Adrian,

My understanding is that any application to discharge or partially discharge a requirement under the DCO is not subject to the Planning Fee Regulations and therefore there is no application fee payable. In that respect it is therefore the S106 that provides the means by which the LPA can recover the cost of dealing with the applications.

As you will appreciate from our meetings, it is very difficult, at this stage to identify what the costs will actually be, without knowing how many applications will be submitted and the amount of work, consultations, negotiations etc. required in each case. Based on your Stage Reporting spreadsheet and my own estimates I conclude that there could potentially be around 300 individual discharge submissions. The table attached is based on this assumption. The table shows the hourly rate for each officer/grade likely to be involved in the discharge process and this includes all relevant on-costs including car allowances, recharges to other council teams e.g. legal team, financial services, IT support etc.    

I hope Halite will be able to accept this figure as a “starter for 10” which can be refined as we go forward and are able to get more clarity on the amount and nature of the discharge applications as the development progresses.

Regards  

From: adrian.smith halite.net [mailto:[email address]]
Sent: 11 October 2017 13:50
To: Thow, David <[email address]>
Cc: colin.harding halite.net <[email address]>
Subject: Fwd: RE: Preesall UGS Section 106 Obligations

Dear David,

I will aim to call you later in the week to discuss progress with estimating fees and rates for managing discharge applications and if convenient with you, come to your office next week to discuss the details. Can I suggest either Monday 16th (am) or Friday 20th (am/pm).

If you do have something you are able to share this week I would appreciate the opportunity to review prior to the proposed meeting.

Kind regards

Adrian

Adrian Smith

Halite Energy Group Limted

---------- Original Message ----------
From: "adrian.smith halite.net" <[email address]>
To: "Thow, David" <[email address]>
Cc: "colin.harding halite.net" <[email address]>
Date: October 4, 2017 at 4:41 AM
Subject: RE: Preesall UGS Section 106 Obligations

Dear David,

Thank you for the spreadsheets which we have reviewed and have no further comments and look forward to receiving the proposed fees and rates.

Kind Regards

Adrian

Adrian Smith

Halite Energy Group Limited

On October 3, 2017 at 7:04 AM "Thow, David" <[email address]> wrote:

Adrian,

 

Please find attached amended table – this one recognises the 15 stages as set out in the latest Stages doc (September 17)

 

Regards

 

David Thow
Head of Planning Services
Wyre Council

[email address]
01253 887287
Civic Centre, Breck Road, Poulton-le-Fylde, Lancashire, FY6 7PU

cid:image001.png@01D342A4.5D3042B0

cid:image002.png@01D342A4.5D3042B0

cid:image003.png@01D342A4.5D3042B0

cid:image004.png@01D342A4.5D3042B0

 

From: adrian.smith halite.net [mailto:[email address]]
Sent: 03 October 2017 10:02
To: Thow, David <
[email address]>
Subject: RE: Preesall UGS Section 106 Obligations

 

Dear David,

Thank you for the note which I will share with the team and get back to you.

Kind Regards

Adrian

Adrian Smith

Halite Energy Group Limited

On October 3, 2017 at 3:40 AM "Thow, David" <[email address]> wrote:

Adrian,

 

I am currently working on calculating a rough estimate for the fees that will be payable and have produced, as a starting point, the attached table which shows the requirements, and parts thereof which require discharge as well as those which will require compliance and will therefore need to be monitored. I have also indicated how many submissions may potentially be required in respect of each requirement.

 

Can you please have a look and confirm whether you agree.

 

Regards

 

David Thow
Head of Planning Services
Wyre Council

[email address]
01253 887287
Civic Centre, Breck Road, Poulton-le-Fylde, Lancashire, FY6 7PU

 

cid:image001.png@01D342A4.5D3042B0

cid:image002.png@01D342A4.5D3042B0

cid:image003.png@01D342A4.5D3042B0

cid:image004.png@01D342A4.5D3042B0

 

The Wyre Council email disclaimer can be found at www.wyre.gov.uk/disclaimer.

 

Be prepared for flooding - Simple steps you can take now that could make all the difference in a flood

Nominations for Wyre Business Awards 2017 - Wyre Awards

 

 

 

 

From: adrian.smith halite.net [mailto:[email address]]
Sent: 02 October 2017 15:41
To: Thow, David <
[email address]>
Cc: colin.harding halite.net <
[email address]>
Subject: Preesall UGS Section 106 Obligations

 

Dear David,

I was hoping to speak to you today as a follow up to our recent meeting, to see if there was any additional information you required to assist in pulling together the rates and fees for the 9th October.

There is an option to copy over some of the information/reports that will be submitted for approval on the understanding that there is no commitment for Wyre Borough Council to process until the above rates/fees have been agreed. Would this be of help to you?

For information, we met with Jonathan Haine on the 29th and have arranged to meet Glenn Robinson from LCC's Highways Team in a couple of weeks to progress the Section 278 obligations.

Do not hesitate to contact me if you require any additional information.

Kind Regards

Adrian

Adrian Smith

Halite Energy Group Limited



Email secured by Check Point



Email secured by Check Point