
Thallium, Mercury, Lead, 
route 
Guidance, ‘TGN 
Chromium, Copper, 
M4 – Guidelines 
Manganese, Nickel, Arsenic, 
for Ash Sampling 
Cobalt, Vanadium, Zinc) 
and Analysis’ 
soluble fractions 
APC Residues 
Metals (Antimony, Cadmium, 

Monthly in the first 
Environment 

Thallium, Mercury, Lead, 
year of operation. 
Agency 
Chromium, Copper, 
Then Quarterly 
Guidance, ‘TGN 
Manganese, Nickel, Arsenic, 
M4 – Guidelines 
Cobalt, Vanadium, Zinc) and 
for Ash Sampling 
their compounds, dioxins/furans 
and Analysis’ 
and dioxin-like PCBs.   
APC Residues 
Total soluble fraction and 
-- 
Before use of a new 
Environment 

metals (Antimony, Cadmium, 
disposal or recycling 
Agency 
Thallium, Mercury, Lead, 
route 
Guidance, ‘TGN 
Chromium, Copper, 
M4 – Guidelines 
Manganese, Nickel, Arsenic, 
for Ash Sampling 
Cobalt, Vanadium, Zinc) 
and Analysis’ 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
23 

Table S3.5  Residue quality 
Emission point reference or 
Parameter 
Limit 
Monitoring 
Monitoring 
Other 
source or description of 
frequency  
standard or 
specifications  
point of measurement 
method * 
 
soluble fractions 

Or other equivalent standard as agreed in writing with the Environment Agency.
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
24 

Schedule 4 – Reporting 
Parameters, for which reports shall be made, in accordance with conditions of this permit, are listed below. 
Table S4.1 Reporting of monitoring data 
Parameter 
Emission or monitoring 
Reporting period  Period begins 
point/reference 
Emissions to air 
A1 & A2 
Quarterly 
1 Jan, 1 Apr, 1 Jul 
Parameters as required by condition 
and 1 Oct 
3.5.1 
TOC  
Bottom Ash 
Quarterly (but 
1 Jan, 1 Apr, 1 Jul 
Parameters as required by condition 
monthly for the 
and 1 Oct 
3.5.1 
first year of 
operation) 
Metals (Antimony, Cadmium, 
Bottom Ash 
Quarterly (but 
1 Jan, 1 Apr, 1 Jul 
Thallium, Mercury, Lead, 
monthly for the 
and 1 Oct 
Chromium, Copper, Manganese, 
first year of 
Nickel, Arsenic, Cobalt, Vanadium, 
operation) 
Zinc) and their compounds, 
dioxins/furans and dioxin-like PCBs  
Parameters as required by condition 
3.5.1  
Total soluble fraction and metals 
Bottom Ash 
Before use of a 
 
(Antimony, Cadmium, Thallium, 
new disposal or 
Mercury, Lead, Chromium, Copper, 
recycling route 
Manganese, Nickel, Arsenic, 
Cobalt, Vanadium, Zinc) soluble 
fractions 
Parameters as required by condition 
3.5.1 
Metals (Antimony, Cadmium, 
APC Residues 
Quarterly (but 
1 Jan, 1 Apr, 1 Jul 
Thallium, Mercury, Lead, 
monthly for the 
and 1 Oct 
Chromium, Copper, Manganese, 
first year of 
Nickel, Arsenic, Cobalt, Vanadium, 
operation) 
Zinc) and their compounds, 
dioxins/furans and dioxin-like PCBs 
Parameters as required by condition 
3.5.1   
Total soluble fraction and metals 
APC Residues 
Before use of a 
 
(Antimony, Cadmium, Thallium, 
new disposal or 
Mercury, Lead, Chromium, Copper, 
recycling route 
Manganese, Nickel, Arsenic, 
Cobalt, Vanadium, Zinc) soluble 
fractions 
Parameters as required by condition 
3.5.1   
Functioning and monitoring of the 
 
Annually  
1 Jan 
incineration plant as required by 
condition 4.2.2 
 
 
 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
25 

Table S4.2: Annual production/treatment 
Parameter 
Units  
Total waste Incinerated  
tonnes 
Electrical energy produced 
KWhrs 
Electrical energy exported 
KWhrs 
Electrical energy used on installation  
KWhrs 
Waste heat utilised by the installation 
KWhrs 
 
