This is an HTML version of an attachment to the Freedom of Information request 'A new pedestrian bridge for Harringay railway station?'.


 
 
 
 
Mr Clive Carter 
Network Rail  
By email: request-509870-
Freedom of Information 
xxxxxxxx@xxxxxxxxxxxxxx.xxx 
The Quadrant  
 
Elder Gate 
Milton Keynes  
MK9 1EN 
 
01908 782405 
E xxx@xxxxxxxxxxx.xx.xx  
 
 
7th September 2018 
 
 
Dear Mr Carter 
 
Information request  
Reference number: FOI2018/01095 
 
Thank you for your email of 14th August 2018, in which you requested the following 
information: 
 
ARE there any plans by Network Rail, or any other body, to replace the 
current pedestrian bridge that runs past Harringay railway station please? 
 
The present unhappy bridge runs between two cul-de-sacs, viz, the ends of 
Quernmore Road N4, Stroud Green Ward and Railway Approach N4, 
Harringay Ward. 
 
► The easternmost end is unreasonably steep for everyone including the 
elderly, infirm or disabled ► The steepness is a problem year-round, but at no 
time more so than in winter ► It is overly steep for any wheeled devices 
including prams, scooters, bicycles, wheelchairs or wheeled suitcases and 
shopping baskets ► Both ends of the bridge are also too narrow for most of 
these wheeled devices ► The moped-blocking fences at either end are crude 
and frustrate more than the intended ► Also, there is no separation anywhere 
for bicycles and pedestrians 
 
This is one of only three main railway line crossing points between Finsbury 
Park and Hornsey stations – the others being Endymion Road and a 
pedestrian bridge at Oxford Road. 
 
If there any plans of any kind, please supply any relevant information. 

 
 
Network Rail Infrastructure Limited Registered Office: Network Rail, One Eversholt Street, London, NW1 2DN Registered in England and Wales No. 2904587 www.networkrail.co.uk 
 
 

 
I have processed your request under the Environmental Information Regulations 
2004 (EIR) as the information requested is environmental according to the definition 
in regulation 2(c) of the EIR. Please note section 39 of the Freedom of Information 
Act 2000 (FOIA) exempts environmental information from the FOIA, but requires us 
to consider it under the EIR). 
 
I can confirm that we hold the information you requested. Further to an optioneering 
process considering several possibilities to improve the footbridge at Harringay 
Station, a final option was selected between the time of your request and the date of 
this letter. This will now be progressed throughout the rest of 2018, with a view to the 
chosen improvements being made by the end of Control Period 6 (CP6), between 
2019 and 2024. 
 
To further assist you, I have attached an extract, ‘FOI201801095 Option 2’ taken 
from a report titled ‘Harringay Station Footbridge ECM1/22 – Optioneering Repair 
Strategy for ECM1/22’
, completed in April 2018.  This extract provides the general 
outlay of the chosen option, showing the intended improvement works for this 
footbridge. Please note that some aspects of this option could be subject to 
amendment during the more specific planning stages, which can now take place on 
the basis that this option is being progressed. 
 
I hope the information provided in this response is helpful. If you have any enquiries 
about this response, please contact me in the first instance at xxx@xxxxxxxxxxx.xx.xx 
or on 01908 782405.  Details of your appeal rights are below. 
 
Please remember to quote the reference number at the top of this letter in all future 
communications. 
 
Yours sincerely 
 
Emma Meadows 
Information Officer 
 
The information supplied to you continues to be protected by copyright. You are free 
to use it for your own purposes, including for private study and non-commercial 
research, and for any other purpose authorised by an exception in current copyright 
law. Documents (except photographs) can also be used in the UK without requiring 
permission for the purposes of news reporting. Any other re-use, for example 
commercial publication, would require the permission of the copyright holder. Please 
contact me if you wish to re-use the information and need to seek the permission of 
the copyright holder.  
 
 

Network Rail Infrastructure Limited Registered Office: Network Rail, 2nd Floor, One Eversholt Street, London, NW1 2DN Registered in England and Wales No. 2904587 www.networkrail.co.uk 
 

 
 
Appeal Rights 
If you are unhappy with the way your request has been handled and wish to make a 
complaint or request a review of our decision, please write to the FOI Compliance 
and Appeals Manager at Network Rail, Freedom of Information, The Quadrant, Elder 
Gate, Milton Keynes, MK9 1EN, or by email at xxx@xxxxxxxxxxx.xx.xx. Your request 
must be submitted within 40 working days of receipt of this letter.  
 
If you are not content with the outcome of the internal review, you have the right to 
apply directly to the Information Commissioner for a decision.  The Information 
Commissioner can be contacted at: 
 