Table S4.3 Performance parameters 
Parameter 
Frequency of assessment 
Units 
Electrical energy exported, imported 
Quarterly 
KWhrs / tonne of 
and used at the installation 
waste incinerated  
Natural gas consumption 
Quarterly 
Kgs / tonne of waste 
incinerated  
Mass of Bottom Ash produced 
Quarterly 
Kgs / tonne of waste 
incinerated  
Mass of APC residues produced 
Quarterly 
Kgs / tonne of waste 
incinerated  
 Urea consumption 
Quarterly 
Kgs / tonne of waste 
incinerated  
Activated Carbon consumption 
Quarterly 
Kgs / tonne of waste 
incinerated  
Lime consumption 
Quarterly 
Kgs / tonne of waste 
incinerated  
Water consumption 
Quarterly 
Kgs / tonne of waste 
incinerated  
Periods of abnormal operation 
Quarterly 
No of occasions and 
cumulative hours for 
current calendar year 
for each line. 
 
Table S4.4 Reporting forms 
Media/parameter 
Reporting format 
Date of form 
Air 
Form air 1 or other form as agreed in writing by the 
10/03/2016 
Environment Agency  
Water usage 
Form water usage 1 or other form as agreed in writing by  10/03/2016 
the Environment Agency 
Energy usage 
Form energy 1 or other form as agreed in writing by the 
10/03/2016 
Environment Agency 
Other performance 
Form performance 1 or other form as agreed in writing 
10/03/2016 
indicators 
by the Environment Agency 
 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
26 

Schedule 5 – Notification  
These pages outline the information that the operator must provide. 
Units of measurement used in information supplied under Part A and B requirements shall be appropriate to 
the circumstances of the emission. Where appropriate, a comparison should be made of actual emissions 
and authorised emission limits. 
If any information is considered commercially confidential, it should be separated from non-confidential 
information, supplied on a separate sheet and accompanied by an application for commercial confidentiality 
under the provisions of the EP Regulations. 
Part A  
Permit Number 
 
Name of operator 
 
Location of Facility 
 
Time and date of the detection  
 
 
(a) Notification requirements for any malfunction, breakdown or failure of equipment or techniques, 
accident, or emission of a substance not controlled by an emission limit which has caused, is 
causing or may cause significant pollution 

To be notified within 24 hours of detection 
Date and time of the event 
 
Reference or description of the 
 
location of the event  
Description of where any release 
 
into the environment took place 
Substances(s) potentially released   
Best estimate of the quantity or 
 
rate of  release of substances 
Measures taken, or intended to be   
taken, to stop any emission 
Description of the failure or 
 
accident. 
 
(b) Notification requirements for the breach of a limit 
To be notified within 24 hours of detection unless otherwise specified below 
Emission point reference/ source 
 
Parameter(s) 
 
Limit 
 
Measured value and uncertainty 
 
Date and time of monitoring 
 
Measures taken, or intended to be   
taken, to stop the emission 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
27 

 
Time periods for notification following detection of a breach of a limit 
Parameter 
Notification period 
 
 
 
 
 
 
 
(c) Notification requirements for the detection of any significant adverse environmental effect 
To be notified within 24 hours of detection 
Description of where the effect on 
 
the environment was detected 
Substances(s) detected 
 
Concentrations of substances 
 
detected 
Date of monitoring/sampling 
 
 
Part B – to be submitted as soon as practicable 
Any more accurate information on the matters for 
 
notification under Part A. 
Measures taken, or intended to be taken, to prevent 
 
a recurrence of the incident 
Measures taken, or intended to be taken, to rectify, 
 
limit or prevent any pollution of the environment 
which has been or may be caused by the emission 
The dates of any unauthorised emissions from the 
 
facility in the preceding 24 months. 
 
Name* 
 
Post 
 
Signature 
 
Date 
 
* authorised to sign on behalf of the operator 
 
 
 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
28 

Schedule 6 – Interpretation 
 “abatement equipment” means that equipment dedicated to the removal of polluting substances from 
releases from the installation to air or water media. 
“abnormal operation” means any technically unavoidable stoppages, disturbances, or failures of the abatement plant or 
the measurement devices , during which the emissions into the air and the discharges of waste water may exceed the 
prescribed emission limit values 
 “accident” means an accident that may result in pollution. 
“APC residues” means air pollution control residues  
 “application” means the application for this permit, together with any additional information supplied by the 
operator as part of the application and any response to a notice served under Schedule 5 to the EP 
Regulations. 
 “authorised officer” means any person authorised by the Environment Agency under section 108(1) of The 
Environment Act 1995 to exercise, in accordance with the terms of any such authorisation, any power 
specified in section 108(4) of that Act. 
 “background concentration” means such concentration of that substance as is present in:  
• 
for emissions to surface water, the surface water quality up-gradient of the site; or  
• 
for emissions to sewer, the surface water quality up-gradient of the sewage treatment works discharge.  
“bottom ash” means ash falling through the grate  
“CEM” Continuous emission monitor 
“CEN” means Commité Européen de Normalisation “bi-annual” means twice per year with at least five 
months between tests;  
 “daily average”  for releases of substances to air means the average of valid half-hourly averages over a 
calendar day during normal operation.  
“dioxin and furans” means polychlorinated dibenzo-p-dioxins and polychlorinated dibenzofurans.  
“disposal”. Means any of the operations provided for in Annex I to Directive 2008/98/EC of the European 
Parliament and of the Council on waste.  
 “emissions to land” includes emissions to groundwater. 
“EP Regulations” means The Environmental Permitting (England and Wales) Regulations SI 2010 No.675 
and words and expressions used in this permit which are also used in the Regulations have the same 
meanings as in those Regulations. 
“emissions of substances not controlled by emission limits” means emissions of substances to air, water or 
land from the activities, either from the emission points specified in schedule 3 or from other localised or 
diffuse sources, which are not controlled by an emission or background concentration limit. 
“groundwater” means all water, which is below the surface of the ground in the saturation zone and in direct 
contact with the ground or subsoil.  
“hazardous property” has the meaning given in Schedule 3 of the Hazardous Waste (England and Wales) 
Regulations 2005 No.894 and the Hazardous Waste (Wales) Regulations 2005 No. 1806 (W.138). 
 “incineration line” means all of the incineration equipment related to a common discharge to air location. 
 “Industrial Emissions Directive” means DIRECTIVE 2010/75/EU OF THE EUROPEAN PARLIAMENT AND 
OF THE COUNCIL of 24 November 2010 on industrial emissions 
 “ISO” means International Standards Organisation. 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
29 

“LOI” means loss on ignition a technique used to determine the combustible material by heating the ash 
residue to a high temperature 
 “MCERTS” means the Environment Agency’s Monitoring Certification Scheme. 
“PAH” means Poly-cyclic aromatic hydrocarbon, and comprises Anthanthrene, Benzo[a]anthracene, 
Benzo[b]fluoranthene, Benzo[k]fluoranthene, Benzo[b]naph(2,1-d)thiophene, Benzo[c]phenanthrene, 
Benzo[ghi]perylene, Benzo[a]pyrene, Cholanthrene, Chrysene, Cyclopenta[c,d]pyrene, 
Dibenzo[ah]anthracene, Dibenzo[a,i]pyrene Fluoranthene, Indo[1,2,3-cd]pyrene, Naphthalene 
“PCB” means Polychlorinated Biphenyl. Dioxin-like PCBs are the non-ortho and mono-ortho PCBs listed in 
the table below. 
Pests” means Birds, Vermin and Insects. 
 “quarter” means a calendar year quarter commencing on 1 January, 1 April, 1 July or 1 October. 
 “recovery” means any of the operations provided for in Annex II to Directive 2008/98/EC of the European 
Parliament and of the Council on waste.  
“shut down” is any period where the plant is being returned to a non-operational state and there is no waste 
being burned as described in the application or agreed in writing with the Environment Agency. 
“start up” is any period, where the plant has been non-operational, after igniting the auxiliary burner until 
waste has been fed to the plant to initiate steady-state conditions as described in the application or agreed in 
writing with the Environment Agency.  
“TOC” means Total Organic Carbon. In respect of releases to air, this means the gaseous and vaporous 
organic substances, expressed as TOC. In respect of Bottom Ash, this means the total carbon content of all 
organic species present in the ash (excluding carbon in elemental form). 
 “Waste code” means the six digit code referable to a type of waste in accordance with the List of Wastes 
(England)Regulations 2005, or List of Wastes (Wales) Regulations 2005, as appropriate, and in relation to 
hazardous waste, includes the asterisk.  
 “Waste Framework Directive” or “WFD” means Waste Framework Directive 2008/98/EC of the European 
Parliament and of the Council on waste  
Where a minimum limit is set for any emission parameter, for example pH, reference to exceeding the limit 
shall mean that the parameter shall not be less than that limit. 
“year” means calendar year ending 31 December. 
Unless otherwise stated, any references in this permit to concentrations of substances in emissions into air 
means:  
in relation to gases from incineration plants other than those burning waste oil, the concentration in dry 
air at temperature of 273K, at a pressure of 101.3 kPa and with an oxygen content of 11% dry 
 
 
 
 
 
 
 
 
 
 
 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
30 

For dioxins/furans and dioxin-like PCBs the determination of the toxic equivalence concentration (I-TEQ, 
& WHO-TEQ for dioxins/furans, WHO-TEQ for dioxin-like PCBs) stated as a release limit and/ or 
reporting requirement, the mass concentrations of the following congeners have to be multiplied with 
their respective toxic equivalence factors before summing. When reporting on measurements of 
dioxins/furans and dioxin-like PCBs, the toxic equivalence concentrations should be reported as a range 
based on: all congeners less than the detection limit assumed to be zero as a minimum, and all 
congeners less then the detection limit assumed to be at the detection limit as a maximum. However the 
minimum value should be used when assessing compliance with the emission limit value in table S3.1. 
 
 
 
TEF schemes for dioxins and furans 
Congener 
I-TEF 
WHO-TEF 
1990 
2005 
1997/8 
 
 
Humans / 
Fish 
Birds 
Mammals 
Dioxins 
 
 
 
 
2,3,7,8-TCDD 




1,2,3,7,8-PeCDD 
0.5 



1,2,3,4,7,8-HxCDD 
0.1 
0.1 
0.5 
0.05 
1,2,3,6,7,8-HxCDD 
0.1 
0.1 
0.01 
0.01 
1,2,3,7,8,9-HxCDD 
0.1 
0.1 
0.01 
0.1 
1,2,3,4,6,7,8-HpCDD 
0.01 
0.01 
0.001 
<0.001 
OCDD 
0.001 
0.0003 


Furans 
 
 
 
 
2,3,7,8-TCDF 
0.1 
0.1 
0.05 

1,2,3,7,8-PeCDF 
0.05 
0.03 
0.05 
0.1 
2,3,4,7,8-PeCDF 
0.5 
0.3 
0.5 

1,2,3,4,7,8-HxCDF 
0.1 
0.1 
0.1 
0.1 
1,2,3,7,8,9-HxCDF 
0.1 
0.1 
0.1 
0.1 
1,2,3,6,7,8-HxCDF 
0.1 
0.1 
0.1 
0.1 
2,3,4,6,7,8-HxCDF 
0.1 
0.1 
0.1 
0.1 
1,2,3,4,6,7,8_HpCDF 
0.01 
0.01 
0.01 
0.01 
1,2,3,4,7,8,9-HpCDF 
0.01 
0.01 
0.01 
0.01 
OCDF 
0.001 
0.0003 
0.0001 
0.0001 
 
 
TEF schemes for dioxin-like PCBs 
Congener 
WHO-TEF 
2005 
1997/8 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
31 

 
Humans / 
Fish 
Birds 
mammals 
Non-ortho PCBs 
 
 
 
3,4,4',5-TCB (81) 
0.0001 
0.0005 
0.1 
3,3',4,4'-TCB (77) 
0.0003 
0.0001 
0.05 
3,3',4,4',5 - PeCB (126) 
0.1 
0.005 
0.1 
3,3',4,4',5,5'-HxCB(169) 
0.03 
0.00005 
0.001 
Mono-ortho PCBs 
 
 
 
2,3,3',4,4'-PeCB (105) 
0.00003 
<0.000005 
0.0001 
2,3,4,4',5-PeCB (114) 
0.00003 
<0.000005 
0.0001 
2,3',4,4',5-PeCB (118) 
0.00003 
<0.000005 
0.00001 
2',3,4,4',5-PeCB (123) 
0.00003 
<0.000005 
0.00001 
2,3,3',4,4',5-HxCB (156) 
0.00003 
<0.000005 
0.0001 
2,3,3',4,4',5'-HxCB (157) 
0.00003 
<0.000005 
0.0001 
2,3',4,4',5,5'-HxCB (167) 
0.00003 
<0.000005 
0.00001 
2,3,3',4,4',5,5'-HpCB (189) 
0.00003 
<0.000005 
0.00001 
 
 
 
 
 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
32 


Schedule 7 – Site plan 
 
 
END OF PERMIT 
 
Permit number                                                                                01/04/2016 
EPR/UP3038WA/A001 
33 

Document Outline